Copper Fox Announces 2024 Schaft Creek Program

Copper Fox Announces 2024 Schaft Creek Program

Copper Fox 宣布 2024 年沙夫特溪计划
newsfile ·  02/29 06:00

Calgary, Alberta--(Newsfile Corp. - February 29, 2024) - Copper Fox Metals Inc. (TSXV: CUU) (OTCQX: CPFXF) ("Copper Fox" or the "Company") is pleased to provide its shareholders an outline of the 2024 program for the Schaft Creek copper-gold-molybdenum-silver project located in northwestern British Columbia. The Schaft Creek project is managed through the Schaft Creek Joint Venture ("SCJV"). Teck Resources Limited ("Teck") is the Operator of the SCJV and holds a 75% interest with Copper Fox holding the remaining 25% interest.

艾伯塔省卡尔加里--(新闻档案公司,2024年2月29日)-Copper Fox Metals Inc. (TSXV: CUU)(场外交易代码:CPFXF)(“Copper Fox” 或 “公司”) 很高兴向其股东概述位于不列颠哥伦比亚省西北部的Schaft Creek铜金钼银项目的2024年计划。沙夫特溪项目由沙夫特溪合资企业(“SCJV”)管理。泰克资源有限公司(“泰克”)是SCJV的运营商,持有75%的权益,Copper Fox持有其余的25%权益。

2024 Program Highlights:

2024 年计划亮点:

  • The objective of the program is to advance the key project parameters to transition the project from Scoping to Prefeasibility Study ("PFS") stage by the end of 2024 or early in 2025.
  • Planned expenditures in 2024 are C$18.7 million to be fully funded by Teck.
  • Technical Activities:
    • Completion of the metallurgical testwork program currently underway
    • 4,500m of drilling focused on key technical areas including the Highwall, Tailing Storage Facility ("TSF"), and Rock Storage Facility ("RSF")
  • Engineering Studies:
    • Site wide geotechnical and facilities assessment of the TSF, RSF and proposed infrastructure
    • Update access road alignment
    • Update construction timeline
    • Updates to the Resource, Geologic, Structural and Slope Stability Models
  • Continue the Environmental Baseline data collection program initiated in 2023 and strengthen collaboration and engagement with the Tahltan Nation.
  • 该计划的目标是推进关键项目参数,以便在2024年底或2025年初将项目从范围界定阶段过渡到预可行性研究(“PFS”)阶段。
  • 2024年的计划支出为1,870万加元,将由泰克全额资助。
  • 技术活动:
    • 完成目前正在进行的冶金测试工作计划
    • 4500米的钻探重点是关键技术领域,包括高墙、尾矿储存设施(“TSF”)和岩石储存设施(“RSF”)
  • 工程研究:
    • 对TSF、RSF和拟议基础设施进行全场岩土工程和设施评估
    • 更新出入道路路线
    • 更新施工时间表
    • 资源、地质、结构和边坡稳定模型的更新
  • 继续执行2023年启动的环境基线数据收集计划,加强与塔尔坦民族的合作和参与。

Elmer B. Stewart, President and CEO of Copper Fox, stated, "The objective of the 2024 program is to gather necessary information to transition the project from Scoping to PFS stage by confirming key aspects of the site design and continuing the environmental baseline program while aligning these activities with the cultural and social traditions of the Tahltan Nation. The planned work activities are focused on completing investigations where required and confirming value-add opportunities which will inform the PFS."

Copper Fox总裁兼首席执行官埃尔默·斯图尔特表示:“2024年计划的目标是通过确认场地设计的关键方面和继续执行环境基准计划,同时使这些活动与塔尔坦民族的文化和社会传统保持一致,收集必要的信息,将项目从范围界定过渡到PFS阶段。计划的工作活动侧重于在需要时完成调查并确认增值机会,这将为PFS提供信息。”

2024 Program Summary
The 2024 program is expected to advance the project from Scoping to PFS stage by confirming key aspects of the site and project design layout and to advance the geotechnical model. Determination of exact drill meter allocation will occur by the end of Q1 2024 as data gathered in 2023 is being processed and interpreted. Essential camp upgrades including completion of the solar power facility is planned.

2024 年计划摘要
通过确认场地和项目设计布局的关键方面,预计2024年的项目将从范围界定阶段推进到PFS阶段,并推进岩土工程模型。随着2023年收集的数据的处理和解释,将在2024年第一季度末确定钻探仪的确切分配。计划进行必要的营地升级,包括完成太阳能发电设施。

The key components of the 2024 program for Schaft Creek are:

沙夫特溪2024年计划的关键组成部分是:

Drilling:
The 2024 program consists of 2 drills and a planned 4,500-meter geotechnical drilling campaign allocated to the proposed open pit Highwall, TMF, and RSFs. The exact drilling allocations will be determined after receiving final results of the Pit Slope Stability study and interpretation of the geotechnical data collected in 2023. This work is expected to be received by the end of March 2024.

钻探:
2024年的计划包括2次钻探和计划中的4500米岩土工程钻探活动,这些钻探活动分配给拟议的露天矿Highwall、TMF和RSF。确切的钻探分配将在收到矿坑边坡稳定性研究的最终结果和对2023年收集的岩土工程数据的解释后确定。这项工作预计将在2024年3月底之前收到。

Environmental Baseline Studies:
The 2024 program plans to continue the Environmental Baseline studies initiated in 2023 in preparation of an Environmental Assessment Permit submission. Studies will include water sampling (both surface and ground water), meteorology, hydrogeology, fish and fish habitat data collection, glacier and wildlife monitoring and cultural, heritage and archaeology studies in and around the project footprint.

环境基线研究:
2024年的计划计划继续进行2023年启动的环境基线研究,为提交环境评估许可证做准备。研究将包括水样采样(地表水和地下水)、气象、水文地质学、鱼类和鱼类栖息地数据收集、冰川和野生动物监测以及项目足迹及其周围的文化、遗产和考古研究。

The data from these studies will be used to refine the project footprint and update details and design of infrastructure components including the Highwall, RSF locations, camp design, TMF, power transmission route, haul and access road designs to inform the PFS.

这些研究的数据将用于完善项目占地面积,更新基础设施组成部分的细节和设计,包括Highwall、RSF地点、营地设计、TMF、输电路线、运输和通道设计,为PFS提供信息。

Cultural/Social:
A significant portion of the 2024 program includes strengthening collaboration with the Tahltan Nation on cultural and social traditions initiatives as well as community support programs, continued community engagement and active engagement with the Tahltan Lands Department and Archaeology Team.

文化/社交:
2024年计划的很大一部分包括加强与塔尔坦民族在文化和社会传统举措以及社区支持计划方面的合作,持续的社区参与以及与塔尔坦地政部和考古小组的积极参与。

Camp Upgrade:
Camp upgrades will include completion of the solar power facility and refurbishment of existing bunkhouses and wash facilities. These upgrades will allow for expanded future field programs and ensure safe and efficient execution of the proposed 2024 field program.

营地升级:
营地升级将包括完成太阳能发电设施以及翻新现有床铺和洗涤设施。这些升级将允许扩大未来的实地项目,并确保安全高效地执行拟议的2024年实地计划。

Elmer B. Stewart, MSc. P. Geol., President and CEO of Copper Fox, is the Company's non-independent, nominated Qualified Person pursuant to National Instrument 43-101, Standards for Disclosure for Mineral Projects, and has reviewed and approves the scientific and technical information disclosed in this news release.

埃尔默·斯图尔特,理学硕士Copper Fox总裁兼首席执行官P. Geol. 是该公司的非独立人士,根据National Instrument 43-101《矿业项目披露标准》被提名为合格人士,并已审查和批准本新闻稿中披露的科学和技术信息。

About Copper Fox
Copper Fox is a Canadian exploration and development company focused on Tier 1 copper projects in Canada and the United States. The principal assets of Copper Fox and its wholly owned subsidiaries, being Northern Fox Copper Inc. and Desert Fox Copper Inc., are the 100% ownership of the Van Dyke oxide copper project located in Miami, AZ, the 100% interest in the Mineral Mountain and Sombrero Butte porphyry copper exploration projects located in Arizona, the 25% interest in the Schaft Creek Joint Venture with Teck Resources Limited on the Schaft Creek copper-gold-molybdenum-silver project and the 100% owned Eaglehead polymetallic porphyry copper project each located in northwestern British Columbia. For more information on Copper Fox's mineral properties and investments visit the Company's website at .

关于 Copper Fox
Copper Fox是一家加拿大勘探和开发公司,专注于加拿大和美国的一级铜矿项目。Copper Fox及其全资子公司——北狐铜业公司和沙漠狐铜业公司——的主要资产是位于亚利桑那州迈阿密的范戴克氧化铜项目的100%所有权、位于亚利桑那州的矿山和Sombrero Butte斑岩铜勘探项目的100%权益、与泰克资源有限公司合资的沙夫特溪铜金钼银项目25%的权益以及 100% 拥有 Eaglehead 多金属斑岩铜项目,每个项目都位于英国西北部哥伦比亚。有关Copper Fox矿产和投资的更多信息,请访问该公司的网站,网址为。

For additional information contact: Lynn Ball at 1-844-464-2820; investor@copperfoxmetals.com.

欲了解更多信息,请联系:Lynn Ball 致电 1-844-464-2820;investor@copperfoxmetals.com。

On behalf of the Board of Directors

代表董事会

Elmer B. Stewart
President and Chief Executive Officer

埃尔默 B. 斯图尔特
总裁兼首席执行官

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多伦多证券交易所风险投资交易所及其监管服务提供商(该术语在多伦多证券交易所风险投资交易所的政策中定义)均不对本新闻稿的充分性或准确性承担责任。

Cautionary Note Regarding Forward-Looking Information
This news release contains "forward-looking information" within the meaning of the Canadian securities laws. Forward-Looking information is generally identifiable by use of the words "believes," "may," "plans," "will," "anticipates," "intends," "budgets", "could", "estimates", "expects", "forecasts", "projects" and similar expressions, and the negative of such expressions. Forward-Looking information in this news release include statements about: the 2024 program advancing the project; updating the project configuration and permitting timeline; a 4,500 m drill program; continuing environmental data collection, completion of metallurgical study; transitioning the project from Scoping to Prefeasibility Study stage; bringing forward value recognition opportunities; and a budget of C$18.7 million.

关于前瞻性信息的警示说明
本新闻稿包含加拿大证券法所指的 “前瞻性信息”。前瞻性信息通常可以通过使用 “相信”、“可能”、“计划”、“将”、“预期”、“打算”、“预算”、“可能”、“估计”、“预期”、“预测”、“项目” 等词语以及此类表述的否定词来识别。本新闻稿中的前瞻性信息包括以下方面的陈述:推进该项目的2024年计划;更新项目配置和许可时间表;4500米的钻探计划;继续收集环境数据,完成冶金研究;将项目从范围界定过渡到预可行性研究阶段;提前提供价值确认机会;以及1,870万加元的预算。

In connection with the forward-looking information contained in this news release, Copper Fox and its subsidiaries have made numerous assumptions regarding, among other things: the geological, metallurgical, engineering, financial and economic advice that Copper Fox has received is reliable and is based upon practices and methodologies which are consistent with industry standards; the speed of field studies; and the stability of economic and market conditions. While Copper Fox considers these assumptions to be reasonable, these assumptions are inherently subject to significant uncertainties and contingencies.

关于本新闻稿中包含的前瞻性信息,Copper Fox及其子公司对以下方面做出了许多假设:Copper Fox收到的地质、冶金、工程、财务和经济建议是可靠的,其基础是符合行业标准的做法和方法;实地研究的速度;以及经济和市场条件的稳定性。尽管Copper Fox认为这些假设是合理的,但这些假设本质上会受到重大的不确定性和突发性的影响。

Additionally, there are known and unknown risk factors which could cause Copper Fox's actual results, performance, or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained herein. Known risk factors include among others: the 2024 drill program and associated metallurgical and geotechnical testwork may not be completed within the timeline or at all; the environmental work and socio-economic interaction with the Tahltan Nation may not be completed within the timeline or at all; the planned expenditures for the 2024 program may be over/under-estimated; uncertainties relating to interpretation of the previous results; the overall economy may deteriorate; uncertainty as to the availability and terms of future financing; fluctuations in commodity prices and demand; currency exchange rates; and uncertainty as to timely availability of permits and other governmental approvals.

此外,还有一些已知和未知的风险因素可能导致Copper Fox的实际业绩、业绩或成就与本文所包含的前瞻性信息所表达或暗示的任何未来业绩、业绩或成就存在重大差异。已知的风险因素包括:2024年的钻探计划及相关的冶金和岩土工程测试工作可能无法在时间表内或根本无法完成;环境工作和与塔尔坦民族的社会经济互动可能无法在时间表内或根本无法完成;2024年计划的计划支出可能被高估/低估;与先前结果解释有关的不确定性;整体经济可能恶化;未来融资可用性和条款的不确定性;大宗商品的波动价格和需求; 货币汇率; 以及及时获得许可证和其他政府批准方面的不确定性.

A more complete discussion of the risks and uncertainties facing Copper Fox is disclosed in Copper Fox's continuous disclosure filings with Canadian securities regulatory authorities at . All forward-looking information herein is qualified in its entirety by this cautionary statement, and Copper Fox disclaims any obligation to revise or update any such forward-looking information or to publicly announce the result of any revisions to any of the forward-looking information contained herein to reflect future results, events, or developments, except as required by law.

Copper Fox向加拿大证券监管机构提交的持续披露文件中披露了对Copper Fox面临的风险和不确定性的更全面的讨论。除非法律要求,否则此处的所有前瞻性信息均受本警示声明的全部限制,Copper Fox不承担修改或更新任何此类前瞻性信息或公开宣布对本文包含的任何前瞻性信息进行任何修订以反映未来业绩、事件或发展的结果的义务。