Fortescue Faces Pipeline Leaks

Fortescue Faces Pipeline Leaks

Fortescue 面临管道泄漏
sharecafe ·  01/24 23:23

Fortescue Metals' (ASX:FMG) troubled Iron Bridge export magnetite iron ore mine in WA's Pilbara continues to cause problems and is nowhere near planned capacity at this stage.

位于西澳大利亚州皮尔巴拉的Fortescue Metals(澳大利亚证券交易所股票代码:FMG)陷入困境的铁桥出口磁铁矿继续造成问题,目前还远未达到计划产能。

Cost overruns, technical problems, management changes, and budget blowouts saw a $US1 billion pre-tax impairment in the June 30, 2023 year, as Fortescue battled to rightsize the budget and the operation of the project.

随着Fortescue努力调整预算和项目运营,成本超支、技术问题、管理层变动和预算井喷在2023年6月30日造成了10亿美元的税前减值。

But now there are leaks in a vital piece of infrastructure - a 220-kilometer water supply pipeline, where more than 30% (approximately 65 kilometers) of steel pipe will need replacing.

但是现在,一条长达220公里的供水管道——一条至关重要的基础设施出现了泄漏,其中超过30%(约65千米)的钢管需要更换。

This problem alone could cost Fortescue more than $A1.3 billion in lost sales revenue and extra costs to fix the leaks.

仅这个问题就可能使Fortescue损失超过13亿澳元的销售收入和修复泄漏的额外成本。

It's the second time in 10 months this pipeline has disrupted the project - in March, it delayed the final work on Iron Bridge for around three months.

这是该管道在10个月内第二次中断该项目——3月,它将Iron Bridge的最后工程推迟了大约三个月。

But according to Fortescue, Iron Bridge is doing okay, which does seem a bit at odds with the pipeline problems and the huge cost to fix it - close to $A200 million.

但是根据Fortescue的说法,Iron Bridge表现不错,这似乎与管道问题和修复管道的巨大成本——接近2亿澳元——有些矛盾。

"Iron Bridge commissioning activities continue to progress well. A second shipment of Iron Bridge Concentrate was achieved during Q2 FY24, and three shipments in January 2024."

“Iron Bridge的调试活动继续进展顺利。Iron Bridge 浓缩物的第二批出货是在24财年第二季度实现的,三批于2024年1月发货。”

"Iron Bridge FY24 shipments guidance has been revised due to the performance of the Raw Water Pipeline. Work is underway to resolve the performance issues.

“由于原水管道的表现,铁桥24财年的出货指导已修订。解决性能问题的工作正在进行中。

Fortescue had already trimmed expected exports from Iron Bridge from 7 million tonnes in its June 30, 2023 announcement to 5 million in its September quarter production and sales report.

Fortescue已经将Iron Bridge的预期出口量从2023年6月30日公告中的700万吨削减至9月季度产量和销售报告中的500万吨。

But Thursday's December quarter saw yet another cut to a range of 2 to 4 million tonnes for the year to June 30 - in other words, the original 7 million tonne estimate for the year to June 30, 2024, has been slashed by more than 70% at worst.

但是,周四的12月季度在截至6月30日的年度中再次削减至200万至400万吨——换句话说,截至2024年6月30日的年度最初估计的700万吨,最坏的情况已经下调了70%以上。

The explanation was detailed in the quarterly report with the project's 61.9% owner, Fortescue, up for an estimated $US100 million (or more than $A150 million) to fix the leaks.

季度报告中详细介绍了这一解释,该项目61.9%的所有者Fortescue估计需要1亿美元(合1.5亿澳元以上)来修复泄漏问题。

"While the performance of the Canning Basin Raw Water Pipeline improved relative to the prior quarter, further leaks were detected during Q2 FY24, which impacted the flow rate and uptime.

“尽管坎宁盆地原水管道的性能与上一季度相比有所改善,但在24财年第二季度发现了进一步的泄漏,这影响了流量和正常运行时间。

"Work is underway to evaluate options to de-risk and improve the performance of the high-pressure section (65 kilometers) of the Raw Water Pipeline, where the leaks have occurred.

“正在评估各种备选方案,以降低发生泄漏的原水管道高压部分(65千米)的性能,并改善其性能。

"It is anticipated that replacing this section of the Pipeline would not materially impact Iron Bridge's ramp-up schedule and would require an investment of approximately US$100 million (Fortescue's share)," Fortescue said.

Fortescue说:“预计更换这段管道不会对Iron Bridge的扩建计划产生重大影响,并且需要投资约1亿美元(Fortescue的份额)。”

The loss is substantial for Fortescue - if it had been able to make the 7 million tonnes of exports from Iron Bridge, it would have added another $US1 billion to annual revenue by June 30 (that's at the $US144 a tonne the Iron Bridge concentrates were sold, according to the latest quarterly report).

Fortescue的损失是巨大——如果它能够从Iron Bridge出口700万吨,到6月30日,其年收入将再增加10亿美元(根据最新的季度报告,铁桥精矿的销售额为每吨144美元)。

If they manage to ship 2 million tonnes by June 30, Fortescue could forgo $US700 million of revenue. Selling four million tonnes would see the company miss revenues of more than $US400 million.

如果他们设法在6月30日之前出货200万吨,Fortescue可能会放弃7亿美元的收入。出售400万吨将使该公司损失超过4亿美元的收入。

Those leaks are an expensive headache in more ways than one.

这些泄漏在许多方面都是一个代价高昂的头疼问题。