Lahontan Gold Reviews 2023 Milestones and Plans for 2024

Lahontan Gold Reviews 2023 Milestones and Plans for 2024

Lahontan Gold 回顾 2023 年里程碑和 2024 年计划
Accesswire ·  02/12 10:30

TORONTO, ON / ACCESSWIRE / February 12, 2024 / Lahontan Gold Corp (TSXV:LG)(OTCQB:LGCXF) (the "Company" or "Lahontan"), is pleased to provide the following review of key milestones achieved by the Company during 2023 and to lay out Lahontan's mine development and exploration plans for 2024. 2023 was a transformative year for the Company, beginning with the January release of the maiden Mineral Resource Estimate* ("MRE") for its 26.4 km2 flagship Santa Fe Mine project located in the Walker Lane of mining friendly Mineral County, Nevada. Lahontan also completed two fully subscribed financings raising over $5.1M, drilled almost 3,700 metres in the Slab-Calvada resource area, initiated base-line cultural and environmental studies covering almost half the Santa Fe Mine project, acquired the 19.7 km2 West Santa Fe Au-Ag project, expanded Santa Fe via staking by 7.5 km2, and completed a comprehensive review/audit of all past metallurgical testing and production reports for Santa Fe. Details are below:

安大略省多伦多/ACCESSWIRE/2024年2月12日/Lahontan Gold Corp(TSXV: LG)(OTCQB: LGCXF)(“公司” 或 “Lahontan”)很高兴对公司在2023年取得的关键里程碑进行以下回顾,并列出拉洪坦2024年的矿山开发和勘探计划。从1月份发布的2023年开始,对公司来说是变革性的一年其 26.4 千米的首次矿产资源估计*(“MRE”)2 旗舰圣达菲矿山项目位于内华达州矿业友好型县的沃克巷。拉洪坦还完成了两笔全额认购的融资,筹集了超过510万美元,在Slab-Calvada资源区钻探了近3700米,启动了涵盖圣达菲矿项目近一半的基线文化和环境研究,收购了19.7公里2 西圣达菲 Au-Ag 项目,通过质押将圣达菲扩大了 7.5 千米2,并完成了对圣达菲过去所有冶金测试和生产报告的全面审查/审计。详情如下:

Santa Fe Mine Project MRE*: The MRE for Santa Fe, released in January 2023, was based upon 1,275 drill holes totaling 125,435 metres, including 50 drill holes totaling 13,118 metres drilled by Lahontan since 2021 (the MRE does not include holes drilled later in 2023). Highlights of the MRE include:

圣达菲矿山项目 MRE*: 2023 年 1 月发布的 Santa Fe MRE 基于总计 125,435 米的 1,275 个钻孔,其中包括 Lahontan 自 2021 年以来钻探的 50 个钻孔,总计 13,118 米(MRE 不包括 2023 年晚些时候钻出的孔)。MRE 的亮点包括:

  • Project-wide pit constrained Indicated Mineral Resources of 1,112,000 contained gold equivalent ("Au Eq") ounces and Inferred Mineral Resources of 544,000 contained Au Eq ounces. (Au Eq is based on the following formula: Au Eq g/t = Au g/t + (Ag g/t/75) and adjusted for historic differences in Au and Ag recovery during mine operations as described in the MRE).
  • Project-wide average grade for the Indicated Mineral Resource is 1.14 g/t Au Eq; the average grade of the Project-wide Inferred Mineral Resource is 1.00 g/t Au Eq.
  • Indicated Oxide Resources total 21.6 Mt grading 1.03 g/t Au Eq for 712,000 Au Eq ounces and Inferred Oxide Resources total 11.1 Mt grading 0.73 g/t Au Eq for 262,000 Au Eq ounces.
  • 整个项目的矿坑限制了1,112,000美元的指示矿产资源含有黄金当量(“金当量”)盎司,推断矿产资源为54.4万盎司含有金当量盎司。(金当量基于以下公式:Au Eq g/t = Au g/t +(Ag g/t/75),并根据矿山作业期间金和银回收率的历史差异进行了调整,如MRE所述)。
  • 项目范围内指定矿产资源的平均品位为1.14 g/t Au Eq;项目范围推断矿产资源的平均品位为1.00 g/t Au Eq。
  • 已指示 氧化物 资源总量为 2160 万吨,金当量品位为 1.03 克/吨,金当量为 712,000 盎司和推断的 氧化物 资源总量为 1110 万吨,金当量品位为 0.73 克/吨,金当量盎司 262,000 个。

Corporate Financings: The Company closed two equity financings during 2023, the first closing in February and March, the second closing in September (please see Company press releases dated February 28, March 8, and September 1, 2023). Combined, the financings raised over $5.1M, leaving Lahontan well-financed to aggressively pursue its exploration and mine development programs.

企业融资: 公司在2023年完成了两次股权融资,第一次在2月和3月完成,第二次在9月收盘(请参阅2023年2月28日、3月8日和9月1日的公司新闻稿)。这些融资共筹集了超过510万美元,使Lahontan有充足的资金来积极开展其勘探和矿山开发计划。

Excellent Drilling Results in the Slab-Calvada area at Santa Fe: Lahontan completed 3,687 metres of reverse-circulation drilling in 18 holes in the Slab-Calvada resource area at the Santa Fe Mine project. The drilling targeted extensions of known resources, defined by the Company's NI 43-101 compliant Technical Report and MRE*, beyond the conceptual pit shells used in the MRE. Drilling highlights include:

圣达菲斯拉布-卡尔瓦达地区的出色钻探结果: 拉洪坦在圣达菲矿项目的斯拉布-卡尔瓦达资源区的18个孔中完成了3687米的反循环钻探。该钻探的目标是扩展已知资源,该资源由该公司符合 NI 43-101 标准的《技术报告》和 MRE* 定义,但不局限于 MRE 中使用的概念矿壳。钻探亮点包括:

  • 38.1 metres grading 0.87 g/t Au and 2.5 g/t Ag (0.89 gpt Au Eq) of oxide metallurgical domain mineralization in drill hole CAL23-004R including 10.6 metres grading 2.02 g/t Au and 2.4 g/t Ag (2.04 gpt Au Eq).
  • 82.3 metres grading 0.68 g/t Au and 2.0 g/t (0.70 gpt Au Eq) of oxide metallurgical domain mineralization in drill hole CAL23-001R, including 21.3 metres grading 0.93 gpt Au and 1.9 gpt Ag (0.95 gpt Au Eq).
  • CAL23-004R 钻孔中 38.1 米的氧化物冶金域矿化含量为 0.87 g/t Au 和 2.5 g/t Ag(0.89 gpt Au Eq),包括品位为 2.02 g/t Au 和 2.4 g/t Ag(2.04 gpt Au Eq)的 10.6 米。
  • CAL23-001R 钻孔中 82.3 米金品位为 0.68 g/t 和 2.0 gpt(0.70 gpt Au Eq)的氧化物冶金域矿化,包括品位为 0.93 gpt Au 和 1.9 gpt Au(0.95 gpt Au Eq)的 21.3 米。

* Please see the Santa Fe Project Technical Report, Authors: Trevor Rabb and Darcy Baker, P. Geos. Effective Date: December 7, 2022, Report Date: March 2, 2023. The Technical Report is available on the Company's website and SEDAR

* 请参阅圣达菲项目技术报告,作者:特雷弗·拉布和达西·贝克,P. Geos。生效日期:2022年12月7日,报告日期:2023年3月2日。技术报告可在公司网站和SEDAR上查阅

The Slab-Calvada area is particularly important from a mine development perspective as gold and silver mineralization crops out at the surface, is completely oxidized, and would therefore be a logical area to resume mining operations. Lahontan believes that this drill campaign was highly successful in expanding the footprint of oxide gold and silver mineralization; this data will be included in an updated technical report as described below (please see Lahontan press releases dated June 27, July 18, and September 12, 2023 for more information).

从矿山开发的角度来看,Slab-Calvada地区尤为重要,因为金银矿化在地表露出来,被完全氧化,因此是恢复采矿作业的合理区域。Lahontan认为,这次钻探活动在扩大氧化金和银矿化的足迹方面取得了巨大成功;这些数据将包含在更新后的技术报告中,如下所述(有关更多信息,请参阅Lahontan于2023年6月27日、7月18日和9月12日发布的新闻稿)。

Plan of Operations: In March 2023, Lahontan and its consultants began work preparing an exploration Plan of Operations ("POO") for the Santa Fe Mine Project. The POO covers approximately 12.1 km2 of the 19.1 km2 Project area. The first phase of work is the completion of environmental baseline studies to document biological, cultural, and surface water resources. Completion of the environmental baseline studies allows the POO to be designed to avoid specific resource conflicts. Eventual approval of the POO by the Federal Bureau of Land Management ("BLM") will allow more surface disturbance on the property giving Lahontan the ability to continue to explore and expand the current mineral resources as well as provide baseline data that can be used in future mine permitting. Work completed to date includes:

运营计划: 2023年3月,拉洪坦及其顾问开始为圣达菲矿项目准备勘探运营计划(“POO”)。POO 覆盖大约 12.1 千米2 19.1 千米中的2 项目区域。工作的第一阶段是完成环境基线研究,以记录生物、文化和地表水资源。环境基线研究的完成使POO的设计能够避免特定的资源冲突。联邦土地管理局(“BLM”)最终批准POO将允许该物业受到更多的地表干扰,使Lahontan能够继续勘探和扩大当前的矿产资源,并提供可用于未来采矿许可的基准数据。迄今为止完成的工作包括:

  • Project initiation meeting with the BLM
  • Biological baseline survey work plan
  • Two special status plant surveys
  • First burrowing owl survey
  • Two acoustic bat surveys
  • Seeps and springs surveys
  • Majority of cultural surveys completed
  • 与 BLM 举行的项目启动会议
  • 生物基线调查工作计划
  • 两项特殊状况的工厂调查
  • 第一次洞穴猫头鹰调查
  • 两次声学蝙蝠调查
  • 渗漏和弹簧调查
  • 大多数文化调查都已完成

Upcoming work:

即将到来的工作:

  • Final cultural survey before reporting
  • Cultural reporting and agency review
  • Fall 2023 and Spring 2024 biological surveys including flowering plants and raptor surveys
  • 报告前的最终文化调查
  • 文化报道和机构审查
  • 2023 年秋季和 2024 年春季生物调查,包括开花植物和猛禽调查

West Santa Fe Acquisition: In July 2023, Lahontan announced an agreement to acquire the advanced West Santa Fe gold-silver exploration project ("West Santa Fe"; also known as Mindora), located only 13 km southwest of the Santa Fe Mine project. West Santa Fe hosts an oxidized gold-silver epithermal mineralized system in a geologic setting similar to Santa Fe. Previous exploration drilling at West Santa Fe totals over 13,000 metres in 171 drill holes; only five holes are deeper than 165 metres. Preliminary modeling of drill hole data by Lahontan geologists outlines a significant, shallow, oxidized gold and silver system.

收购西圣达菲: 2023年7月,拉洪坦宣布达成协议,收购位于圣达菲矿项目西南仅13公里处的先进的西圣达菲金银勘探项目(“西圣达菲”;也称为明多拉)。西圣达菲拥有一个氧化金银超热矿化系统,其地质环境与圣达菲类似。此前在西圣达菲的勘探钻探总量超过13,000米,共有171个钻孔;只有五个钻孔深度超过165米。Lahontan 地质学家对钻孔数据的初步建模概述了一个重要的浅层氧化金和银系统。

The acquisition agreement requires Lahontan to make payments totalling US$1.8M over a seven-year period, back-end loaded, to exercise an option to acquire a 100% interest in West Santa Fe. The option payments can be made in a combination of cash and shares at Lahontan's discretion. In addition, the Company will commit to exploration expenditures totalling US$1.4M over the same seven-year period, these expenditures should be sufficient to define an initial mineral resource estimate for West Santa Fe (please see Lahontan press releases dated May 15, July 20, August 15, and August 16, 2023 for more details).

收购协议要求Lahontan在七年内支付总额为180万美元的款项,后端装载,以行使收购西圣达菲100%权益的期权。Lahontan可以自行决定以现金和股票的组合方式支付期权。此外,该公司将承诺在同一个七年期内共计140万美元的勘探支出,这些支出应足以确定西圣达菲的初步矿产资源估算(更多细节请参阅2023年5月15日、7月20日、8月15日和8月16日的Lahontan新闻稿)。

Lahontan also acquired an additional 794 hectares of mineral rights at West Santa Fe by staking 95 unpatented lode mining claims; the Project now covers a of total 19.7 km2 (please see Lahontan press release dated May 31, 2023). The Lahontan geologic team concluded that there was potential for significant resource expansion outside the original West Santa Fe claim group. The new unpatented mining claims also cover areas that could be used for potential future mining infrastructure such as heap-leach facilities.

拉洪坦还通过质押95项未获专利的矿脉采矿权在西圣达菲又获得了794公顷的矿产权;该项目现在总覆盖19.7千米2 (请参阅 2023 年 5 月 31 日的 Lahontan 新闻稿)。拉洪坦地质小组得出结论,在最初的西圣达菲索赔群体之外有可能进行重大资源扩张。新的未获专利的采矿索赔还涵盖了可用于未来潜在采矿基础设施(例如堆浸设施)的区域。

Expand Santa Fe Mine Project: Lahontan significantly expanded its land holdings at its flagship Santa Fe Mine project by staking 98 unpatented lode mining claims covering over 7.5 km2 in November 2023. The newly staked claims cover possible extensions to the Slab gold and silver resources*, other exploration targets covered by young gravel, and a vast area of flat terrain that could be suitable for mine infrastructure such as heap leach pads and waste rock dumps. The Santa Fe Mine now covers over 26.4 km2 adding to the 64.1 km2 the Company controls in Nevada's prolific Walker Lane.

扩大圣达菲矿山项目: Lahontan通过提出98份覆盖超过7.5公里的未获专利的矿脉采矿索赔,大幅扩大了其旗舰圣达菲矿项目的土地持有量2 2023 年 11 月。新提出的索赔涵盖了板坯金银资源*的可能延伸部分、由幼砾覆盖的其他勘探目标以及可能适合堆浸垫和废石堆放场等矿山基础设施的大片平坦地形。圣达菲矿现在的覆盖范围超过26.4千米2 再加上 64.1 千米2 该公司控制着内华达州多产的沃克巷。

Metallurgical Data Review: The data review was completed by Kappes, Cassiday and Associates ("KCA") of Reno, Nevada, a global leader in metallurgical and process consulting. KCA reviewed metallurgical test work on oxide gold and silver mineralization completed by previous operators of the Santa Fe Mine as well as production data. When recovery estimates of the individual deposits are applied to the MRE shown in the Santa Fe Mine Technical Report*, it results in weighted project-wide gold recoveries of 74.4% for gold and 29.0% for silver at a 1⁄2-inch crush size from oxide mineralization (please see Lahontan press release dated January 22, 2024 for more information).

冶金数据审查: 数据审查由内华达州里诺市的Kappes、Cassiday and Associates(“KCA”)完成,该公司是冶金和工艺咨询领域的全球领导者。KCA审查了圣达菲矿前运营商完成的氧化金和银矿化冶金测试工作以及生产数据。当将单个矿床的回收率估计值应用于圣达菲矿技术报告*中显示的MRE时,在1⁄2英寸的压碎量下,整个项目的黄金加权回收率为74.4%,银的加权回收率为29.0%(有关更多信息,请参阅2024年1月22日的Lahontan新闻稿)。

KCA believes that there is sufficient data available to establish recovery ranges of oxide gold and silver mineralization for inclusion in a Preliminary Economic Assessment ("PEA"). This is a result of previous operational data, and the amount of column leach testing available on the component that makes up the bulk of the resource (the Santa Fe pit resource).

KCA认为,有足够的数据可以确定氧化金和银矿化的回收范围,以纳入初步经济评估(“PEA”)。这是先前的运营数据,以及对构成大部分资源的组件(圣达菲矿坑资源)进行的柱浸测试量的结果。

Plans and Catalysts for 2024: Kimberly Ann, Founder, CEO, President and Director provided the following summary of Company objectives for 2024: "Certainly 2023 was an enormous year for the Company, establishing the size and scale of oxide mineral resources at Santa Fe and clearly moving Lahontan from being a pure explorer to a future mine developer. As we have outlined, the two critical paths going forward in 2024 for the Company will be completing a PEA for Santa Fe and submitting a Plan of Operations to the Federal Bureau of Land Management. These two key steps set the stage for a potential Santa Fe production decision in 2024. We are currently evaluating proposals from multiple prominent consulting groups to prepare the Santa Fe PEA. We expect to select a group to lead the PEA process shortly.

2024年的计划和催化剂: 创始人、首席执行官、总裁兼董事金伯利·安对2024年的公司目标进行了以下总结:“当然,2023年对公司来说是重要的一年,它确定了圣达菲氧化物矿产资源的规模和规模,显然使拉洪坦从纯粹的勘探公司转变为未来的矿山开发商。正如我们已经概述的那样,公司在2024年前进的两条关键路径将是完成圣达菲的PEA并向联邦土地管理局提交运营计划。这两个关键步骤为2024年圣达菲的潜在生产决策奠定了基础。我们目前正在评估多个知名咨询团体的提案,以准备圣达菲PEA。我们预计很快会选择一个小组来领导PEA流程。

Simultaneously, we intend to design and permit a Phase one drill program for West Santa Fe, evaluate further drilling at the Santa Fe Mine project, and of course, continue to seek out opportunities that allow the Company to jump-start the growth curve."

同时,我们打算设计并批准西圣达菲的第一阶段钻探计划,评估圣达菲矿项目的进一步钻探,当然,还将继续寻找机会,使公司能够快速启动增长曲线。”

About Lahontan Gold Corp.

关于拉洪坦黄金公司

Lahontan Gold Corp. is a fully financed Canadian mine development and mineral exploration company that holds, through its US subsidiaries, four top-tier gold and silver exploration properties in the Walker Lane of mining friendly Nevada. Lahontan's flagship property, the 26.4 km2 Santa Fe Mine, had past production of 345,000 ounces of gold and 711,000 ounces of silver between 1988 and 1995 from open pit mines utilizing heap-leach processing (Nevada Bureau of Mines and Geology, 1995). The Santa Fe Mine has a Canadian National Instrument 43-101 compliant Indicated Mineral Resource of 1,112,000 oz Au Eq (grading 1.14 g/t Au Eq) and an Inferred Mineral Resource of 544,000 oz Au Eq (grading 1.00 g/t Au Eq), all pit constrained (Au Eq is inclusive of recovery, please see Santa Fe Project Technical Report*). The Company will continue to aggressively explore Santa Fe during 2024 and begin the process of evaluating development scenarios to bring the Santa Fe Mine back into production. Anthony Gesualdo, CPG, Consulting Geologist to Lahontan Gold Corp., is the Qualified Person for the Company and approved the technical content of this news release. For more information, please visit our website:

Lahontan Gold Corp. 是一家资金充足的加拿大矿山开发和矿产勘探公司,通过其美国子公司在矿业友好型内华达州沃克巷拥有四处顶级金银勘探地产。拉洪坦的旗舰酒店,26.4 千米2 圣达菲矿过去在1988年至1995年间利用堆浸处理的露天矿山生产了34.5万盎司黄金和71.1万盎司白银(内华达矿业和地质局,1995年)。圣达菲矿拥有符合加拿大国家仪器 43-101 标准的指示矿产资源 1,112,000 盎司金当量(金当量等级为1.14 g/t Au Eq),推断矿产资源为54.4万盎司金当量(品位为1.00 g/t Au Eq),均受矿坑限制(金当量包含回收量,请参阅圣达菲项目技术报告*)。该公司将在2024年继续积极勘探圣达菲,并开始评估开发情景,以使圣达菲矿恢复生产。拉洪坦黄金公司的咨询地质学家CPG安东尼·格苏尔多是该公司的合格人士,他批准了本新闻稿的技术内容。欲了解更多信息,请访问我们的网站:

* Please see the Santa Fe Project Technical Report, Authors: Trevor Rabb and Darcy Baker, P. Geos. Effective Date: December 7, 2022, Report Date: March 2, 2023. The Technical Report is available on the Company's website and SEDAR.

* 请参阅圣达菲项目技术报告,作者:Trevor Rabb 和 Darcy Baker,P. Geos。生效日期:2022年12月7日,报告日期:2023年3月2日。技术报告可在公司网站和SEDAR上查阅。

On behalf of the Board of Directors

代表董事会

Kimberly Ann

金伯利安

Founder, CEO, President, and Director

创始人、首席执行官、总裁兼董事

FOR FURTHER INFORMATION, PLEASE CONTACT:

欲了解更多信息,请联系:

Lahontan Gold Corp.
Kimberly Ann
Founder, Chief Executive Officer, President, Director

拉洪坦黄金公司
金伯利安
创始人、首席执行官、总裁、董事

Phone: 1-530-414-4400
Email: Kimberly.ann@lahontangoldcorp.com

电话:1-530-414-4400
电子邮件:Kimberly.ann@lahontangoldcorp.com

Cautionary Note Regarding Forward-Looking Statements:

关于前瞻性陈述的警示说明:

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. Except for statements of historical fact, this news release contains certain "forward-looking information" within the meaning of applicable securities law. Forward-looking information is frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or "will" occur. Forward-looking statements are based on the opinions and estimates at the date the statements are made and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those anticipated in the forward-looking statements including, but not limited to delays or uncertainties with regulatory approvals, including that of the TSXV. There are uncertainties inherent in forward-looking information, including factors beyond the Company's control. The Company undertakes no obligation to update forward-looking information if circumstances or management's estimates or opinions should change except as required by law. The reader is cautioned not to place undue reliance on forward-looking statements. Additional information identifying risks and uncertainties that could affect financial results is contained in the Company's filings with Canadian securities regulators, which filings are available at

多伦多证券交易所风险交易所及其监管服务提供商(该术语在多伦多证券交易所风险交易所的政策中定义)均不对本新闻稿的充分性或准确性承担责任。除历史事实陈述外,本新闻稿包含适用证券法所指的某些 “前瞻性信息”。前瞻性信息通常以 “计划”、“期望”、“项目”、“打算”、“相信”、“预测”、“估计” 等词语为特征,或某些事件或条件 “可能” 或 “将” 发生的陈述。前瞻性陈述基于陈述发表之日的观点和估计,受各种风险和不确定性以及其他因素的影响,这些因素可能导致实际事件或结果与前瞻性陈述中的预期存在重大差异,包括但不限于监管机构批准(包括多伦多证券交易所的批准)的延迟或不确定性。前瞻性信息固有的不确定性,包括公司无法控制的因素。除非法律要求,否则如果情况或管理层的估计或意见发生变化,公司没有义务更新前瞻性信息。提醒读者不要过分依赖前瞻性陈述。确定可能影响财务业绩的风险和不确定性的其他信息包含在公司向加拿大证券监管机构提交的文件中,这些文件可在以下网址查阅

SOURCE: Lahontan Gold Corp.

来源:Lahontan Gold Corp.