Highlights:

亮点:

  • Heliostar undertakes review of financing options to complete the existing decline and test mining of a bulk gold sample in advance of a Feasibility Study
  • Multiple scenarios show the potential to recover >20,000 ounces of gold from stopes averaging 7-10 g/t gold
  • Demonstrates a potential pathway to production from test mining within 12 months
  • The Company is assesing non-equity funding options for this program
  • Heliostar has initiated a Preliminary Economic Assessment ("PEA") planned for completion in H2, 2024
  • Continued resource growth drilling, PEA, and underground permit modifcation submission to be completed in 2024
  • Heliostar对融资方案进行了审查,以完成现有的下跌,并在可行性研究之前测试大宗黄金样本的开采
  • 多种情景表明,有可能从平均7-10 g/t黄金的止损中回收超过20,000盎司的黄金
  • 展示了在 12 个月内通过试采实现生产的潜在途径
  • 该公司正在评估该计划的非股权融资方案
  • Heliostar已启动初步经济评估(“PEA”),计划于2024年下半年完成
  • 持续的资源增长钻探、PEA和地下许可证修改申请将于2024年完成

Vancouver, British Columbia--(Newsfile Corp. - February 8, 2024) - Heliostar Metals Ltd. (TSXV: HSTR) (OTCQX: HSTXF) (FSE: RGG1) ("Heliostar" or the "Company") is pleased to provide an update on the potential to advance the underground decline and complete test mining to process a bulk sample from the Ana Paula deposit in Guerrero, Mexico.

不列颠哥伦比亚省温哥华--(新闻文件公司,2024年2月8日)——Heliostar Metals Ltd.(多伦多证券交易所股票代码:HSTR)(场外交易所股票代码:HSTXF)(FSE:RGG1)(”Heliostar“或者”公司“)很高兴提供有关推进地下采矿的可能性的最新信息,并完成试采,以处理来自墨西哥格雷罗安娜·保拉矿床的大量样本。

Heliostar CEO, Charles Funk, commented, "Since acquiring Ana Paula 10 months ago, Heliostar's team has moved quickly to redefine Ana Paula as a high-grade underground gold project. We have successfully increased the resource, identified a >10 g/t gold zone for possible commencement of mining, identified additional resource growth areas, demonstrated significant improvement to gold recoveries, and bolstered the Company's management team. The Company intends to maintain the current high pace of progress in 2024 by studying the benefits of completing the existing underground decline to test mine a bulk sample. In our view, this will be a large step towards de-risking the underground plan for Ana Paula. In addition, it will provide greater confidence in the deposit's gold recoveries, lower the cost of infill drilling and provide a platform for deeper resource growth drilling. The gold contained in the bulk sample can potentially fund the decline development. Heliostar also intends to complete a PEA in the second half of 2024, submit the underground mining permit modifications and continue resource drilling to further grow the Ana Paula resource."

Heliostar 首席执行官查尔斯·芬克评论说: “自从10个月前收购安娜·保拉以来,Heliostar的团队迅速采取行动,将安娜·保拉重新定义为一个高品位的地下金矿项目。我们成功地增加了资源,确定了>10 g/t的黄金区域以供可能开始采矿,确定了其他资源增长区域,黄金回收率显著改善,并加强了公司的管理团队。该公司打算通过研究完成现有地下采矿试开采批量样本的好处,在2024年保持目前的高速进展。我们认为,这将是朝着降低安娜·保拉地下计划风险迈出的重要一步。此外,它将增强人们对该矿床的黄金回收率的信心,降低填充钻探的成本,并为更深的资源增长钻探提供平台。批量样本中所含的黄金有可能为下跌发展提供资金。Heliostar还打算在2024年下半年完成PEA,提交地下采矿许可证的修改,并继续进行资源钻探,以进一步发展安娜·保拉的资源。”

Bulk Sample Options

批量样本选项

Ana Paula has a 412-metre-long decline currently completed to one third of its target length by a previous operator. Heliostar is undertaking an internal review on the potential to extend this decline to the base of the High Grade Panel to test mine a bulk sample of the deposit.

安娜·保拉目前已经完成了长达412米的下沉长度,下降至目标长度的三分之一。Heliostar正在进行内部审查,探讨是否有可能将这一下降范围扩大到高品位小组的基地,以便对矿床的大量样本进行试采。

The engineering study indicates that the bulk sample will require an additional 1,100m of tunnel development and 317 metres of spiral and stope development. The decline design option has been designed as the best option for future mine production from the current resource.

工程研究表明,批量样本将需要再开发1,100米的隧道以及317米的螺旋和采场开发。减少设计选项被设计为未来利用现有资源进行矿山生产的最佳选择。

The design indicates that a production rate of four metres per day would complete tunnel development and stope development within eleven months from commencement. Completing the development would allow for test production within 12 months of commencement of the start of construction.

该设计表明,每天四米的生产率将在开工后的11个月内完成隧道开发和采场开发。完成开发将允许在施工开始后的12个月内进行试产。

Gold grades within potential stope targets vary from 7-10 g/t gold. Multiple scenarios indicate potential to recover more than 20,000 ounces of gold from a bulk sample.

潜在采矿目标范围内的黄金等级从7-10 g/t的黄金不等。多种情景表明,有可能从散装样本中回收超过20,000盎司的黄金。

Advancement of the decline and mining of a bulk sample can be completed with the current permits held by the Company.

凭公司目前持有的许可证,可以推进批量样本的下降和开采。

Heliostar is advancing a detailed engineering, mining, and metallurgy review of the potential bulk sample. The Company has held discussions with potential offtake partners and currently has samples from the Ana Paula deposit being assessed for metallurgy, recovery and payability information by potential offtake partners. Preliminary financial modelling suggests the recovered gold value exceeds development costs. The Company is exploring self-funding, non-equity options to finance the decline development, test mining processes, and bulk sample collection.

Heliostar正在推进对潜在批量样本的详细工程、采矿和冶金审查。该公司已与潜在的承购合作伙伴进行了讨论,目前潜在的承购合作伙伴正在对安娜·保拉矿床的样本进行冶金、回收和应付能力信息评估。初步财务模型表明,回收的黄金价值超过开发成本。该公司正在探索自筹资金的非股权期权,为衰落开发、测试采矿过程和批量样本收集提供资金。

Heliostar expects this review to be completed before March 30th, 2024, and will provide an update upon completion of this analysis.

Heliostar预计这项审查将在3月30日之前完成第四,2024 年,并将在分析完成后提供最新情况。

Figure 1: Plan and Section map of a decline and stope design option for test mining at Ana Paula.

图 1: 安娜·保拉试采的下坡和采场设计选项的平面图和剖面图。

Preliminary Economic Assessment and 2024 work program

初步经济评估和2024年工作计划

Heliostar filed a technical report for the updated mineral resource estimate on January 11th, 2024 (see news release on January 12th, 2024). Following this report the company intends to complete a Preliminary Economic Assessment based on this resource in 2024. The company is finalizing the scope of this program and expects to deliver the report in the second half of 2024.

Heliostar于1月11日提交了最新矿产资源估算的技术报告第四,2024 年(见 1 月 12 日的新闻稿)第四,2024)。继这份报告之后,该公司打算在2024年根据该资源完成初步经济评估。该公司正在敲定该计划的范围,并预计将在2024年下半年提交报告。

In addition to the PEA, the current resource indicates significant areas for resource expansion and the company has designed a 10,000-15,000-metre drill program to expand the current resource. The drill program's goals include resource growth, infill drilling (to convert gold ounces to higher confidence categories) and new exploration drilling. The potential for constructing the decline will have a significant impact on program design. The Company expects to provide additional details on the 2024 drill program in conjunction with the test mining and bulk sample review. Upon completion of the 2024 drill program, the company intends to provide a resource update that will support a Feasibility Study that is expected to be delivered in 2025.

除PEA外,目前的资源还表明了重要的资源扩张领域,该公司设计了一项10,000-15,000米的钻探计划,以扩大现有资源。该钻探计划的目标包括资源增长、填充钻探(将黄金盎司转换为更高的置信度类别)和新的勘探钻探。造成下降的可能性将对项目设计产生重大影响。该公司预计将在试采和批量样本审查的同时,提供有关2024年钻探计划的更多细节。2024年钻探计划完成后,该公司打算提供资源更新,以支持预计于2025年交付的可行性研究。

Upon completion of the PEA the Company intends to use the engineering designs to submit a modification to the open pit mining permit that the company currently holds. The modification to underground only mining is expected to have a significantly smaller physical and environmental footprint than the currently approved permit. Permit modifications are expected to be received prior to completion of the Feasibility Study.

PEA完成后,公司打算使用工程设计提交对公司目前持有的露天采矿许可证的修改。改为仅限地下采矿的做法预计将比目前批准的许可证小得多的物理和环境足迹。预计将在可行性研究完成之前收到许可证的修改。

Statement of Qualified Person

合格人员声明

Samuel D. Anderson, CPG., Vice President of Projects, of Heliostar Metals Limited, a Qualified Person, as such term is defined by NI 43-101, has reviewed the scientific and technical information that forms the basis for this news release and has approved the disclosure herein. Samuel Anderson relied on resource information contained within the "Ana Paula Project NI 43-101 Technical Report Mineral Resource Estimate Update", filed on SEDAR on January 11, 2024 and prepared by by Lewis Teal and Rita Teal of Teal CPG Inc. Ms. Teal and Mr. Teal are each independent Qualified Persons as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

塞缪尔·安德森,CPG.,Heliostar Metals Limited项目副总裁,该术语由NI 43-101定义,“合格人士” 已经审查了构成本新闻稿基础的科学和技术信息,并批准了此处的披露。塞缪尔·安德森依赖于2024年1月11日向SEDAR提交的 “北卡罗来纳州安娜·保拉项目43-101技术报告矿产资源估算更新” 中包含的资源信息,该报告由蒂尔CPG公司的刘易斯·蒂尔和丽塔·蒂尔编写。根据国家仪器43-101——矿产项目披露标准的定义,蒂尔女士和蒂尔先生都是独立的合格人士。

About Heliostar Metals Ltd.

关于 Heliostar Metals Ltd

Heliostar is a junior mining company with a portfolio of high-grade gold projects in Mexico and Alaska.

Heliostar是一家初级矿业公司,在墨西哥和阿拉斯加拥有高品位黄金项目组合。

The Company is developing the 100% owned Ana Paula Project in Guerrero, Mexico. In addition, Heliostar in conjunction with the Mexican federal and local government, is working to permit the San Antonio Gold Project in Baja Sur, Mexico. The Company continues to explore the Unga Gold Project in Alaska, United States of America.

该公司正在墨西哥格雷罗开发100%拥有的Ana Paula项目。此外,Heliostar与墨西哥联邦和地方政府合作,正在努力批准墨西哥巴哈苏尔的圣安东尼奥黄金项目。该公司继续勘探位于美利坚合众国阿拉斯加的Unga黄金项目。

Ana Paula hosts measured and indicated resources of 710,920 ounces of gold (320,204 measured and 390,716 indicated ounces) at 6.60 g/t gold and an inferred resource of 447,512 ounces of gold at 4.24 g/t gold. The asset is permitted for open-pit mining and contains significant existing infrastructure including a portal and a 412-metre-long decline.

安娜·保拉主持人测量并标明了710,920盎司黄金(测得的320,204盎司和390,716盎司的黄金资源),金量为6.60克/吨,推断的黄金资源为447,512盎司黄金,金量为4.24克/吨。该资产允许进行露天采矿,包含重要的现有基础设施,包括入口和长达412米的下坡。

For additional information, please contact:

欲了解更多信息,请联系:

Charles Funk

查尔斯·芬克

Chief Executive Officer
Heliostar Metals Limited
Email: charles.funk@heliostarmetals.com

首席执行官
Heliostar 金属有限公司
电子邮件:charles.funk@heliostarmetals.com

Rob Grey

罗伯·格雷

Investor Relations Manager
Heliostar Metals Limited
Email: rob.grey@heliostarmetals.com

投资者关系经理
Heliostar 金属有限公司
电子邮件:rob.grey@heliostarmetals.com

Caution Regarding Forward-Looking Information and Statements

关于前瞻性信息和陈述的注意事项

This press release contains statements which constitute "forward‐looking information" within the meaning of applicable securities laws. Forward‐looking information is often identified by the words "may," "would," "could," "should," "will," "intend," "plan," "anticipate," "believe," "estimate," "expect" or similar expressions. Readers are cautioned that forward‐looking information is not based on historical facts but instead reflects the Company's management's expectations, estimates or projections concerning the business of the Company's future results or events based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made. Forward-looking information in this press release includes statements regarding exploration plans, the use of proceeds, and other future plans and objectives, and statements pertaining to receipt of TSX Venture Exchange approval. Although the Company believes that the expectations reflected in such forward‐looking information are reasonable, such information involves risks and uncertainties, and undue reliance should not be placed on such information, as unknown or unpredictable factors could have material adverse effects on future results, performance, or achievements. Among the key factors that could cause actual results to differ materially from those projected in the forward‐looking information are the following: changes in general economic, business and political conditions, including changes in the financial markets; decreases in the prevailing prices for products in the markets that the Company operates in; adverse changes in applicable laws or adverse changes in the application or enforcement of current laws; regulations and enforcement priorities of governmental authorities; compliance with government regulation and related costs; and other risks described in the Prospectus. Should one or more of these risks or uncertainties materialize, or should assumptions underlying the forward‐looking information prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated, or expected. Although the Company has attempted to identify important risks, uncertainties and factors which could cause actual results to differ materially, there may be others that cause results not to be as anticipated, estimated or intended. The Company does not intend, and does not assume any obligation, to update this forward‐looking information except as otherwise required by applicable law.

本新闻稿包含构成适用证券法所指的 “前瞻性信息” 的声明。前瞻性信息通常用 “可能”、“会”、“可以”、“应该”、“将”、“打算”、“计划”、“预测”、“相信”、“估计”、“期望” 或类似的表达方式来识别。提醒读者,前瞻性信息不是基于历史事实,而是反映了公司管理层对公司未来业绩或事件业务的预期、估计或预测,这些预期、估计或预测是基于管理层在声明发表之日认为合理的观点、假设和估计。本新闻稿中的前瞻性信息包括有关勘探计划、所得款项用途和其他未来计划和目标的声明,以及与获得多伦多证券交易所风险交易所批准有关的声明。尽管公司认为此类前瞻性信息所反映的预期是合理的,但此类信息涉及风险和不确定性,不应过度依赖此类信息,因为未知或不可预测的因素可能会对未来的业绩、业绩或成就产生重大不利影响。可能导致实际业绩与前瞻性信息中的预测存在重大差异的关键因素包括:总体经济、商业和政治状况的变化,包括金融市场的变化;公司经营所在市场产品现行价格的下降;适用法律的不利变化或现行法律的适用或执行方面的不利变化;政府当局的法规和执法重点;遵守政府监管和相关成本;以及招股说明书中描述的其他风险。如果其中一种或多种风险或不确定性成为现实,或者前瞻性信息所依据的假设被证明不正确,则实际结果可能与本文所述的预期、计划、预期、相信、估计或预期的结果存在重大差异。尽管公司已尝试确定可能导致实际业绩出现重大差异的重要风险、不确定性和因素,但可能还有其他因素导致业绩与预期、估计或预期不符。除非适用法律另有要求,否则公司无意更新这些前瞻性信息,也不承担任何义务。

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多伦多证券交易所风险投资交易所及其监管服务提供商(该术语在多伦多证券交易所风险交易所的政策中定义)均不对本新闻稿的充分性或准确性承担责任。

声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发