Ascot Reports Second Quarter 2023 Results and Provides Construction Update on the Premier Gold Project

Ascot Reports Second Quarter 2023 Results and Provides Construction Update on the Premier Gold Project

Ascot公布了2023年第二季度业绩,并提供了Premier Gold项目的施工最新情况
GlobeNewswire ·  2023/08/14 07:00

VANCOUVER, British Columbia, Aug.  14, 2023  (GLOBE NEWSWIRE) -- Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) ("Ascot" or the "Company") is pleased to announce the Company's unaudited financial results for the three months and six months ended June 30, 2023 ("Q2 2023"), and also to provide a construction update on the Company's Premier Gold Project ("PGP" or the "project"), located on Nisga'a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. For details of the unaudited condensed interim consolidated financial statements and Management's Discussion and Analysis for the three and six months ended June 30, 2023, please see the Company's filings at  or on SEDAR+ ().

温哥华,不列颠哥伦比亚省,2023年8月14日-(环球通讯社)爱思高资源有限公司(TSX:AOT;OTCQX:AOTVF)(“阿斯科特“或”公司)欣然公布本公司截至2023年6月30日止三个月及六个月的未经审计财务业绩(“2023年第二季度),并提供该公司黄金项目的最新施工情况(“PGP“或”项目“),位于NIS上G《国家条约》位于不列颠哥伦比亚省西北部多产的金三角地区。关于截至2023年6月30日的三个月和六个月的未经审计简明中期综合财务报表和管理层的讨论和分析的详情,请参阅公司提交的文件,网址为:或SEDAR+()。

Derek White, President and CEO, commented, "Construction activity at the Premier Gold Project continued to increase in the second quarter, with much progress being made on the critical outdoor and earthworks areas, including the tailings storage facility and new water treatment plant. As of Q2 2023, detailed engineering and major procurement are substantially complete, and project construction excluding mine development is at 48%.

总裁兼首席执行官德里克·怀特评论说,“Premier Gold Project的建筑活动在第二季度继续增加,在关键的户外和土方工程领域取得了很大进展,包括尾矿储存设施和新的水处理厂。截至2023年第二季度,详细工程和主要采购基本完成,不包括矿山开发的项目建设占48%。

Additionally, at the corporate level we have made steady progress on important agreements including the signing of a 3-year mining contract with Procon, the US$15 million equipment lease facility with CAT Financial, and the US$14 million convertible facility with Nebari.

此外,在公司层面,我们在重要协议上取得了稳步进展,包括与Procon签署了为期3年的采矿合同,与CAT Financial签署了价值1,500万美元的设备租赁设施,与内巴里签署了价值1,400万美元的可转换设施。

The 2023 exploration program has been steadily progressing, with encouraging results encountered in both the drilling program and the IP geophysics program. We anticipate starting to release exploration results in the coming weeks as we receive them."

2023年勘探方案稳步推进,钻井方案和IP地球物理方案都取得了令人鼓舞的成果。我们预计在收到勘探结果后,将在未来几周内开始发布。“

All amounts herein are reported in $000s of Canadian dollars ("C$") unless otherwise specified.

报告中的所有金额均以加元为单位(“加元“)除非另有说明,否则。

Q2 2023 AND RECENT HIGHLIGHTS

2023年第二季度和最近的亮点

  • The earthworks contract for the tailings storage facility was signed in March 2023 and the contractor was mobilized to the site in April 2023. Tailings pond de-watering was completed in June 2023 and the construction of the tailings storage facility commenced.

  • On April 20, 2023, the Company closed a previously announced non-brokered private placement (the "Offering"). The Offering raised total gross proceeds of $4,050 and consisted of 5,000,000 common shares of the Company, which qualify as "flow-through shares" within the meaning of the Income Tax Act (Canada) (the "FT Shares"), at a price of C$0.81 per FT Share. The proceeds from the Offering will be used to fund the 2023 exploration program at PGP.

  • On May 11, 2023, the Company announced the 2023 exploration program at PGP. The program consists of an initial 10,000 metres of surface drilling and will include exploration drilling for resource expansion as well as in-fill drilling of initial mining areas at the Big Missouri and Premier deposits. The exploration drilling will focus on extending the Day Zone at Big Missouri and the Sebakwe Zone north of the Premier mill. Up to an additional 4,000 meters of drilling have been budgeted and will be deployed towards surface and underground drilling depending on results of the initial 10,000 metres. The 2023 exploration program commenced on June 21, 2023.

  • On June 27, 2023, the Company closed a previously announced US$14 million subordinated convertible credit facility (the "Convertible Facility") with Nebari Gold Fund 1, LP ("Nebari"). The full proceeds from the Convertible Facility were used to repay principal, accrued interest and fees of Ascot's existing subordinated convertible credit facility with Beedie Investments Ltd. ("Beedie").

  • On July 31, 2023, the Company entered into a master lease agreement with Caterpillar Financial Services ("CAT Financial") for an equipment lease facility up to US$15 million on an uncommitted basis for surface mining equipment and construction equipment. The lease terms of the equipment are 4 to 5 years at an interest rate of the Canadian Dollar Offered Rate plus 4.25%.

  • On August 8, 2023, the Company entered into a contract with Procon Mining & Tunnelling Ltd. for underground mining services for an initial term of 3 years with option to renew for two consecutive 1-year periods.

  • 尾矿储存设施的土方工程合同于2023年3月签署,承包商于2023年4月被动员到现场。尾矿库脱水于2023年6月完成,尾矿库存储设施开始建设。

  • 2023年4月20日,本公司完成了此前宣布的一项非经纪私募(以下简称“招股”)。是次发行筹集总收益4,050美元,包括5,000,000股本公司普通股,符合《加拿大所得税法》(加拿大)所指的“流通股”(“FT股”),每股FT股份的价格为0.81加元。此次发行所得资金将用于PGP 2023年的勘探项目。

  • 2023年5月11日,公司宣布了2023年在PGP的勘探计划。该计划包括最初10,000米的地面钻探,并将包括为扩大资源而进行的勘探钻探,以及大密苏里州和Premier矿藏初始矿区的充填钻探。勘探钻探的重点将是扩大大密苏里州的Day区和Premier Mill以北的Sebakwe区。已编入多达4 000米的额外钻探预算,并将根据最初10 000米的钻探结果部署用于地面和地下钻探。2023年勘探计划于2023年6月21日开始。

  • 2023年6月27日,本公司完成了与Nebari Gold Fund 1,LP(“Nebari”)之前宣布的1,400万美元的附属可转换信贷安排(“可转换贷款”)。可转换贷款的全部收益用于偿还Ascot与Beedie Investments Ltd.(“Beedie”)现有的附属可转换信贷贷款的本金、应计利息和费用。

  • 于2023年7月31日,本公司与卡特彼勒金融服务公司(“卡特彼勒金融”)订立一项总租赁协议,就露天采矿设备及建筑设备的未承诺基础上最高达1,500万美元的设备租赁设施。设备的租赁期限为4至5年,利率为加元报价利率加4.25%。

  • 2023年8月8日,公司与Procon矿业和隧道有限公司签订了一份地下采矿服务合同,初始期限为3年,并有权连续两次续签1年。

PROJECT CONSTRUCTION

项目建设

In January 2023, the Company closed a project financing package consisting of US$110 million as a deposit in respect of gold and silver streaming agreements (the "Stream") and a strategic equity investment (the "Strategic Investment") of C$45 million, a portion of which is structured as Canadian Development Expenditures flow through shares, such that the total gross proceeds to the Company were C$50 million. Upon securing the new project financing, Ascot re-mobilized various contractors to progress activities for the remainder of construction scope for the Project. At the start of Q2 2023, there were approximately 118 employees and contractors working at the project site, and by the end of the quarter on June 30, 2023, there were over 180 people working at site.

于2023年1月,本公司完成一项由1.1亿美元作为金银分流协议保证金(“溪流”)及4,500万加元战略股权投资(“战略投资”)的项目融资方案,其中部分为加拿大发展开支流经股份的结构,使本公司的总收益为5,000万加元。在获得新的项目融资后,ASCOT重新动员了各种承包商,以推进项目剩余建设范围的活动。2023年第二季度初,约有118名员工和承包商在项目现场工作,到2023年6月30日季度末,现场工作人员超过180人。

Progress key performance indicators ("KPI") and budget
At the end of Q2 2023, overall construction excluding mine development was 48% complete, with engineering at 99% and procurement at 99%. The Project remains on schedule and budget for first gold production in the first quarter of 2024. Capital costs, including mining, incurred as of June 30, 2023 were $200 million. As of June 30, 2023, the remaining project construction capital required to complete construction and achieve the first gold pour is approximately $110 million including mining but excluding certain pre-operating costs and working capital. This is slightly higher than the most recent total project budget of $300 million to achieve first gold production reported in the Company's News Release dated December 12, 2022. The modest cost increase is attributable to a slight delay of several weeks to achieve initial gold production, which arose as the Company progressed the detailed commissioning schedule. However, the target for initial gold production in Q1 of 2024 is unchanged. The company is assessing the working capital requirements as the project progresses from commissioning to production and ramp up phases, and is evaluating various potential financing options should additional funding be required.

进展关键绩效指标(“KPI”)和预算
于2023年第二季度末,不计矿山开发的整体建设完成48%,工程完成99%,采购完成99%。该项目仍按计划和预算在2024年第一季度生产第一批黄金。截至2023年6月30日,包括采矿在内的资本成本为2亿美元。截至2023年6月30日,完成建设和实现第一次倒金所需的剩余项目建设资本约为1.1亿美元,包括采矿,但不包括某些前期运营成本和营运资本。这略高于公司在日期为2022年12月12日的新闻稿中报道的实现首次黄金生产的最新项目预算总额3亿美元。成本小幅上升是由于在本公司进行详细的投产时间表时,实现初步黄金生产的时间略有延迟数周。然而,2024年第一季度的初始黄金产量目标没有变化。随着项目从投产到投产和投产阶段的进展,该公司正在评估营运资金需求,并正在评估各种潜在的融资选择,如果需要额外资金的话。

Safety
The Project continues to have an excellent safety record with 633,224 hours of work to date and zero lost time incidents. The total recordable incident frequency has been reduced from 1.28 at the end of Q1 2023, to 0.95 by the end of Q2 2023. However, with the increased activity on site and additional work areas, the number of incidents has increased including property damage, first aid injuries, and near misses. Reporting activity has been encouragingly high, and the Company will continue to work on proactive safety training and measures to reduce overall incidents at the Project site.

安全问题
该项目继续保持着良好的安全记录,迄今已工作633224小时,没有发生任何损失时间事件。总的可记录事件频率已从2023年第一季度末的1.28次减少到2023年第二季度末的0.95次。然而,随着现场活动的增加和更多的工作区域,事故的数量也有所增加,包括财产损失、急救受伤和险些错过预期。报告活动一直很高,令人鼓舞,公司将继续致力于积极主动的安全培训和措施,以减少项目现场的总体事故。

Processing Plant
Mechanical work continued in the mill during Q2 2023; various trommels, dust collection and chute infrastructure were installed around the SAG and Ball mills. The Intensive Leach Reactor was assembled. Electricians continued installing electrical cabinetry, pulling wire, installing cable trays, and working in the mine control centre room. Piping installation at the mill is approximately 50% complete. The tailings thickener and cyanide destruction tank outside the mill was also substantially completed in the quarter. Concrete and structural steel contractors also have been restarted and their scope updated for the mill completion.

加工厂
2023年第二季度,磨机继续进行机械工作;SAG和球磨机周围安装了各种滚筒、除尘和溜槽基础设施。密集的LEACH反应堆已经组装完毕。电工们继续安装电气柜,拉钢丝,安装电缆桥架,并在矿井控制中心房间工作。工厂的管道安装大约完成了50%。该厂外的尾矿浓缩机和氰化物销毁罐也在本季度基本完工。混凝土和结构钢承包商也已重新启动,其范围也已更新,以完成磨坊。

Tailings Storage Facility ("TSF") and Cascade Creek Diversion Channel ("CCDC")
The earthworks contract for the TSF and CCDC was signed in March 2023 and the contractor was mobilized to the site in April 2023. In order to de-water the tailings facility for the required earthworks, an additional temporary water treatment plant ("WTP") was mobilized to site and commissioned in May 2023. Despite minor issues with initial ramp up, at the end of May the plant was operating at full capacity and in combination with other discharge points, the TSF was discharging near the permitted rate of 20,000 m3 per day. By the end of June 2023, dewatering was completed and the temporary WTP was demobilized. Drilling and blasting were started on the CCDC in May, with a target of one blast of 7,000 to 8,000 m3 every other day. To date, geological monitoring hasn't noted potentially acid generating ("PAG") material, and work is progressing well. Work continued at the TSF with earthworks contractors producing and placing T-zone material at the south dam, preparing the foundation at the east dam, blasting rock from the CCDC and bringing it to the crusher plant. The earthworks contractor added a night shift at the end of June to increase productivity.

尾矿储存设施和下跌溪引水渠
TSF和CCDC的土方工程合同于2023年3月签署,承包商于2023年4月进驻工地。为了为所需的土方工程对尾矿设施进行脱水,已调集额外的临时水处理厂到现场,并于2023年5月投入使用。尽管最初的排污量出现了一些小问题,但在5月底,该厂已满负荷运行,与其他排污点相结合,TSF的排污量接近每天20,000立方米的许可排污量。到2023年6月底,脱水工作完成,临时污水处理厂复员。今年5月,中纪委开始钻探爆破,目标是每隔一天进行一次7000至8000立方米的爆破。到目前为止,地质监测还没有发现潜在的产酸物质,工作进展顺利。TSF的工作仍在继续,土方承包商在南大坝生产和放置T区材料,在东大坝准备地基,从CCDC爆破岩石并将其送到破碎机厂。这家土方承包商在6月底增加了一班夜班,以提高生产率。

Water Treatment Plant ("WTP")
Crews have also made progress on the new WTP and associated infrastructure, including the tailings thickener, lime silos, moving bed bio-reactor ("MBBR") tanks and clarifier foundation pedestals. Construction remains targeted for July and August to coincide with new WTP completion in September and subsequent commissioning.

滤水厂(“WTP”)
工作人员还在新的污水处理厂和相关基础设施方面取得了进展,包括尾矿浓缩机、石灰仓、移动床生物反应器(“MBBR”)池和澄清池底座。施工的目标仍然是在7月和8月,以配合9月新的WTP完工和随后的投产。

Site Infrastructure
During Q2 2023, much work was completed on constructing the new electrical substation near the Premier mill. With the substation mostly complete, crews are now working on the 138kV power line to connect to the power grid less than 500 metres away. Crews also have been making progress on relocating the Big Missouri water pipeline from one side of the Big Missouri haul road to the other, which is expected to enhance the long-term safety and integrity of the pipeline.

站点基础设施
在2023年第二季度,在Premier Mill附近建造新的变电站的工作已经完成。随着变电站基本完工,工作人员现在正在138千伏的输电线上工作,以连接到不到500米远的电网。工作人员还在将大密苏里州输水管道从大密苏里州运输公路的一侧搬迁到另一侧的工作中取得了进展,预计这将增强管道的长期安全性和完整性。

Mine Development
After an extensive and competitive process involving six contracting companies, Ascot selected Procon Mining & Tunnelling ("Procon") for a 3-year contract to advance the underground portion of the project. Procon is headquartered in Burnaby, BC and has extensive underground mining experience in the province, including its current mining and development contract at the nearby Brucejack underground gold mine.

矿山开发
经过六家承包公司的广泛竞争,ASCOT选择了Procon矿业和隧道公司(“Procon”)作为一份为期3年的合同,以推进该项目的地下部分。Procon总部位于卑诗省伯纳比,在该省拥有丰富的地下采矿经验,包括其目前在附近Brucejack地下金矿的采矿和开发合同。

In 2022, work commenced on the S1 portal and approximately 907 metres of underground development was completed in the Big Missouri area before being paused for the winter. Procon will pick up from this existing development and continue the ramp and ore accesses as planned in September 2023, eventually connecting over to the Silver Coin deposit.

2022年,S1门户开始施工,大密苏里地区约907米的地下开发工程在冬季暂停之前完成。Procon将从这个现有的开发项目中恢复过来,并按计划在2023年9月继续修建坡道和矿石通道,最终连接到银币矿藏。

In late summer 2023, Procon will also start a new ramp development at the Premier deposit immediately adjacent to the existing mill facilities. They will drive the initial access ramp from surface down into the Premier deposit for initial mining at the Prew zone and will eventually connect a footwall ramp over to 602 area in the Premier deposit to commence mining there.

2023年夏末,Procon还将在紧挨着现有磨坊设施的Premier矿藏开始新的坡道开发。他们将把最初的入口坡道从地表向下推入Premier矿藏,以便在Prew区进行初步开采,并最终将连接一个底部坡道至Premier矿藏的602区,在那里开始采矿。

Recruitment
During Q2 2023, Ascot hired and onboarded a full-time recruitment professional to lead the Company's staffing efforts as it advances towards operations in 2024. Recruitment has already begun to ramp up for a number of key positions added recently, including Health, Safety, Training and Emergency Preparedness, Human Resources and Fixed Maintenance Planner.

招聘
在2023年第二季度,ASCOT聘请并聘用了一名全职招聘专业人员来领导公司在2024年开始运营时的人员配备工作。最近增加的一些关键职位的招聘工作已经开始加快,包括健康、安全、培训和应急准备、人力资源和固定维护计划员。

As recruitment efforts continue to ramp up in the coming months. The interest in Ascot is high and many good quality candidates continue to apply for open positions. Encouragingly, local interest is high, as many applications are coming from candidates in the area of Stewart and northwestern B.C.

未来几个月,招聘工作将继续加大力度。对阿斯科特的兴趣很高,许多优秀的应聘者继续申请空缺职位。令人鼓舞的是,当地的兴趣很高,因为许多申请者来自斯图尔特和不列颠哥伦比亚省西北部地区的候选人。

Permitting and Environmental Compliance
As a result of the project slowdown in 2022 due to the required re-financing process, a Joint Permit Amendment Application ("JPAA") will be submitted in August 2023 to change targeted conditions within the permit, mostly due to the delay of meeting the new water treatment and quality requirements from December 2022 to Q4 2023. In addition, a Mines Act Permit Amendment ("MAPA") was submitted in mid-June 2023 with respect to changing the planned location of the Premier mine portal from the southern location to an area much closer to the mill facility. All comments and information requests from the Nisga'a Lisims Government have been addressed and closed, and comments from the regulator are expected to be finalized in the coming weeks.

许可和环境合规
由于所需的再融资程序导致2022年项目放缓,将于2023年8月提交联合许可证修订申请(JPAA),以改变许可证中的目标条件,主要是由于满足新的水处理和水质要求的时间从2022年12月推迟到2023年第四季度。此外,2023年6月中旬提交了一份《矿业法许可证修正案》(“MAPA”),涉及将Premier矿山门户的规划位置从南部改为更靠近工厂设施的区域。来自国家情报机构的所有评论和信息请求GA‘a Lisims政府已经得到解决并关闭,监管机构的评论预计将在未来几周内敲定。

2023 EXPLORATION PROGRAM

2023年勘探计划

The exploration program commenced on June 21, 2023 when a drill rig was mobilized to the Prew zone of the Premier deposit. The first nine drill holes have been completed and have intercepted visual sulfide mineralization very close to expected depth and corresponding stope locations. Visible gold was intercepted in at least one of the drill holes. It appears that the location and geometry of the mineralization at the Prew is well defined and should provide a good starting point for mining operations. Four more holes are planned in this area aiming at extensions of stopes and gaps between designed stopes. On completion of the drilling at the Prew zone, the rig will move up to Big Missouri to conduct additional drilling in that area.

勘探计划于2023年6月21日开始,当时一个钻机被动员到Premier矿床的Prew区。前九个钻孔已经完成,截获了非常接近预期深度和相应采场位置的可视硫化物矿化。至少在一个钻孔中截获了可见的黄金。看来,Prew矿化的位置和几何形状已经确定,应该为采矿作业提供一个良好的起点。计划在该地区再打四个洞,以扩大采场范围和设计采场之间的空隙。在Prew区完成钻探后,钻井平台将向上移动到大密苏里州,在该地区进行额外的钻探。

The ground geophysical induced polarization ("IP") survey commenced on June 26, 2023 and is now approximately 70% complete. The crew completed two grids, one near the Premier mill targeting the western extension of the Sebakwe Zone that yielded very good exploration results last year. The grid has been designed to cover approximately 1,000 metres of strike extent to the west of the drilling in 2022. It is not known if the Sebakwe Zone extends further west and if so, where it is located in terms of northing. The mineralization at Premier shows very well in induced polarization data and preliminary results are highly anticipated.

地面地球物理激电调查于2023年6月26日开始,现已完成约70%。工作人员完成了两个网格,其中一个位于Premier Mill附近,目标是Sebakwe区的西部延伸,去年产生了非常好的勘探结果。该网格的设计覆盖了2022年钻井以西约1000米的走向范围。目前还不知道塞巴奎地区是否进一步向西延伸,如果是的话,它在北向的位置。激发极化数据很好地显示了Premier的矿化作用,初步结果令人高度期待。

The second grid was completed around the Dilworth deposit in the northern part of the property. The geology of this area is not as well understood as Premier and Big Missouri and the exploratory induced polarization data should help with effective targeting of prospective areas. A third grid is currently being laid out at the northern extension of the Day Zone. This area has yielded very good exploration results in the last two years and mineralization remains open towards the north and south. The strike extent to the north could potentially connect the Day Zone with the Martha Ellen deposit further north. The results from the IP survey will be utilized for drill targeting in the second half of the 2023 field season.

第二个网格是围绕着地产北部的迪尔沃斯矿藏完成的。这一地区的地质情况不如密苏里州首府和大密苏里州,探索性的激发极化数据应该有助于有效定位远景地区。第三个网格目前正在日区的北部延伸部分铺设。近两年来,该地区取得了很好的勘探效果,矿化仍向南北开放。北部的罢工范围可能会将Day Zone与更靠北的Martha Ellen矿床连接起来。IP调查的结果将用于2023年下半个野外赛季的钻探目标。

FINANCIAL RESULTS FOR THE THREE MONTHS ENDED JUNE 30, 2023

截至2023年6月30日的三个月的财务业绩

The Company reported a net loss of $3,073 for Q2 2023 compared to $1,054 for Q2 2022. The higher net loss in current quarter is driven by a $2,262 loss on extinguishment of convertible debt.

该公司报告2023年第二季度净亏损3,073美元,而2022年第二季度净亏损1,054美元。本季度较高的净亏损是由可转换债券清偿造成的2262美元亏损推动的。

LIQUIDITY AND CAPITAL RESOURCES

流动资金和资本资源

As at June 30, 2023, the Company had cash & cash equivalents of $119,324 and working capital of $103,147. In H1 2023, the Company issued 120,048,007 common shares, no vested warrants, 613,334 stock options, 32,665 deferred share units, no restricted share units and no performance share units. Also, 520,250 stock options expired and 55,530 stock options, 352,006 deferred share units and 683,398 restricted share units were exercised in H1 2023.

截至2023年6月30日,公司的现金及现金等价物为119,324美元,营运资本为103,147美元。于2023年上半年,本公司发行了120,048,007股普通股、无既得认股权证、613,334份股票期权、32,665份递延股份单位、无限制性股份单位及无履约股份单位。此外,520,250份股票期权于2023年上半年到期,55,530份股票期权、352,006份递延股份单位及683,398份限制性股份单位于2023年上半年获行使。

As at August 11, 2023, the Company had 555,909,153 common shares outstanding, 23,822,382 stock options, 13,710,500 vested share purchase warrants, 1,557,071 deferred share units, 3,796,930 restricted share units and 108,108 performance share units outstanding. Also, 25,767,777 unvested Prepayment Warrants issued to Nebari are outstanding.

截至2023年8月11日,公司拥有555,909,153股已发行普通股、23,822,382份股票期权、13,710,500份既有认股权证、1,557,071份递延股份单位、3,796,930股限制性股份单位及108,108份已发行业绩股份单位。此外,向内巴里发行的25,767,777份未归属预付款认股权证尚未完成。

MANAGEMENT'S OUTLOOK FOR 2023

管理层对2023年的展望

With the financing package closed on January 19, 2023 and refinancing of the existing convertible debt on June 28, 2023, the Company is focusing on the completion of construction of the Project and achieving first gold production in early 2024. The key activities for remainder of 2023 include:

随着融资方案于2023年1月19日结束,现有可转债于2023年6月28日进行再融资,公司正专注于完成该项目的建设,并于2024年初实现首次黄金生产。2023年剩余时间的主要活动包括:

  • Construction of the processing plant and associated surface infrastructure such that the plant is expected to be in pre-commissioning by the end of 2023

  • Completion of the tailings dam improvements and start up of the new water treatment plant by Q4 2023

  • Advancement of the Premier portal and underground development and additional underground development of the Big Missouri mine, as well as initial production stoping to provide mill feed for commissioning.

  • Maintaining a Health and Safety record of zero lost time incidents and achieving the 2023 goals outlined in the Company's 2022 Sustainability Report

  • Advancing the recruitment of site personnel in line with the site personnel plan by the end of 2023

  • Maintaining permitting and environmental compliance so that there are no delays in the project construction schedule

  • More exploration and infill drilling north and west of existing resources at the Premier Northern Light and Day zone resources areas

  • 建造加工厂和相关的地面基础设施,以使工厂预计在2023年底前投入试运行

  • 在2023年第四季度前完成尾矿库改善工程和新滤水厂的投产

  • 推进Premier门户和地下开发,以及大型密苏里州矿山的额外地下开发,以及初步生产停产,为投产提供磨矿原料。

  • 保持零损失时间事故的健康和安全记录,实现公司2022年可持续发展报告中概述的2023年目标

  • 按照现场人员计划在2023年底前提前招聘现场人员

  • 维护许可和环境合规性,使项目施工进度不会出现延误

  • 在Premier Northern Light and Day区域资源区现有资源的北部和西部进行更多勘探和加密钻探

Qualified Person

有资格的人

John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company's Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.

公司首席运营官John Kiernan,P.Eng是国家仪器43-101定义的公司合格人员(QP),并已审查和批准了本新闻稿的技术内容。

On behalf of the Board of Directors of Ascot Resources Ltd.
"Derek C. White"
President & CEO

我代表爱思高资源有限公司董事会发言。
“德里克·C·怀特”
总裁兼首席执行官

For further information contact:

如需进一步信息,请联系:

David Stewart, P.Eng.
VP, Corporate Development & Shareholder Communications
dstewart@ascotgold.com
778-725-1060 ext. 1024

David·斯图尔特,P.
企业发展和股东公关副总裁
邮箱:dstewart@ascotGold.com
778-725-1060分机1024

About Ascot Resources Ltd.

关于阿斯科特资源有限公司

Ascot is a Canadian junior exploration and development company focused on re-starting the past producing Premier gold mine, located on Nisga'a Nation Treaty Lands, in British Columbia's prolific Golden Triangle. Ascot shares trade on the TSX under the ticker AOT. Concurrent with progressing the development of Premier, the Company continues to successfully explore its properties for additional high-grade underground resources. Ascot is committed to the safe and responsible development of Premier in collaboration with Nisga'a Nation as outlined in the Benefits Agreement.

ASCOT是一家加拿大初级勘探和开发公司,专注于重新启动位于尼斯岛的Premier金矿的过去生产G一个国家条约土地,在不列颠哥伦比亚省多产的金三角。Ascot的股票在多伦多证交所交易,股票代码为AOT。在推进Premier开发的同时,该公司继续成功地勘探其物业,以获得更多的高品位地下资源。ASCOT致力于与Nisga‘a Nisga Nation合作,安全和负责任地发展Premier,正如福利协议中概述的那样。

For more information about the Company, please refer to the Company's profile on SEDAR+ at  or visit the Company's web site at , or for a virtual tour visit  under Ascot Resources.

有关公司的更多信息,请参阅公司在SEDAR+上的简介,或访问公司的网站,或访问Ascot Resources下的虚拟参观访问。

The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

多伦多证券交易所没有对本新闻稿的充分性或准确性进行审查,也不承担任何责任。