share_log

SolGold PLC Announces Completion of New Cascabel Pre-Feasibility Study

SolGold PLC Announces Completion of New Cascabel Pre-Feasibility Study

SolGold PLC宣布完成新的Cascabel预可行性研究
Accesswire ·  02/16 02:20

Announces Successful Completion of New Cascabel Pre-Feasibility Study with
Significantly Reduced Initial Capital Cost and 24% Internal Rate of Return

宣布成功完成新的Cascabel预可行性研究
显著降低了初始资本成本和24%的内部回报率

  • $5.4bn pre-tax Net Present Value ("NPV8%") and 33% internal rate of return ("IRR")
  • $3.2bn after-tax NPV8%, 24% IRR and 4-year payback period from the start of processing[1]
  • Average production[2] of 123ktpa of copper, 277kozpa of gold and 794kozpa of silver - 182ktpa copper equivalent ("CuEq")[3] - with peak[4] copper production of 216ktpa (370ktpa CuEq)
  • Pre-production capital of $1.55bn for the initial mine development, first process plant module and infrastructure
  • 85% of Mineral Reserves are classified as Proven in updated Mineral Reserve Estimate
  • Initial 28-year mine plan of 540Mt containing 3.2Mt Cu @ 0.60%, 9.4Moz Au @ 0.54 g/t and 28Moz Ag @ 1.62 g/t based on the updated Mineral Reserve Estimate[5]
  • The Project economics have been calculated based on the economic terms and conditions previously negotiated with the Ecuadorian Government[6]
  • 54亿美元的税前净现值(“NPV”)8%“) 和 33% 的内部收益率 (“IRR”)
  • 32 亿美元的税后净现值8%,24% 的内部收益率和自处理之日起的 4 年投资回收期[1]
  • 平均产量[2] 123ktpa 的铜、277kozpa 的金和 794kozpa 的银 — 182ktpa 铜当量(“cueQ”)[3] -有峰值[4] 铜产量为216ktpa(370ktpa cueQ)
  • 15.5亿美元的预生产资本,用于初始矿山开发、第一个加工厂模块和基础设施
  • 在更新的矿产储量估算中,85% 的矿产储量被归类为已探明储量
  • 根据最新的矿产储量估计,最初的 28 年采矿计划为 540 吨,含有 3.2Mt Cu @ 0.60%、9.4Moz Au @ 0.54 g/t 和 28Moz Ag @ 1.62 g/t[5]
  • 项目经济是根据先前与厄瓜多尔政府谈判的经济条款和条件计算得出的[6]

BISHOPSGATE, UK / ACCESSWIRE / February 16, 2024 / SolGold (LSE:SOLG)(TSX: SOLG) is pleased to announce the successful completion of a new Pre-Feasibility Study ("PFS" or "Study"), prepared in accordance with National Instrument 43-101 ("NI 43-101") that supports a Phased Block Cave Mine at its flagship Cascabel Project ("Cascabel" or "Project") in Ecuador. Cascabel is 100%-owned through SolGold's Ecuadorian subsidiary Exploraciones Novomining S.A. ("ENSA"). All dollar amounts are quoted in US Dollars.

英国毕晓普斯盖特/ACCESSWIRE/2024年2月16日/SolGold(伦敦证券交易所股票代码:SOLG)(多伦多证券交易所股票代码:SOLG)欣然宣布,一项新的预可行性研究(“PFS” 或 “研究”)已成功完成,该研究根据国家仪器43-101(“NI 43-101”)编写,支持其旗舰卡斯卡贝尔项目(“Cascabel” 或 “项目”)的分阶段区块洞穴矿”)在厄瓜多尔。Cascabel由SolGold的厄瓜多尔子公司Exploraciones Novomining S.A.(“ENSA”)100%持有。所有美元金额均以美元报价。

Key Highlights of the Pre-Feasibility Study

预可行性研究的主要亮点

  • Excellent economic viability of a Cascabel Phased Approach Block Cave Mine
  • +$1bn initial capital expenditure savings compared to previous estimates, reflecting efficient project development strategies, lower technical risk attributed to the phased strategy
  • Potential for accelerated cash flow and project development
  • The current Cascabel mine plan reflects the profitable exploitation of only 18% of the Alpala measured and indicated mineral resource through a 28-year mine life - the size of the entire resource indicates the mine's potential to be a multi-generational mining asset
  • Strong commitment to responsible and sustainable mining practices, including the use of renewable energy (hydropower) and an environmentally conscious Project footprint reduction
  • Cascabel 分阶段进场区块洞穴矿具有卓越的经济可行性
  • 与先前的估计相比,初始资本支出节省了超过10亿美元,这反映了有效的项目开发策略,分阶段战略带来的技术风险较低
  • 加速现金流和项目开发的潜力
  • 当前的卡斯卡贝尔矿山计划反映了在28年的矿山寿命中仅对Alpala测定和指示矿产资源的18%的盈利开采——整个资源的规模表明该矿有潜力成为多代采矿资产
  • 对负责任和可持续采矿行为的坚定承诺,包括使用可再生能源(水力发电)和减少具有环保意识的项目足迹

Scott Caldwell, SolGold's CEO and President of SolGold Ecuador, commented:

SolGold首席执行官兼厄瓜多尔SolGold总裁斯科特·考德威尔评论说:

"Cascabel is not just a mining project; it's a promise of responsible mining, lasting value for all stakeholders and a sustainable legacy for the planet. With reduced capital needs and lower risk compared to previous approaches, together with our ongoing commitment to sustainability and responsible mining, Cascabel is more than copper and gold; it's a story of innovation, collaboration and a vision for a greener and more prosperous tomorrow for the people of Ecuador. This Study was conducted with the best outcomes for all our stakeholders in mind."

“Cascabel不仅仅是一个采矿项目;它承诺负责任的采矿,为所有利益相关者带来持久的价值,并为地球留下可持续的遗产。与以前的方法相比,资本需求减少,风险更低,再加上我们对可持续发展和负责任采矿的持续承诺,Cascabel不仅仅是铜和金;它是一个创新、合作的故事,也是厄瓜多尔人民对更绿色、更繁荣明天的愿景。这项研究是在考虑所有利益相关者的最佳结果的情况下进行的。”

Summary of Cascabel PFS Results

Cascabel PFS 结果摘要

Table 1: Economic and Operating Summary

表 1:经济和运营摘要

Key PFS Outcomes (US$)

Base Case

Economic Assumptions Copper ($/lb)

$3.85

Gold ($/oz)

$1,750

Silver ($/oz)

$22.50

Operating Parameters Throughput

Phase 1: 12Mtpa; Phase 2: 24Mtpa

Initial Project LOM

28 years

Total Ore Mined

540 Mt

Average Copper Grade / Recovery

0.60% | 88.7%

Average Gold Grade / Recovery

0.54 g/t | 72.9%

Average Silver Grade / Recovery

1.62 g/t | 65.7%

Production Total CuEq Produced

4.3 Mt

Total Copper Produced

2.9 Mt

Total Gold Produced

6.9 Moz

Total Silver Produced

18.4 Moz

Annual CuEq Production (peak/average)

370 kt | 182 kt

Annual Copper Production (peak/average)

216 kt | 123 kt

Annual Gold Production (peak/average)

734 koz | 277 koz

Annual Silver Production (peak/average)

1,159 koz | 794 koz

Capital Pre-production

$1.55bn

Post-production

$2.57bn

Operating Costs
($/t processed)
Mining Costs

$6.2

Processing Costs

$7.4

G&A Costs

$1.0

Tailings, Port and Infrastructure Costs

$0.7

Total Operating Costs

$15.3

Cash Costs LOM Average Net Cash Cost ($/lb Cu)

$0.25

LOM Average AISC ($/lb Cu)

$0.69

Financials Pre-tax NPV8% / IRR

$5.4bn | 33%

After-tax NPV8% / IRR

$3.2bn | 24%

Capital payback period

4 years

Average Annual Free Cash Flow

(first 5 years of production)

$449m

First 10-Years Free Cash Flow Generation

$7.1bn

PFS 的关键成果(美元)

基础案例

经济假设 铜(美元/磅)

3.85 美元

黄金(美元/盎司)

1,750 美元

白银(美元/盎司)

22.50

操作参数 吞吐量

第 1 阶段:12Mtpa;第 2 阶段:24Mtpa

初始项目 LOM

28 年

开采的矿石总量

540 公吨

平均铜品位/回收率

0.60% | 88.7%

平均黄金等级/回收率

0.54 克/吨 | 72.9%

平均白银等级/回收率

1.62 克/吨 | 65.7%

制作 生产的 CueQ 总数

4.3 公吨

铜产总量

2.9 公吨

黄金总产量

6.9 Moz

白银总产量

18.4 摩兹

CueQ 年产量(峰值/平均值)

370 千克 | 182 千克

年铜产量(峰值/平均值)

216 千克 | 123 千瓦时

年黄金产量(峰值/平均值)

734 koz | 277 koz

年白银产量(峰值/平均值)

1,159 koz | 794 koz

资本 预制作

15.5 亿美元

后期制作

25.7 亿美元

运营成本
(已处理 $/t)
采矿成本

6.2 美元

处理成本

7.4 美元

并购成本

1.0 美元

尾矿、港口和基础设施成本

0.7 美元

总运营成本

15.3 美元

现金成本 LOM 平均净现金成本(美元/磅立方米)

0.25 美元

LOM 平均值 AISC(美元/磅 Cu)

0.69 美元

金融 税前净现值8% /IRR

54亿美元 | 33%

税后净现值8% /IRR

32 亿美元 | 24%

资本投资回收期

4 年

平均年度自由现金流

(生产的前 5 年)

4.49 亿美元

第一个 10 年自由现金流的产生

71 亿美元

Reduced Initial Capital Expenditure

减少了初始资本支出

Compared to previously considered development scenarios, the Phased Approach Block Cave Mine has substantially reduced the initial capital expenditure required to develop Cascabel. This approach optimizes project development by gradually scaling up operations, effectively managing costs and minimizing financial risk.

与先前考虑的开发情景相比,分阶段进场区块洞穴矿大幅减少了开发Cascabel所需的初始资本支出。这种方法通过逐步扩大运营规模、有效管理成本和最大限度地降低财务风险来优化项目开发。

After a ramp-up period of approximately two years, the initial block cave will achieve a production rate of 12 million tonnes per annum ("Mtpa"). The initial cave will extract high-grade ore, averaging approximately 1.45% CuEq for the first ten years of production. The extraction of this high-grade material will not sterilize the surrounding lower-grade ore. The mining operations will be expanded by an additional 12Mtpa, increasing to a total annual production rate of 24Mtpa in year 6. The phase 2 mill expansion is expected to be entirely funded from Project cash flow. This phased approach also allows for scaling other capital items over time, such as the tailings storage facility, the camp and mining equipment.

经过大约两年的扩建期,最初的区块洞穴将达到每年1200万吨(“Mtpa”)的产量。最初的洞穴将开采高品位的矿石,在生产的前十年中,平均CueQ约为1.45%。这种高品位材料的提取不会对周围的低品位矿石进行消毒。采矿业务将再扩大1200万吨/年,在第6年将增加到2400万吨/年的总产量。第二阶段的工厂扩建预计将完全由项目现金流提供资金。这种分阶段的方法还允许随着时间的推移扩大其他资本项目,例如尾矿储存设施、营地和采矿设备。

Lower Technical Risk

降低技术风险

The phased development strategy also contributes to a reduction in technical risk. Incrementally advancing the Project provides an opportunity to implement and fine-tune mining and processing methodologies, ensuring a more efficient and stable production process. This approach enhances the Project's overall resilience and minimizes potential challenges associated with large-scale development. A practical height-of-draw for this deposit was determined to be 400m which is considered to be more technically feasible than other alternatives.

分阶段开发战略还有助于降低技术风险。逐步推进该项目为实施和微调采矿和加工方法提供了机会,从而确保了更高效、更稳定的生产过程。这种方法增强了项目的整体弹性,并最大限度地减少了与大规模开发相关的潜在挑战。该矿床的实际开采高度被确定为400米,这被认为比其他替代方案在技术上更可行。

Accelerated Cash Flow

加速现金流

The Study's results indicate a strong potential for accelerated cash flow generation. With a reduced initial capital burden and lower technical risk, Cascabel is expected to deliver a quicker path to positive cash flow.

该研究的结果表明,加速产生现金流的潜力巨大。通过减少初始资本负担和降低技术风险,Cascabel有望更快地实现正现金流。

Commitment to Responsible Mining

对负责任采矿的承诺

SolGold remains committed to responsible and sustainable mining practices. The Company's dedication to environmental, social and governance (ESG) standards remains unwavering. Cascabel's development will continue to prioritize minimizing environmental impact, promoting community engagement and ensuring ethical practices throughout the Project's lifecycle.

SolGold仍然致力于负责任和可持续的采矿行为。公司对环境、社会和治理(ESG)标准的承诺仍然坚定不移。Cascabel的开发将继续优先考虑最大限度地减少环境影响,促进社区参与并确保在整个项目生命周期中遵循道德规范。

Integration of Renewable Energy

整合可再生能源

SolGold is proud to prioritize sustainability and environmental responsibility in the development of the Cascabel Project. The Company is actively integrating renewable energy supplied by governmental and private sources into the Project's energy supply strategy as part of a net zero commitment.

SolGold很自豪能够在卡斯卡贝尔项目的开发中优先考虑可持续发展和环境责任。作为净零承诺的一部分,该公司正在积极将政府和私人来源提供的可再生能源纳入该项目的能源供应战略。

Project Description

项目描述

Cascabel is located in northern Ecuador approximately a three hours' drive north of Quito, the capital city of Ecuador. Access is via sealed highways through the closest major centre of Ibarra, located approximately 80 km south of the property. Infrastructure in the region and throughout Ecuador is generally of a high standard, with excellent road access, power and water sources readily available in the local area.

卡斯卡贝尔位于厄瓜多尔北部,距离厄瓜多尔首都基多以北约三小时车程。通过封闭的高速公路进入,穿过最近的伊巴拉主要中心,该中心位于该物业以南约80公里处。该地区和整个厄瓜多尔的基础设施总体上处于高水准,当地拥有良好的道路交通、电力和水源。

Cascabel Project - Alpala Underground: Mineral Resource Estimate ("MRE") #4

Cascabel 项目-Alpala Underground:矿产资源估算 (“MRE”) #4

Table 2: Cascabel Project Alpala Underground Mineral Resource Estimate (Effective Date November 11, 2023)

表 2: Cascabel 项目 Alpala 地下矿产资源估算(生效日期 2023 年 11 月 11 日)

Cut-Off Grade

(CuEq%)

Resource Category

Tonnage

(Mt)

Grade

Contained Metal

CuEq

(%)

Cu

(%)

Au

(g/t)

Ag

(g/t)

CuEq

(Mt)

Cu

(Mt)

Au

(Moz)

Ag

(Moz)

0.21

Measured

1,576

0.64

0.43

0.35

1.16

10.0

6.7

17.5

58.6

Indicated

1,437

0.39

0.28

0.20

0.71

5.6

4.0

9.3

32.7

Measured + Indicated

3,013

0.52

0.35

0.28

0.94

15.6

10.7

26.8

91.3

Inferred

607

0.36

0.26

0.19

0.56

2.2

1.5

3.7

11.0

截止等级

(CUeQ%)

资源类别

吨位

(公吨)

等级

所含金属

cueQ

(%)

(%)

Au

(g/t)

Ag

(g/t)

cueQ

(公吨)

(公吨)

Au

(莫兹)

Ag

(莫兹)

0.21

已测量

1,576

0.64

0.43

0.35

1.16

10.0

6.7

17.5

58.6

已指明

1,437

0.39

0.28

0.20

0.71

5.6

4.0

9.3

32.7

已测量 + 已指示

3,013

0.52

0.35

0.28

0.94

15.6

10.7

26.8

91.3

推断

607

0.36

0.26

0.19

0.56

2.2

1.5

3.7

11.0

Notes:

注意事项:

  1. Dr Arseneau, P. Geo. Associate Consultant with SRK Consulting (Canada) is responsible for this Mineral Resource statement and is an "independent Qualified Person" as such term is defined in NI 43-101.
  2. Reasonable prospects of eventual economic extraction were assessed by enclosing the mineralised material in the block model estimate in a 3D wireframe shape that was constructed with adherence to a minimum mining unit with geometry appropriate for a block cave.
  3. The cut-off grade for the shape was defined as the cut-off grade under a breakeven, eventual economic extraction criterion. The cut-off grade of 0.21% CuEq was calculated using (copper grade (%)) + (gold grade (g/t) x 0.683).
  4. All material within this shape was reported in the Mineral Resource statement as block caving is a non-selective method, and all material extracted is treated as mill feed.
  5. The material inside the shape without a Mineral Resource category was reported as planned dilution.
  6. The resulting shape contained planned internal and edge dilution that the QP considers appropriate.
  7. Cut-off inputs included:
    1. Metal prices of Cu at US$3.60/lb and Au at US$1,700/oz,
    2. Recoveries of Cu 93% and Au 83%,
    3. Costs including mining, processing, general and administration (G&A), and off-site realization (TCRC), including royalties.
  8. The QP considers that the Mineral Resource has reasonable prospects for eventual economic extraction by an underground mass mining method such as block caving.
  9. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.
  10. Mineral Resources are reported inclusive of Mineral Reserves.
  11. Figures may not add up due to rounding.
  1. Arseneau 博士,P. Geo。SRK Consulting(加拿大)的助理顾问负责本矿产资源声明,并且是NI 43-101中定义的 “独立合格人士”。
  2. 通过将区块模型估计值中的矿化材料封装成三维线框形状,评估了最终经济开采的合理前景,该线框的构造遵循了最小采矿单元,其几何形状适合区块洞穴。
  3. 形状的临界等级被定义为盈亏平衡(最终的经济开采标准)下的临界等级。0.21% CueQ的临界等级是使用(铜品位(%))+(金品位(g/t)x 0.683)计算得出的。
  4. 矿产资源声明中报告了所有处于这种形状的材料,因为区块开采是一种非选择性方法,所有提取的材料都被视为磨机进料。
  5. 据报告,形状内没有矿产资源类别的材料按计划稀释。
  6. 由此产生的形状包含计划中的内部和边缘稀释,QP认为合适。
  7. 截止输入包括:
    1. 铜的金属价格为3.60美元/磅,金的价格为1,700美元/盎司,
    2. 铜的回收率为93%,金的回收率为83%,
    3. 成本包括采矿、加工、一般和管理(G&A)和场外实现(TCRC),包括特许权使用费。
  8. QP认为,该矿产资源具有合理的前景,可以最终通过地下大规模开采方法(例如区块洞开采)进行经济开采。
  9. 矿产资源不是矿产储量,没有显示出经济可行性。
  10. 据报告,矿产资源包括矿产储量。
  11. 由于四舍五入,数字相加可能不一致。

Cascabel Project - Alpala Underground: Mineral Reserve Estimate

卡斯卡贝尔项目-Alpala Underground:矿产储量估算

The Mineral Reserves have been estimated for a block caving method and take into account the effect of mixing indicated material with dilution from low-grade or barren material originating from within the caved zone and the overlying cave backs. The Mineral Resources reflected in MRE#4 are inclusive of the Mineral Reserve estimate, which represents only 18% of the Measured and Indicated Resource estimate. The mining practices contemplated in this study do not compromise the potential extraction of the remaining resources not included in the current mine plan.

矿产储量是通过区块洞穴探测法估算的,并考虑了将所示物质与来自洞穴区和上覆洞穴背部的低品位或贫乏材料的稀释液混合所产生的影响。MRE #4 中反映的矿产资源包括矿产储量估计值,该估计值仅占测定和指示资源估计值的18%。本研究中考虑的采矿做法不会影响当前采矿计划中未包括的剩余资源的潜在开采。

Table 3: Cascabel Project Alpala Underground Mineral Reserve Estimate

表 3: Cascabel 项目 Alpala 地下矿产储量估算

Mineral Reserve Category

Tonnage

(Mt)

Grade

Contained Metal

Cu

(%)

Au

(g/t)

Ag

(g/t)

Cu

(Mt)

Au

(Moz)

Ag

(Moz)

Proven

457.5

0.64

0.60

1.7

2.9

8.9

24.9

Probable

82.2

0.36

0.22

1.2

0.3

0.6

3.1

Total

539.7

0.60

0.54

1.6

3.2

9.4

28.0

矿产储量类别

吨位

(公吨)

等级

所含金属

(%)

Au

(g/t)

Ag

(g/t)

(公吨)

Au

(莫兹)

Ag

(莫兹)

经过验证

457.5

0.64

0.60

1.7

2.9

8.9

24.9

很可能

82.2

0.36

0.22

1.2

0.3

0.6

3.1

总计

539.7

0.60

0.54

1.6

3.2

9.4

28.0

Notes:

注意事项:

  1. CIM Definition Standards were followed for Mineral Reserves.
  2. Mineral Reserves for the Cascabel Project have an effective date of December 31, 2023
  3. The Mineral Reserve reported above was not additive to the Mineral Resource.
  4. The Mineral Reserve is based on the November 11, 2023 Mineral Resource.
  5. Totals may not match due to rounding.
  6. Mineral Reserves are reported using long-term metal prices of US$1,700/oz Au, US$3.60/lb Cu, US$19.90/oz Ag.
  7. Mineral Reserves are constrained within a block cave design, using the following input parameters: height of draw of 400 m; mixing horizon of 350 m; 15% dilution (at 350 m column height); overall operating cost of US$15.00/t; metallurgical recoveries that range from 85-92% for copper and 70-81% for gold; a footprint development cost of US$1,750/m2; cut-off value of US$15.00/t.
  8. Units are metric tonnes, metric grams, troy ounces and imperial pounds. Gold ounces and copper pounds are estimates of in-situ material and do not account for processing losses.
  9. The Mineral Reserve Estimate as of 31 December 2023 for Alpala was independently verified by Jarek Jakubec, C.Eng., FIMMM. Mr. Jakubec fulfils the requirements to be a "Qualified Person" for the purposes of NI 43-101 and is the Qualified Person under NI 43-101 for the Mineral Reserve.
  1. 矿产储量遵循了 CIM 定义标准。
  2. 卡斯卡贝尔项目的矿产储量的生效日期为2023年12月31日
  3. 上面报告的矿产储量不是矿产资源的补充。
  4. 矿产储量以 2023 年 11 月 11 日的矿产资源为基础。
  5. 由于四舍五入,总数可能不匹配。
  6. 根据长期金属价格报告矿产储量,金价为1,700美元/盎司,铜价3.60美元/磅,每盎司19.90美元。
  7. 矿产储量在区块洞穴设计中受到限制,使用以下输入参数:开采高度为400 m;混合水平为350 m;稀释量为15%(柱高为350 m);总运营成本为15.00美元/吨;冶金回收率介于铜的85-92%和黄金的70-81%之间;占地面积开发成本为1,750美元/吨;截止价值为15.00美元/吨。
  8. 单位是公吨、公制克、金衡盎司和英制磅。金盎司和铜磅是原地材料的估计值,不考虑加工损失。
  9. 阿尔帕拉截至2023年12月31日的矿产储量估计已由FIMMM的Jarek Jakubec, C.Eng. 独立验证。Jakubec先生符合NI 43-101所述 “合格人员” 的要求,并且是NI 43-101规定的矿产储备合格人士。

Mining

采矿

Underground mining will utilize the block cave mining method, a low-cost, bulk mining method. After a ramp-up period of approximately two years, the initial cave will achieve a production rate of 12Mtpa. The initial cave will extract high-grade ore, averaging 1.5% CuEq for the first ten years of operation. Extraction of this high-grade material will not sterilize surrounding lower-grade ore. The mining operations will be expanded by an additional 12Mtpa, increasing to a total annual production rate of 24Mtpa in year 6 of mine production.

地下采矿将使用区块洞穴采矿方法,这是一种低成本的批量采矿方法。经过大约两年的扩建期,最初的洞穴将达到1200万吨/年的产量。最初的洞穴将开采高品位矿石,运营的前十年平均CueQ为1.5%。提取这种高品位的材料不会对周围的低品位矿石进行消毒。采矿业务将再扩大1200万吨/年,在矿山生产的第6年将增加到2400万吨/年的总产量。

Ore from the mine will be transported to the underground primary crushers by load haul dump loaders ("LHDs") and crushed to minus 160 mm. The crushed ore will be conveyed directly to the coarse ore stockpile adjacent to the mill at the surface.

矿山中的矿石将通过负载运输卸载机(“LHD”)运送到地下初级破碎机,并粉碎至负160 mm。破碎的矿石将直接输送到磨机地表附近的粗矿石库中。

Process Plant

加工工厂

Ore will be reclaimed from the coarse ore stockpile and conveyed to a conventional semi-autogenous grinding ball mill crusher ("SABC") circuit. Slurry from the ball mill will be pumped to the flotation circuit, where concentrate will be floated, filtered and stored for transport by truck to the port site concentrate storage barn. Tailings will flow by gravity to the Tailings Storage Facility.

矿石将从粗矿石库存中回收并输送到传统的半自磨球磨机破碎机(“SABC”)回路。来自球磨机的浆料将被泵送到浮选回路,浓缩物将在那里漂浮、过滤和储存,然后由卡车运送到港口的浓缩物储存仓。尾矿将通过重力流向尾矿储存设施。

Production Plan

生产计划

Additional mining optimization studies indicated that the optimum production profile for the Cascabel Project is, to begin with a processing rate of 12Mtpa, extracting high-grade ore for 6 years, and then expanding the process plant by an additional 12Mtpa, increasing to a total processing rate of 24Mtpa. The initial 12Mtpa throughput rate is expected to be achieved six years after the start of Project development. Over the current life of mine, the plant is expected to produce 2.9 million tonnes of copper, 6.9 million ounces of gold and 18.4 million ounces of silver.

其他采矿优化研究表明,Cascabel项目的最佳生产概况是,一开始加工率为1200万吨/年,开采高品位矿石6年,然后再将加工厂扩建1200万吨/年,总加工率提高到24Mtpa。最初的1200万吨/年吞吐率预计将在项目开发开始六年后实现。在矿山目前的使用寿命中,该工厂预计将生产290万吨铜、690万盎司黄金和1,840万盎司银。

Tandayama-Ameríca (TAM) Deposit

Tandayama-America (TAM) 存款

The TAM deposit, located approximately 6 kilometres northeast of the Apala deposit, further emphasizes the significant potential of the Cascabel Project. The TAM deposit outcrops at the surface, resulting in a low strip ratio, offering an excellent opportunity to provide additional mill feed for up to 7 years and the potential for an earlier start of metal production from an open-cut mining method.

位于阿帕拉矿床东北约6公里处的TAM矿床进一步凸显了卡斯卡贝尔项目的巨大潜力。TAM 矿床在地表露出,导致带材比率低,为提供长达 7 年的额外磨机原料提供了绝佳的机会,并且有可能通过露天采矿方法提早开始金属生产。

The current evaluation of the TAM deposit is not at a PFS level and is, therefore, not included in the Cascabel Project economics presented above or in the PFS mine plan. The Company will begin the additional metallurgical testing, waste rock characteristic testing, geotechnical, hydrogeology, and detailed mine planning required to finalize planning efforts.

目前对TAM矿床的评估不在PFS水平,因此未包含在上述Cascabel项目经济学或PFS矿山计划中。该公司将开始额外的冶金测试、废岩特性测试、岩土工程、水文地质学和详细的矿山规划,以完成规划工作。

Table 4: Tandayama-Ameríca Mineral Resource Statement (Effective Date November 11, 2023)

表 4:Tandayama-America 矿产资源声明(生效日期 2023 年 11 月 11 日)

Potential

Mining Method

Cut-off Grade (CuEq %)

Resource Category

Tonnage (Mt)

Grade

Contained Metal

Cu

(%)

Au

(g/t)

CuEq

(%)

Cu

(Mt)

Au

(Moz)

CuEq

(Mt)

Open Pit

0.16

Indicated

492

0.22

0.20

0.35

1.1

3.1

1.7

Inferred

45

0.18

0.18

0.31

0.1

0.3

0.1

Underground

0.19

Indicated

230

0.26

0.18

0.39

0.6

1.3

0.9

Inferred

201

0.21

0.21

0.36

0.4

1.4

0.7

Total Indicated

722

0.23

0.19

0.36

1.7

4.5

2.6

Total Inferred

247

0.21

0.21

0.35

0.5

1.6

0.9

潜力

挖矿方法

截止等级 (CueQ%)

资源类别

吨位 (Mt)

等级

所含金属

(%)

Au

(g/t)

cueQ

(%)

(公吨)

Au

(莫兹)

cueQ

(公吨)

露天矿坑

0.16

已指明

492

0.22

0.20

0.35

1.1

3.1

1.7

推断

45

0.18

0.18

0.31

0.1

0.3

0.1

地下

0.19

已指明

230

0.26

0.18

0.39

0.6

1.3

0.9

推断

201

0.21

0.21

0.36

0.4

1.4

0.7

显示的总数

722

0.23

0.19

0.36

1.7

4.5

2.6

推断总数

247

0.21

0.21

0.35

0.5

1.6

0.9

Notes:

注意事项:

  1. Dr. Gilles Arseneau, P. Geo., Associate Consultant with SRK Consulting (Canada), is responsible for this Mineral Resource statement and is an "independent Qualified Person" as such term is defined in NI 43-101.
  2. Reasonable prospects of eventual economic extraction were assessed by:
    1. First presenting the mineralised material in the block model estimate to a conventional Lersch-Grossman open pit optimisation routine based on a cut-off grade of 0.16 % CuEq, and the cost and revenue assumptions listed below. Mineralised material inside the revenue factor one pit and above the cut-off grade were then reported in the "Open pit" section of the Mineral Resource statement.
    2. Subsequently, the remaining material was enclosed in a 3D wireframe shape that was constructed with adherence to a minimum mining unit with geometry appropriate for a block cave.
  3. The Cut-off grade for the underground shape was defined as the cut-off grade under a breakeven, eventual economic extraction criterion. The cut-off grade of 0.19% CuEq was calculated using (copper grade (%)) + (gold grade (g/t) x 0.683).
  4. All material within the underground shape was reported in the "Underground" section of the Mineral Resource statement, as block caving is a non-selective method, and all material extracted is treated as mill feed.
  5. The resulting shape contained planned internal and edge dilution that the QP considers appropriate.
  6. Cut-off/Cut-off inputs included:
    1. Metal prices of Cu at US$3.60/lb and Au at US$1,700/oz,
    2. Recoveries of Cu 93% and Au 83%,
    3. Costs including mining, processing and general and administration (G&A) and
    4. Off-site realization (TCRC), including royalties.
  7. The QP considers that the Mineral Resource has reasonable prospects for eventual economic extraction by open pit or an underground mass mining method such as block caving, as presented in the Mineral Resource statement.
  8. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.
  9. Mineral Resources are reported inclusive of those Mineral Resources that were converted to Mineral Reserves.
  10. Numbers may not add up due to rounding.
  1. SRK Consulting(加拿大)助理顾问 Gilles Arseneau, P. Geo. 博士对本矿产资源声明负责,他是 NI 43-101 中定义的 “独立合格人士”。
  2. 通过以下方式评估了最终经济开采的合理前景:
    1. 首先介绍区块模型中基于0.16%CueQ的临界等级以及下面列出的成本和收入假设,根据传统的Lersch-Grossman露天矿优化程序估算的矿化材料。然后,矿产资源报表的 “露天矿” 部分报告了收入系数一矿坑内且高于临界品位的矿化物质。
    2. 随后,剩余的材料被封闭在三维线框形状中,该线框的构造遵循了最小采矿单元,其几何形状适合区块洞穴。
  3. 地下形状的截止等级被定义为盈亏平衡(最终是经济开采标准)下的临界等级。0.19% CueQ的临界等级是使用(铜品位(%))+(金品位(g/t)x 0.683)计算得出的。
  4. 矿产资源声明的 “地下” 部分报告了地下形状的所有物质,因为区块开采是一种非选择性方法,所有开采的材料都被视为磨机进料。
  5. 由此产生的形状包含计划中的内部和边缘稀释,QP认为合适。
  6. 截止/截止输入包括:
    1. 铜的金属价格为3.60美元/磅,金的价格为1,700美元/盎司,
    2. 铜的回收率为93%,金的回收率为83%,
    3. 成本包括采矿、加工、一般和管理 (G&A) 以及
    4. 场外实现(TCRC),包括特许权使用费。
  7. QP认为,正如矿产资源声明中所述,该矿产资源具有合理的前景,可以最终通过露天矿或地下大规模开采方法(例如区块洞开采)进行经济开采。
  8. 矿产资源不是矿产储量,没有显示出经济可行性。
  9. 据报告,矿产资源包括转化为矿产储量的矿产资源。
  10. 由于四舍五入,数字相加可能不一致。

Environmental, Social and Governance ("ESG")

环境、社会和治理(“ESG”)

SolGold's unwavering commitment to the highest social and environmental sustainability of our projects positions the Company as a leading advocate of responsible mining practices, particularly in Ecuador. As SolGold advances the Cascabel Project, we remain dedicated to the highest transparency standards and ESG principles.

SolGold坚定不移地致力于实现我们项目的最高社会和环境可持续性,这使该公司成为负责任采矿行为的主要倡导者,尤其是在厄瓜多尔。随着SolGold推进Cascabel项目,我们将继续致力于最高的透明度标准和ESG原则。

In line with our corporate values, SolGold has established a comprehensive framework encapsulating the following key ESG criteria:

根据我们的企业价值观,SolGold建立了一个全面的框架,其中包含以下关键的ESG标准:

  • Environment: We are deeply committed to managing our carbon footprint and maximizing the use of renewable resources. We aim to minimize the ecological impact of our operations and contribute to a cleaner environment and biodiversity conservation.
  • Social: SolGold champions diversity and equitable wages within our workforce. We believe that fostering an inclusive workplace and ensuring fair compensation are fundamental to the well-being of our employees and the communities in which we operate.
  • Governance: SolGold is dedicated to adhering to the highest standards of governance practices. We stand for transparency, integrity, and accountability in all our operations, aligning ourselves with global best practices.
  • 环境:我们坚定地致力于管理我们的碳足迹并最大限度地利用可再生资源。我们的目标是最大限度地减少运营对生态的影响,为更清洁的环境和生物多样性保护做出贡献。
  • 社交:SolGold倡导员工队伍中的多元化和公平工资。我们认为,营造包容性的工作场所和确保公平的薪酬是我们员工和我们运营所在社区的福祉的基础。
  • 治理:SolGold致力于遵守治理实践的最高标准。我们主张所有业务的透明度、诚信和问责制,并与全球最佳实践保持一致。

Over the past decade, we have forged robust community partnerships in Ecuador underpinned by extensive engagement efforts. These relationships underscore our commitment to responsible resource development and mutual prosperity.

在过去的十年中,在广泛的参与努力的支持下,我们在厄瓜多尔建立了强大的社区伙伴关系。这些关系凸显了我们对负责任的资源开发和共同繁荣的承诺。

In accordance with Ecuadorian law, an Environmental and Sustainability Impact Assessment ("EISA") is required before obtaining authorization for construction and operations. SolGold is committed to ensuring the EISA is aligned with international standards. These standards encompass the Equator Principles, the International Finance Corporation ("IFC") Performance Standards, Environmental, Health, and Safety Guidelines, as well as the Sustainable Development Goals ("SDG"), as well as other international standards that apply to the mining sector.

根据厄瓜多尔法律,在获得施工和运营许可之前,需要进行环境和可持续发展影响评估(“EISA”)。SolGold致力于确保EISA符合国际标准。这些标准包括《赤道原则》、国际金融公司(“IFC”)绩效标准、环境、健康和安全指南,以及可持续发展目标(“SDG”),以及其他适用于采矿业的国际标准。

Furthermore, SolGold will undertake a comprehensive evaluation to manage and reduce the project's overall carbon footprint. Our initiatives will encompass maximizing the utilization of renewable energy sources, exploring electrification of mobile and fixed equipment options, optimizing operational efficiency through process integration and other innovative strategies to minimize our environmental footprint.

此外,SolGold将进行全面评估,以管理和减少该项目的整体碳足迹。我们的举措将包括最大限度地利用可再生能源,探索移动和固定设备的电气化选项,通过流程整合和其他创新策略优化运营效率,以最大限度地减少我们的环境足迹。

Our commitment to ESG principles remains unwavering, and we are dedicated to ensuring that the Cascabel Project sets the benchmark for responsible and sustainable mining practices in Ecuador and beyond.

我们对ESG原则的承诺坚定不移,我们致力于确保Cascabel项目为厄瓜多尔及其他地区的负责任和可持续采矿行为树立基准。

Sensitivity Analysis

灵敏度分析

A sensitivity analysis was performed on the Study's after-tax NPV8% to examine the sensitivity to commodity prices, capital costs and operating costs.

对该研究的税后净现值进行了灵敏度分析8% 研究对商品价格、资本成本和运营成本的敏感性。

Figure 1: After-tax NPV8% Sensitivity to Changes in Project Parameters

图 1: 税后净现值8% 对项目参数变化的敏感度

Figure 2: Metal Price and Discount Rate Sensitivity

图 2: 金属价格和折现率敏感度

Outstanding Opportunities and Upside Options

绝佳的机会和上行选择

Opportunities for further optimization of the Cascabel Project that management will continue to investigate include:

管理层将继续研究进一步优化Cascabel项目的机会包括:

  • Process plant design optimization following additional metallurgical test work focusing on improved gold recovery and other by-product recovery
  • Viability of the TAM open-cut mine to provide early mill feed
  • Continue to examine the impacts of utilizing tunnel boring technology to accelerate underground development
  • Further define the economic benefits of renewable energy, such as hydro and solar, on the project
  • Continue to examine the economic impact of the sub-level cave mining method on the upper portions of the Alpala deposit
  • Process plant design optimization following additional metallurgical test work
  • 经过额外的冶金测试工作,重点是提高黄金回收率和其他副产品回收率,优化工艺厂的设计
  • TAM 露天矿在提供早期磨机饲料方面的可行性
  • 继续研究利用隧道钻探技术加速地下开发的影响
  • 进一步定义水电和太阳能等可再生能源对该项目的经济效益
  • 继续研究亚层洞穴采矿方法对阿尔帕拉矿床上部的经济影响
  • 在额外的冶金测试工作之后优化工艺设备设计

Next Steps

后续步骤

SolGold intends to release a NI 43-101 technical report on Cascabel within 45 days of this release (the "Technical Report").

SolGold打算在本报告发布后的45天内发布关于卡斯卡贝尔的NI 43-101技术报告(“技术报告”)。

SolGold expects to commence the technical work to further advance and de-risk the Cascabel Project.

SolGold预计将开始技术工作,以进一步推进和降低卡斯卡贝尔项目的风险。

Qualified Persons

合格人员

The Qualified Persons for the "Cascabel Project, Ecuador, NI 43-101 Technical Report on Pre-Feasibility Study", which has an effective date of December 31, 2023, are detailed in the table below.

下表详细介绍了生效日期为2023年12月31日的 “厄瓜多尔卡斯卡贝尔项目,北爱尔兰州43-101预可行性研究技术报告” 的合格人员。

Category Name Company
Mineral Resource Estimate Dr. Gilles Arseneau, P. Geo. SRK Consulting (Canada) Inc.
Mineral Reserve Estimate and Mining (Underground) Jarek Jakubec, C.Eng., FIMMM SRK Consulting (Canada) Inc.
Mining (Open Pit Tandayama) Scott Wilson, CPG, SME Registered Member Resource Development Associates Inc.
Environment, Social, Tailings & Water Tim Rowles, BSc MSc FAusIMM CP RPEQ Knight Piésold Pty Ltd
Metallurgy & Process Plant Ben Adaszynski, P.Eng Sedgman Canada Ltd.
Surface Infrastructure Richard Boenke, P.Eng JDS Energy and Mining Inc.
Financial Evaluation and Marketing Carl Kottmeier, P.Eng SRK Consulting (Canada) Inc.
类别 姓名 公司
矿产资源估算 Gilles Arseneau 博士,P. Geo SRK 咨询(加拿大)有限公司
矿产储量估算和采矿(地下) Jarek Jakubec,C.Eng.,FIMMM SRK 咨询(加拿大)有限公司
采矿(露天田山矿) 斯科特·威尔逊,CPG,中小企业注册会员 资源开发协会公司
环境、社会、尾矿和水 蒂姆·罗尔斯,理学硕士 FausimM CP RPEQ Knight Pie'sold 私人有限公司
冶金和加工厂 本·阿达辛斯基,P.Eng 加拿大塞奇曼有限公司
地面基础设施 理查德·博恩克,P.Eng JDS 能源和矿业公司
财务评估和营销 卡尔·科特迈尔,P.Eng SRK 咨询(加拿大)有限公司

This announcement was approved for release by Scott Caldwell-Chief Executive Officer.

该公告已获斯科特·考德威尔首席执行官批准发布。

Certain information contained in the announcement would have been deemed inside information.

公告中包含的某些信息将被视为内幕消息。

CONTACTS

联系人

Scott Caldwell
SolGold Plc (CEO)


Tel: +44 (0) 20 3807 6996

Tavistock (Media)
Jos Simson/Gareth Tredway


Tel: +44 (0) 20 7920 3150

斯科特·考德威尔
SolGold Plc(首席执行官)


电话:+44 (0) 20 3807 6996

Tavistock(媒体)
Jos Simson/Gareth Tredway


电话:+44 (0) 20 7920 3150

ABOUT SOLGOLD

关于 SOLGOLD

SolGold is a leading resources company focused on the discovery, definition, and development of world-class copper and gold deposits and continues to strive to deliver objectives efficiently and in the interests of shareholders.

SolGold是一家领先的资源公司,专注于发现、定义和开发世界一流的铜和金矿床,并将继续努力高效地实现目标并符合股东的利益。

The Company operates with transparency and in accordance with international best practices. SolGold is committed to delivering value to its shareholders while simultaneously providing economic and social benefits to impacted communities, fostering a healthy and safe workplace, and minimizing environmental impact.

公司以透明的方式运营,并遵循国际最佳实践。SolGold致力于为股东创造价值,同时为受影响的社区提供经济和社会福利,营造健康安全的工作场所,并最大限度地减少对环境的影响。

SolGold is listed on the London Stock Exchange and Toronto Stock Exchange (LSE/TSX: SOLG).

SolGold在伦敦证券交易所和多伦多证券交易所上市(伦敦证券交易所/多伦多证券交易所:SOLG)。

See for more information. Follow us on "X" @SolGold plc

有关更多信息,请参见。在 “X” 上关注我们 @SolGold plc

CAUTIONARY NOTICE

警示通知

News releases, presentations and public commentary made by SolGold plc (the "Company") and its Officers may contain certain statements and expressions of belief, expectation or opinion which are forward looking statements, and which relate, inter alia, to interpretations of exploration results to date and the Company's proposed strategy, plans and objectives or to the expectations or intentions of the Company's Directors, including the plan for developing the Project currently being studied as well as the expectations of the Company as to the forward price of copper. Such forward-looking and interpretative statements involve known and unknown risks, uncertainties and other important factors beyond the control of the Company that could cause the actual performance or achievements of the Company to be materially different from such interpretations and forward-looking statements.

SolGold plc(“公司”)及其高管的新闻稿、陈述和公开评论可能包含某些陈述和信念、期望或观点表达,这些陈述和表达是前瞻性陈述,除其他外,与对迄今为止勘探结果和公司拟议战略、计划和目标的解释或公司董事的期望或意图有关,包括目前正在研究的项目的开发计划以及公司对以下方面的期望的远期价格铜。此类前瞻性和解释性陈述涉及已知和未知的风险、不确定性以及公司无法控制的其他重要因素,这些因素可能导致公司的实际业绩或成就与此类解释和前瞻性陈述存在重大差异。

Accordingly, the reader should not rely on any interpretations or forward-looking statements; and save as required by the exchange rules of the TSX and LSE or by applicable laws, the Company does not accept any obligation to disseminate any updates or revisions to such interpretations or forward-looking statements. The Company may reinterpret results to date as the status of its assets and projects changes with time expenditure, metals prices and other affecting circumstances.

因此,读者不应依赖任何解释或前瞻性陈述;除多伦多证券交易所和伦敦证券交易所的交易规则或适用法律的要求外,公司不承担任何发布此类解释或前瞻性陈述的最新或修订的义务。随着其资产和项目状况随时间支出、金属价格和其他影响情况而变化,公司可能会重新解释迄今为止的业绩。

This release may contain "forward‐looking information". Forward‐looking information includes, but is not limited to, statements regarding the Company's plans for developing its properties. Generally, forward‐looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved".

此版本可能包含 “前瞻性信息”。前瞻性信息包括但不限于有关公司开发房产计划的陈述。通常,前瞻性信息可以通过使用前瞻性术语来识别,例如 “计划”、“期望” 或 “不预期”、“预期”、“预算”、“预算”、“预测”、“打算”、“预期” 或 “不预期” 或 “相信”,或者此类词语的变体或陈述某些行动、事件或结果 “可能” “可能””、“将”、“可能” 或 “将被采取”、“发生” 或 “实现”。

Forward‐looking information is subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward‐looking information, including but not limited to: transaction risks; general business, economic, competitive, political and social uncertainties; future prices of mineral prices; accidents, labour disputes and shortages and other risks of the mining industry. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to, risks relating to the ability of exploration activities (including assay results) to accurately predict mineralization; errors in management's geological modelling and/or mine development plan; capital and operating costs varying significantly from estimates; the preliminary nature of visual assessments; delays in obtaining or failures to obtain required governmental, environmental or other required approvals; uncertainties relating to the availability and costs of financing needed in the future; changes in equity markets; inflation; the global economic climate; fluctuations in commodity prices; the ability of the Company to complete further exploration activities, including drilling; delays in the development of projects; environmental risks; community and non-governmental actions; other risks involved in the mineral exploration and development industry; the ability of the Company to retain its key management employees and skilled and experienced personnel; and those risks set out in the Company's public documents filed on SEDAR+ at . Accordingly, readers should not place undue reliance on forward‐looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.

前瞻性信息受已知和未知风险、不确定性和其他因素的影响,这些因素可能导致公司的实际业绩、活动水平、业绩或成就与此类前瞻性信息所表达或暗示的结果存在重大差异,包括但不限于:交易风险;一般商业、经济、竞争、政治和社会不确定性;矿产价格的未来价格;事故、劳资纠纷和短缺以及采矿业的其他风险。尽管公司试图确定可能导致实际业绩与前瞻性信息中包含的结果存在重大差异的重要因素,但可能还有其他因素导致业绩与预期、估计或预期不符。无法保证此类信息会被证明是准确的,因为实际结果和未来事件可能与此类报表中的预期存在重大差异。可能导致实际结果与此类前瞻性信息存在重大差异的因素包括但不限于与勘探活动(包括化验结果)准确预测矿化的能力有关的风险;管理层的地质建模和/或矿山开发计划中的错误;资本和运营成本与估计相差很大;目视评估的初步性质;延迟获得或未能获得所需的政府、环境或其他所需批准;相关的不确定性未来所需融资的可用性和成本;股票市场的变化;通货膨胀;全球经济环境;大宗商品价格的波动;公司完成包括钻探在内的进一步勘探活动的能力;项目开发的延迟;环境风险;社区和非政府行动;矿产勘探和开发行业涉及的其他风险;公司留住关键管理人员和熟练和经验丰富的人员的能力;以及中列出的风险公司在SEDAR+上提交的公开文件,网址为。因此,读者不应过分依赖前瞻性信息。除非根据适用的证券法,否则公司不承诺更新任何前瞻性信息。

The findings in the PFS and the implementation of the Cascabel project are subject to all the necessary approvals, permits, internal and regulatory requirements and further works. The estimates are indicative only and are subject to market and operating conditions. They should not be interpreted as guidance. The information contained herein is a summary only and is qualified in its entirety by reference to the Technical Report (as defined herein).

PFS中的调查结果和Cascabel项目的实施需要获得所有必要的批准、许可、内部和监管要求以及进一步的工作。这些估计仅是指示性的,受市场和运营条件的约束。不应将它们解释为指导。此处包含的信息仅为摘要,并参照技术报告(定义见此处)进行了全面限定。

The Company and its officers do not endorse, or reject or otherwise comment on the conclusions, interpretations or views expressed in press articles or third-party analysis.

公司及其高管不认可、拒绝或以其他方式评论新闻文章或第三方分析中表达的结论、解释或观点。

The Company recognises that the term World Class is subjective and for the purpose of the Company's projects the Company considers the drilling results at the Alpala porphyry copper-gold deposit at its Cascabel project to represent intersections of a World Class deposit on the basis of comparisons with other drilling intersections from World Class deposits, some of which have become, or are becoming, producing mines and on the basis of available independent opinions which may be referenced to define the term "World Class" (or "Tier 1").

公司认识到 “世界级” 一词是主观的,为了公司项目的目的,公司在与来自世界级矿床的其他钻探交叉点(其中一些已经成为或正在生产矿山)进行比较的基础上,将Cascabel项目Alpala斑岩铜金矿床的钻探结果视为世界级矿床的交叉点,并根据可用于定义该术语的现有独立意见 “世界一流”(或 “一级”)。

The Company considers that World Class deposits are rare, very large, long life, low cost, and are responsible for approximately half of total global metals production. World Class deposits are generally accepted as deposits of a size and quality that create multiple expansion opportunities and have or are likely to demonstrate robust economics that ensure development irrespective of position within the global commodity cycles, or whether or not the deposit has been fully drilled out, or a feasibility study completed.

该公司认为,世界级矿床稀有、非常大、寿命长、成本低,约占全球金属总产量的一半。世界级矿床通常被视为规模和质量的矿床,这些矿床可以创造多种扩张机会,并且具有或可能表现出稳健的经济效益,无论在全球大宗商品周期中处于什么位置,或者矿床是否已完全钻出,或者是否已完成可行性研究,都能确保发展。

Standards drawn from industry experts (1Singer and Menzie, 2010; 2Schodde, 2006; 3Schodde and Hronsky, 2006; 4Singer, 1995; 5Laznicka, 2010) have characterised World Class deposits at prevailing commodity prices. The relevant criteria for World Class deposits, adjusted to current long run commodity prices, are considered to be those holding or likely to hold more than 5 million tonnes of copper and/or more than 6 million ounces of gold with a modelled net present value of greater than US$1billion.

从行业专家那里得出的标准(1Singer and Menzie,2010年;2Schodde,2006年;3Schodde and Hronsky,2006年;4Singer,1995年;5Laznicka,2010年)描述了按现行大宗商品价格计算的世界级存款。经当前长期大宗商品价格调整后,世界级矿床的相关标准被视为那些持有或可能持有超过500万吨铜和/或超过600万盎司黄金、模拟净现值超过10亿美元的矿床。

The Company cautions that the Cascabel Project remains an early-stage project at this time and there is inherent uncertainty relating to any project at prior to the determination of pre-feasibility study and/or defined feasibility study.

该公司警告说,Cascabel项目目前仍处于早期阶段,在确定预可行性研究和/或确定的可行性研究之前,任何项目都存在固有的不确定性。

On this basis, reference to the Cascabel Project as "World Class" (or "Tier 1") is considered to be appropriate.

在此基础上,将Cascabel项目称为 “世界一流”(或 “1级”)被认为是适当的。

[1] Based on long-term commodity price assumptions of (US$): $3.85/lb for copper, $1,750/oz for gold and $22.50/oz for silver.

[1] 根据长期大宗商品价格假设(美元):铜为3.85美元/磅,黄金为1750美元/盎司,白银为22.50美元/盎司。

[2] Average based on years 6 - 23 at full nameplate capacity.

[2] 按满名牌容量计算的 6-23 年平均值。

[3] Assumptions for copper equivalent calculations as provided in Table 1 for commodity prices, grades and recoveries. Copper equivalent production (by-product basis) = Recovered Cu tonnes + (Au Price US$/oz) / (Cu Price US$/t) x (Recovered gold ounces) + (Ag Price US$/oz) / (Cu Price US$/t) x (Recovered silver ounces).

[3] 表1中提供了大宗商品价格、等级和回收率的铜当量计算假设。铜当量产量(副产品基础)= 回收铜吨 +(金价美元/盎司)/(铜价格美元/吨)x(回收的黄金盎司)+(银价美元/盎司)/(铜价格美元/吨)x(回收的银盎司)x(回收的白银盎司)。

[4] Peak based on year 6 from start of production.

[4] 峰值以投产之日起的第 6 年为基准。

[5] See Table 3: Cascabel Project Alpala Underground Mineral Reserve Estimate for details including cut-off assumptions.

[5] 参见表 3: Cascabel 项目 Alpala 地下矿产储量估算 了解包括截止假设在内的详细信息。

[6] See SolGold press release dated 20 July 2023 for additional details.

[6] 有关更多详细信息,请参阅 SolGold 于 2023 年 7 月 20 日发布的新闻稿。

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit .

该信息由伦敦证券交易所的新闻服务RNS提供。RNS已获得金融行为监管局的批准,成为英国的主要信息提供商。与使用和分发此信息相关的条款和条件可能适用。欲了解更多信息,请联系 rns@lseg.com 或访问。

SOURCE: SolGold PLC

来源:SolGold PLC


声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发