Pekat Unit Bags RM21.79mil Job for Earthing and Lightning Protection Systems

Pekat Group Bhd's sub-subsidiary Pekat E&LP Sdn Bhd has secured an award from Gamuda Engineering Sdn Bhd for the construction of earthing and lightning protection systems in Rawang, Selangor for RM21.79mil.
In a filing with Bursa Malaysia, the group said the contract commenced on July 1, 2024. The trade completion data will be on Sept 30, 2025, and the main contract substantial completion date will be on Feb 27, 2026.