Iris Energy has increased its installed self-mining capacity by 33% to 28 EH/s following the energization of its Childress Phase 3 substation. The company is on track to reach 31 EH/s this month, with sufficient miner inventory on-site and four data center buildings already operational. The remaining two data centers are expected to complete internal fit-out this month.The company has accelerated its expansion target to 50 EH/s and 810MW of data centers from H2 2025 to H1 2025. This growth is supported by Childress Phase 4 & 5 development (+300MW) with ongoing earthworks, site teams capable of constructing 50MW monthly, and previously secured S21 Pro miners at $18.9/TH. The company maintains a competitive position with an estimated all-in cash cost per Bitcoin of ~$29,000, supported by best-in-class fleet efficiency and low electricity costs.
Iris Energy has increased its installed self-mining capacity by 33% to 28 EH/s following the energization of its Childress Phase 3 substation. The company is on track to reach 31 EH/s this month, with sufficient miner inventory on-site and four data center buildings already operational. The remaining two data centers are expected to complete internal fit-out this month.The company has accelerated its expansion target to 50 EH/s and 810MW of data centers from H2 2025 to H1 2025. This growth is supported by Childress Phase 4 & 5 development (+300MW) with ongoing earthworks, site teams capable of constructing 50MW monthly, and previously secured S21 Pro miners at $18.9/TH. The company maintains a competitive position with an estimated all-in cash cost per Bitcoin of ~$29,000, supported by best-in-class fleet efficiency and low electricity costs.
Iris Energy在其Childress Phase 3变电站投入使用后,已将自挖矿总能力提升33%至28 EH/s。该公司预计本月将达到31 EH/s,现场拥有足够的矿机库存,并且已有四座IDC概念建筑投入运营。其余两座IDC概念预计本月完成内部装修。该公司已将扩张目标从2025年下半年提前至2025年上半年,计划达到50 EH/s和810MW的IDC概念。这一增长得益于Childress Phase 4 & 5的开发(+300MW),正在进行的土木工程,能够每月建设50MW的现场团队,以及先前以$18.9/TH的价格获得的S21 Pro矿机。该公司在比特币的全额现金成本估计约为$29,000,借助一流的设备效率和低电力成本,保持了竞争优势。
Iris Energy在其Childress Phase 3变电站投入使用后,已将自挖矿总能力提升33%至28 EH/s。该公司预计本月将达到31 EH/s,现场拥有足够的矿机库存,并且已有四座IDC概念建筑投入运营。其余两座IDC概念预计本月完成内部装修。该公司已将扩张目标从2025年下半年提前至2025年上半年,计划达到50 EH/s和810MW的IDC概念。这一增长得益于Childress Phase 4 & 5的开发(+300MW),正在进行的土木工程,能够每月建设50MW的现场团队,以及先前以$18.9/TH的价格获得的S21 Pro矿机。该公司在比特币的全额现金成本估计约为$29,000,借助一流的设备效率和低电力成本,保持了竞争优势。