Geomega Provides Update on Demo Plant, Project Design Change and Start of Site Preparation Activities at Saint-Hubert Facility

Geomega Provides Update on Demo Plant, Project Design Change and Start of Site Preparation Activities at Saint-Hubert Facility

Geomega提供有关Saint-Hubert工厂演示工厂、项目设计变更和场地准备活动开始的最新情况
GlobeNewswire ·  03/19 07:26

MONTREAL, March  19, 2024  (GLOBE NEWSWIRE) -- Geomega Resources Inc. ("Geomega" or the "Corporation") (TSX.V: GMA) (OTC: GOMRF), a developer of clean technologies for the mining, refining, and recycling of rare earths and other critical materials, is pleased to provide an update to shareholders on its rare earths recycling demonstration plant, including certain required project design modifications, and an update on site preparation activities that have started at the Saint-Hubert facility.

蒙特利尔,2024年3月19日(GLOBE NEWSWIRE)——稀土和其他关键材料的开采、提炼和回收清洁技术开发商Geomega Resources Inc.(“Geomega” 或 “公司”)(TSX.V:GMA)(场外交易代码:GOMRF)很高兴向股东介绍其稀土回收示范工厂的最新情况,包括某些必要的项目设计修改和更新现场准备活动已在圣休伯特设施开始。

Project engineering update
The past 6 months have been dedicated to bringing engineering to a sufficient level of completion that it could be tendered to the construction contractors for execution and completion of the rare earths recycling demonstration project. Procurement also progressed and various items were ordered while others were received at the Saint-Hubert facility during this period. In parallel, permitting activities have been ongoing at both the municipal and provincial levels. The objective was to be able to start the construction activities in February 2024. As a result of providing all the requested data to the governmental authorities, Geomega was notified by the municipality of Saint-Hubert, a borough within the city of Longueuil, that the sewer system capacity is not currently able to accommodate the water discharges from the cooling tower that was to be installed for the demonstration plant (please see September 20, 2023 press release for the 3D model of the originally intended layout of the plant and cooling tower). Various solutions have been evaluated by Geomega, including in collaboration with city engineers, however none were appropriate for the project due to resulting increased costs, additional unforeseeable delays, and the overall feasibility of the proposed solution. As a result, Geomega had to undertake a design change for the rare earths recycling demonstration plant.

项目工程更新
过去的6个月一直致力于使工程达到足够的完成水平,可以将其招标给建筑承包商,以执行和完成稀土回收示范项目。采购工作也取得了进展,订购了各种物品,在此期间,圣休伯特工厂收到了其他物品。同时,在市和省两级开展了许可活动。目标是能够在2024年2月开始施工活动。在向政府当局提供了所有要求的数据后,隆格伊尔市的圣休伯特市政府通知吉欧米加,下水道系统的容量目前无法容纳为示范工厂安装的冷却塔的排水(请参阅2023年9月20日新闻稿,了解该工厂和冷却塔原定布局的三维模型)。Geomega已经对各种解决方案进行了评估,包括与城市工程师的合作,但是由于导致成本增加、额外的不可预见的延误以及拟议解决方案的总体可行性,没有一个适合该项目。结果,Geomega不得不对稀土回收示范工厂进行设计变更。

Project design change from batch to continuous
Geomega's engineering team has begun a design change for the rare earths recycling demonstration plant from a batch process to a continuous 24hrs operation with smaller equipment and lower demand for utilities, most importantly in regard to the cooling requirements (chillers with a closed loop operation instead of a cooling tower with regular water discharges into the municipal sewer system). Despite the design change, the demonstration plant throughput capacity is planned to remain unchanged at 1.5 tonnes of feed material per day.

项目设计从批量变为连续设计
Geomega的工程团队已开始对稀土回收示范厂进行设计变更,从分批处理改为使用较小的设备和较低的公用事业需求连续运行24小时,最重要的是在冷却要求方面(采用闭环运行的制冷机而不是定期向市政下水道系统排放水的冷却塔)。尽管设计发生了变化,但示范工厂的吞吐能力计划保持不变,为每天1.5吨饲料。

Geomega's engineering team believes that there are advantages to the change to continuous design:

Geomega 的工程团队认为,转向持续设计有好处:

  • Continuous design is usually preferred over batch design in industrial operations and was the ultimate goal for the project in the long-term. Switching to this design now is much more applicable to the long-term market targeted by the Corporation, namely swarf recycling from NdFeB magnet factories that are being planned for Europe and North America. The first priority of the demonstration plant remains to process end of life and scrap magnets.

  • Continuous design simplifies the control system, improves the quality of the product and, therefore, has advantages on both the operating and capital costs of the demonstration plant.

  • The smaller equipment should have better availability with shorter lead times which should help the project to remain within the Corporation's timeline for the rare earths recycling demonstration plant.

  • 在工业运营中,连续设计通常比批量设计更受青睐,从长远来看,这是该项目的最终目标。现在改用这种设计更适用于公司目标的长期市场,即计划在欧洲和北美开展的钕铁硼磁体工厂的切屑回收利用。该示范工厂的首要任务仍然是处理报废和废磁铁。

  • 连续设计简化了控制系统,提高了产品质量,因此在演示工厂的运营和资本成本方面都有优势。

  • 较小的设备应具有更好的可用性,更短的交货时间,这将有助于该项目保持在公司的稀土回收示范工厂的时间表内。

Geomega is aware that such a major design change may result in significant risks. The following are some of the primary risks that were considered and are being addressed by the management and engineering teams at Geomega:

Geomega意识到,如此重大的设计变更可能会导致重大风险。以下是Geomega的管理和工程团队考虑并正在解决的一些主要风险:

  • Engineering – Batch to continuous design change is an important modification and requires a major rework of engineering documentation. The current detailed engineering package can no longer be used for construction as is, except for some sections. The new engineering package will be using components from the previous design and will help reduce some delays.

  • Procurement – The design change has a major impact on size of equipment and on equipment selection. An ongoing procurement review has already identified equipment that has been purchased and received but is no longer needed for the continuous design and has been already put for sale. Other equipment that has been ordered but not yet received was cancelled. Replacement equipment is being selected as part of the ongoing engineering rework and will be ordered as soon as possible.

  • Piloting – The batch process was piloted in 2019 and 2020 with the main objective of scaling it up and then converting to continuous process. Implementing the scale up of the process and switching from batch to continuous in one step is not optimal. On the other hand, the Corporation's R&D team has been working over the last year on continuous piloting in other similar processes. That experience gained provides the management and engineering teams with the confidence that the continuous process now proposed for the rare earths recycling demonstration plant should achieve the set product targets.

  • Feed material – Dealing with end-of-life material always had a risk of feed variability which is better to adjust to with a batch design. Switching to continuous design requires a more uniform feed which may have an impact on sourcing of material and might require blending and preparation of feed in a way that will not impose significant changes on the operation conditions.

  • 工程 — 从批量到持续的设计变更是一项重要的修改,需要对工程文档进行重大修改。除某些部分外,目前的详细工程包不能再按原样用于施工。新的工程包将使用先前设计的组件,这将有助于减少一些延迟。

  • 采购 — 设计变更对设备尺寸和设备选择有重大影响。正在进行的采购审查已经确定了已经购买和收到的设备,但不再需要进行持续设计并已开始出售。其他已订购但尚未收到的设备已取消。作为正在进行的工程返修的一部分,正在选择替换设备,并将尽快订购。

  • 试点——批处理流程于2019年和2020年试行,主要目标是扩大规模,然后转换为连续流程。逐步扩大流程规模并从批处理切换到连续流程并不是最佳选择。另一方面,该公司的研发团队在过去一年中一直在持续试点其他类似工艺。所获得的经验使管理层和工程团队相信,目前为稀土回收示范工厂提议的连续工艺应该能够实现设定的产品目标。

  • 饲料 — 处理报废材料总是存在饲料变异的风险,最好通过批量设计进行调整。切换到连续设计需要更均匀的进料,这可能会影响材料的采购,并且可能需要以不会对操作条件造成重大变化的方式来混合和制备饲料。

For ease of reference, a comparison between batch and continuous design is presented in the table below:

为了便于参考,下表列出了批量设计和连续设计之间的比较:

Batch Design

Continuous Design

Operation schedule

8-10 hrs per day

24 hrs per day

Process cooling technology

Cooling tower with regular water discharges

Chillers with closed loop operation

Magnet throughput capacity

1.5 tpd

1.5 tpd

Heating duty

1,962 kW

466 kW

Cooling duty

1,940 kW

449 kW

批量设计

持续设计

操作日程

每天 8-10 小时

每天 24 小时

过程冷却技术

定期排水的冷却塔

闭环运行的制冷机

磁体吞吐能力

1.5 吨/日

1.5 吨/日

加热负荷

1,962 千瓦

466 千瓦

冷却任务

1,940 千瓦

449 千瓦

Start of Site Preparation Activities at the Saint-Hubert Facility
Following a thorough review of the required construction activities and the ongoing design change, the engineering team was able to select several items that are not being impacted by the design change to continuous operation. In particular, Geomega has secured the services of a local construction company that will manage and execute the required work. The site preparation activities that have begun at the Saint-Hubert facility include some of the civil work that is not being affected by the design change, electrical work, installation of the required fire protection system and the HVAC system for the rare earths recycling demonstration plant. The majority of that work is expected to be completed by end of June 2024. Engineering and procurement work will continue in parallel to these site preparation activities to avoid any further delays once equipment installation and assembly is ready to commence.

圣休伯特设施场地准备活动开始
在对所需的施工活动和正在进行的设计变更进行了全面审查之后,工程团队得以选择几项不受持续运营设计变更影响的项目。特别是,Geomega已经获得了当地建筑公司的服务,该公司将管理和执行所需工作。圣休伯特工厂已开始的场地准备活动包括一些不受设计变更影响的土木工程、电气工程、安装所需的消防系统和稀土回收示范厂的暖通空调系统。其中大部分工作预计将在2024年6月底之前完成。工程和采购工作将在这些场地准备活动的同时继续进行,以避免设备安装和组装准备就绪后出现进一步的延误。

"We have been working diligently with all the stakeholders to build a sustainable solution for rare earths recycling. Although we have some challenging engineering work to do during the coming months, we are excited to finally start the site preparation activities at our Saint-Hubert facility. We believe that the proposed design modifications not only resolve the obstacle we faced with the municipality's sewer infrastructure but overall makes our process a more environmentally sustainable technological solution to REE recycling, a more robust industrial application and a better demonstration plant for our future clients to see. As design modifications and procurement progress during the coming months, we will be better positioned to provide regular updates. In addition, I would like to highlight that none of the recent developments and changes to the REE demonstration plant are expected to affect our bauxite residues valorization initiatives. Furthermore, we continue to believe that the centralized facility in Saint-Hubert is the best available option for both the demonstration plant and our other R&D activities," commented Kiril Mugerman, President & CEO of Geomega.

“我们一直在努力与所有利益相关者合作,为稀土回收建立可持续的解决方案。尽管在接下来的几个月中,我们有一些艰巨的工程工作要做,但我们很高兴终于在圣休伯特工厂开始了场地准备活动。我们认为,拟议的设计修改不仅解决了我们在市政下水道基础设施方面面临的障碍,而且总体而言,使我们的流程成为更具环境可持续性的稀土回收技术解决方案,更强大的工业应用以及更好的示范工厂供我们未来的客户观看。随着未来几个月的设计修改和采购的进展,我们将更好地提供定期更新。此外,我想强调的是,稀土矿示范工厂的最新发展和变化预计不会影响我们的铝土矿残留物估值计划。此外,我们仍然认为,位于圣休伯特的集中设施是示范工厂和其他研发活动的最佳选择。” Geomega总裁兼首席执行官基里尔·穆格曼评论道。

Addendum to the Last Press Release
Geomega would like to make an addendum to its January 26, 2024 Press Release relative to the vesting of the Restricted Share Units ("RSUs") in order to align with the policies of the TSX Venture Exchange. The change is as follows:

上次新闻稿的附录
Geomega希望在2024年1月26日发布的有关限制性股票单位(“RSU”)归属的新闻稿中补充一份附录,以符合多伦多证券交易所风险交易所的政策。变更如下:

Vesting and settlement terms as indicated in the January 26, 2024 press release: "The RSUs vest over a 2-year period in increments of 25% every 6 months and may be settled after 3 years."

2024年1月26日新闻稿中指出的归属和结算条款:“限制性股票单位在2年内以每6个月增量25%的增量进行归属,并可能在3年后结算。”

The corrected vesting and settlement terms: "The RSUs vest over a 2-year period in increments of 50% every year and may be settled after 3 years."

更正后的归属和结算条款:“限制性股票单位在2年内以每年50%的增量进行归属,并可以在3年后结算。”

The rest of the information presented in the January 26, 2024 press release remains unchanged.

2024年1月26日新闻稿中提供的其余信息保持不变。

声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息