Skeena Resources has secured a US$750 million financing package from Orion Resource Partners to advance its Eskay Creek Gold-Silver Project. The funding includes a US$100 million equity investment, US$200 million gold stream, US$350 million senior secured loan, and US$100 million cost over-run facility. This financing is structured to provide flexibility and certainty, allowing the project to proceed efficiently towards production, targeted for H1 2027. The package exceeds the project's estimated capital expenditures of US$528 million. Key timelines include finalizing permits by end-2025, starting full-scale construction in 2026, and commencing production in 2027. The investment aims to deliver significant economic benefits to the local community, including potential contracts worth C$700 million to Tahltan businesses and creating over 800 direct jobs.