share_log

Alta Copper Announces Robust Economics for Cañariaco With US$2.3 Billion After-Tax NPV and 24% IRR

Alta Copper Announces Robust Economics for Cañariaco With US$2.3 Billion After-Tax NPV and 24% IRR

阿尔塔铜业宣布加纳里亚科经济表现强劲,税后净现值为23亿美元,内部收益率为24%
Accesswire ·  05/15 20:00

VANCOUVER, BC / ACCESSWIRE / May 15, 2024 / Alta Copper Corp. (TSX:ATCU)(OTCQX:ATCUF)(BVL:ATCU) ("Alta Copper" or "the Company") is pleased to announce attractive economics results from the 2024 Optimized Preliminary Economic Assessment ("2024 PEA") at its 100% owned Cañariaco Project ("Cañariaco" or the "Project"), a world class porphyry copper project, located 700 km northwest of Lima. The 2024 PEA has been prepared by Ausenco Engineering Canada ULC ("Ausenco"), AGP Mining Consultants Inc. ("AGP") and Whittle Consulting Pty. Ltd., ("Whittle"), respectively leading international engineering and mining consultancy firms.

不列颠哥伦比亚省温哥华/ACCESSWIRE/2024年5月15日/阿尔塔铜业公司(多伦多证券交易所股票代码:ATCU)(OTCQX: ATCU)(BVL: ATCU)(“Alta Copper” 或 “公司”)欣然宣布其100%持股的世界级卡纳里亚科项目(“卡纳里亚科” 或 “项目”)的2024年优化初步经济评估(“2024 PEA”)的诱人经济业绩斑岩铜项目,位于利马西北700公里处。2024年的PEA由加拿大奥森科工程有限责任公司(“Ausenco”)、AGP矿业顾问公司(“AGP”)和惠特尔咨询有限公司编写。Ltd.(“Whittle”),分别是领先的国际工程和采矿咨询公司。

All values contained in this press release are reported in US dollars.

本新闻稿中包含的所有价值均以美元报告。

Cañariaco 2024 PEA Highlights

Canáriaco 2024 PEA 亮点

  • Robust Economics: Cañariaco 2024 PEA using 8% discount factor and three year trailing average metal prices of US$4.00/pound (lb) copper (Cu), US$1,850/ounce (oz) gold (Au) and US$23.00/ounce (oz) silver (Ag):
    • Base-case Pre-tax Net Present Value ("NPV8%") of US$4.1 billion and IRR of 32.4%
    • Base-case After-tax NPV8% of US$2.3 billion and Internal Rate of Return ("IRR") of 24.1%
    • Significant Upside to Higher Metal Prices - At US$4.50/lb Cu After-tax NPV8% of US$3.2 billion and IRR of 28.9% (See Table 1)
    • Highly Leveraged to Copper Price: For every US$0.25/lb Cu increase above US$$4.00 Cu approximately US$425 Million is added to the After-Tax NPV8%
  • Life-of mine ("LOM") metal production of 8,026M lb (3,642M tonnes) Cu, 1.67 million oz Au, and 33.2 million oz Ag
  • Average annual metal production (Year 1 to 10) of 347M lb (158k tonnes) Cu; 70K oz Au; 1.5 million oz Ag
  • Average annual metal production LOM of 294M lb (134K tonnes) Cu; 61K oz Au; 1.2 million oz Ag
  • After-tax Average Annual Free Cash Flow (Year 1-10) from Start of Operation: US$538 million
  • After-tax Average Annual Free Cash Flow LOM from Start of Operation: US$383 million
  • C-1 cost of $1.86/lb copper (net of by-products)
  • Total average operating cost of $11.21 per tonne processed
  • All In Costs ("AISC") of $1.96/lb copper
  • Pre-production capital cost of $2.2 billion based on leased mining equipment and including a contingency allocation of 21% on initial project capital
  • Rapid After-tax payback period of 3.1 years from initial production with a 27 year mine life
  • One of the lowest capital intensities when compared to other current global copper development projects
  • 强劲的经济学:Canariaco 2024 PEA 使用8%的折扣系数和三年来的金属平均价格为4.00美元/磅(磅)铜(Cu)、1,850美元/盎司(盎司)的黄金(Au)和23.00美元/盎司(盎司)白银(Ag):
    • 基本案例税前净现值(“净现值8%”)为41亿美元,内部收益率为32.4%
    • 基本案例税后净现值为23亿美元的8%,内部收益率(“IRR”)为24.1%
    • 金属价格上涨的重大上行空间——按每磅铜4.50美元计算,税后净现值占32亿美元的8%,内部收益率为28.9%(见表1)
    • 铜价杠杆率高:每增加0.25美元/磅铜价至4.00美元以上,税后净现值将增加约4.25亿美元
  • 矿山寿命(“LOM”)金属产量为80.26亿磅(36.42亿吨)铜、167万盎司金和3320万盎司银
  • 金属年平均产量(第 1 年至 10 年)为 3.47 亿磅(15.8 万吨)铜;7 万盎司金;150 万盎司银
  • 金属年平均产量 LOM 为 2.94 亿磅(13.4 万吨)铜;6.1 万盎司金;120 万盎司银
  • 自运营开始以来的税后平均年度自由现金流(第1-10年):5.38亿美元
  • 自运营之初的税后平均年度自由现金流LOM:3.83亿美元
  • 每磅铜的C-1成本为1.86美元(扣除副产品)
  • 每加工一吨的平均总运营成本为11.21美元
  • 每磅铜的总成本(“AISC”)为1.96美元
  • 基于租赁采矿设备的预生产资本成本为22亿美元,其中包括初始项目资本的21%的应急拨款
  • 自首次生产起3.1年的快速税后投资回收期,矿山寿命为27年
  • 与当前其他全球铜开发项目相比,这是最低的资本密集度之一

The 2024 PEA is preliminary in nature. Current published resources for both of the Cañariaco Norte and Cañariaco Sur deposits (previously reported in News Release dated January 28, 2022) includes Inferred Mineral Resources along with a significant percentage of Measured and Indicated Resources. Inferred Mineral Resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the 2024 PEA will be realized. Mineral resources that are not mineral reserves have not demonstrated economic viability.

2024年的PEA本质上是初步的。目前公布的北加纳里亚科和南加纳里亚科矿床资源(此前曾在2022年1月28日的新闻稿中报道)包括推断的矿产资源以及很大比例的实测和指示资源。推断的矿产资源在地质学上被认为过于投机,无法将其归类为矿产储量,因此无法确定2024年的PEA能否实现。非矿产储量的矿产资源尚未显示出经济可行性。

An independent technical report for the 2024 PEA,prepared in accordance with NI 43-101,will be available under the Company's SEDAR+ profile and website on or before June 7, 2024.

根据NI 43-101编写的2024年PEA的独立技术报告将于2024年6月7日当天或之前在公司的SEDAR+简介和网站上公布。

For readers to fully understand the information in this news release, they should read the technical report in its entirety when it is available, including all qualifications, assumptions, exclusions and risks. The technical report is intended to be read in its entirety and sections should not be read or relied upon out of context.

为了使读者充分理解本新闻稿中的信息,他们应在技术报告发布时完整地阅读该报告,包括所有限定条件、假设、排除和风险。技术报告旨在完整阅读,不应断章节阅读或依赖断章节。

An updated Corporate Presentation will be available on the Company's website at

更新的公司简报将在公司的网站上公布,网址为

Giulio T. Bonifacio, Executive Chair, commented "We are extremely pleased with our 2024 PEA which is well advanced as we have clearly benefited from several previous engineering studies and a wealth of experience from our external international engineering firms. This PEA will prove of great value as we advance Alta Copper to the next stage. The PEA shows that Cañariaco is clearly a Tier 1 asset that provides a long-life, large-scale copper project producing annual average copper of 158,000 tonnes per year in the first 10 years. The Cañariaco project is economically robust with considerable leverage to increasing copper prices while also possessing considerable upside through resource expansion drilling with numerous high priority drill targets identified to date at Norte, Sur and the undrilled Quebrada Verde porphyry target".

执行主席Giulio T. Bonifacio评论说:“我们对2024年的PEA感到非常满意,因为我们显然受益于先前的几项工程研究和外部国际工程公司的丰富经验。随着我们将Alta Copper推向下一阶段,该PEA将具有巨大的价值。PEA显示,Canariaco显然是一级资产,它提供了一个寿命长、规模大的铜项目,在最初的10年中,年平均铜产量为15.8万吨。卡纳里亚科项目经济稳健,对铜价上涨具有相当大的杠杆作用,同时还通过资源扩张钻探拥有可观的上升空间,迄今已在北部、南方确定了许多高优先级的钻探目标以及尚未钻探的Quebrada Verde斑岩目标”。

Table 1 - Summary of Economic Results

表 1-经济业绩摘要

AFTER-TAX (US$M, Unless Otherwise Stated)

Cu Price (US$/lb)

3.50

3.85

4.00

4.50

5.00

Undiscounted After-Tax Cash Flow (LOM)

5,887

7,572

8,293

10,677

13,055

Net Present Value (8%)

1,450

2,054

2,312

3,163

4,011

IRR (%)

18.7

22.5

24.1

28.9

33.4

Average Annual Revenue (US$M)

1,118

1,217

1,259

1,401

1,542

Average Annual EBITA

463

561

604

744

885

Average Annual Free Cash Flow (Note 3)

295

356

383

470

557

Average Annual Free Cash Flow (Year 1-10) (Note 3)

437

508

538

638

739

Payback Period (Note 3)

3.7

3.2

3.1

2.6

2.3

PRE-TAX (US$M, Unless Otherwise Stated)

Undiscounted Pre-Tax Cash Flow (LOM)

9,746

12,433

13,585

17,424

21,264

Net Present Value (8%)

2,735

3,701

4,115

5,496

6,876

IRR (%)

25.3

30.3

32.4

39.0

45.1

Mill Throughput

120,000 tpd

Average Annual Cu Production (Year 1 to 10)

347 million lbs Cu | 158K tonne Cu

Average Annual Cu Production (LOM)

294 million lbs Cu | 134K tonne Cu

C-1 Cash Costs (net of by-products) $/lb

1.86

AISC (Note 5) $/lb

1.96

Strip Ratio (Waste to Ore)

1.33 to 1

Initial Mine Life (Years)

27

Initial Project Capital

2,160

Sustaining Capital

526

Closure Cost

216

税后(除非另有说明,否则为百万美元)

铜价(美元/磅)

3.50

3.85

4.00

4.50

5.00

未贴现的税后现金流 (LOM)

5,887

7,572

8,293

10,677

13,055

净现值 (8%)

1,450

2,054

2,312

3,163

4,011

IRR (%)

18.7

22.5

24.1

28.9

33.4

平均年收入(百万美元)

1,118

1,217

1,259

1,401

1,542

年均息税折旧摊销前利润

463

561

604

744

885

平均年度自由现金流 (注三)

295

356

383

470

557

平均年度自由现金流(第 1-10 年) (注三)

437

508

538

638

739

投资回收期 (注三)

3.7

3.2

3.1

2.6

2.3

税前(除非另有说明,否则为百万美元)

未贴现的税前现金流 (LOM)

9,746

12,433

13,585

17,424

21,264

净现值 (8%)

2735

3,701

4,115

5,496

6,876

IRR (%)

25.3

30.3

32.4

39.0

45.1

磨机吞吐量

120,000 吨/日

年平均铜产量(第 1 年至 10 年)

347 百万磅铜 | 158K 吨铜

年平均铜产量 (LOM)

294 百万磅铜 | 13.4 万吨铜

C-1 现金成本(扣除副产品)美元/磅

1.86

AISC (注五) 美元/磅

1.96

剥离率(废物与矿石)

1.33 到 1

矿山初始寿命(年)

27

初始项目资本

2,160

维持资本

526

关闭成本

216

Notes
(1) Copper contributes 88% of the net revenue with the balance of 12% from gold silver credits in copper concentrate.
(2) For this analysis Gold is US$1,850/oz and Sliver is US$23/oz and remain constant with only the Copper price changing.
(3) From Commencement of Operations.
(4) Cash Costs consist of mining, processing, site G&A, off-site treatment and refining, transport, and royalties net of by-product credits (Au & Ag).
(5) AISC consists of Cash Costs plus sustaining capital and closure costs.

注意事项
(1) 铜占净收入的88%,其余的12%来自铜精矿中的金银信贷。
(2)在本分析中,黄金为每盎司1,850美元,白银为23美元/盎司,并且保持不变,只有铜价发生变化。
(3) 从运营开始之日起。
(4) 现金成本包括采矿、加工、场地并购、场外处理和提炼、运输以及扣除副产品信贷(Au & Ag)后的特许权使用费。
(5) AISC由现金成本加上维持资本和关闭成本组成。

NPV Sensitivities

NPV 灵敏度

The sensitivity analysis provides a range of outcomes for the Project when the key parameters vary from their base-case values. The NPV estimate is most sensitive to changes of metal prices, resource grade, overall operating costs and capital costs as illustrated in Figure 1 and 2.

当关键参数与其基准值不同时,灵敏度分析为项目提供了一系列结果。净现值估计对金属价格、资源等级、总体运营成本和资本成本的变化最为敏感,如图1和图2所示。

The After-tax NPV ranges from US$2,054 billion to US$4,011 billion as the applied Copper price varies from US$3.85/lb Cu to $5.00/lb Cu.

税后净现值介于20.54亿美元至40.11亿美元之间,因为适用的铜价格从3.85美元/磅铜到每磅铜5.00美元不等。

Figure 1 - Sensitivity Summary Post - Tax NPV 8% ($M)

图 1-税后敏感度摘要 NPV 8%(百万美元)

Figure 2 - Sensitivity Summary Post - Tax IRR (%)

图 2-税后敏感度摘要 IRR (%)

Figure 3 - Cañariaco displays strong economics, generating NPV for lower capital compared to its peers
(After-Tax NPV 8% / Total Capex (US$M) | Bubble size based on annual production)

图3-Canariaco表现出强劲的经济效益,与同行相比,以较低的资本产生净现值
(税后净现值8%/总资本支出(百万美元)| 基于年产量的泡沫大小)

Source/Notes: FactSet. Technical reports
(1) Copper equivalent production calculated using stated metal prices from each project's latest technical report

来源/注释:FactSet。技术报告
(1) 铜当量产量使用每个项目最新技术报告中的规定金属价格计算

Table 2 - Detailed Results

表 2-详细结果

METRIC

Unit of Measure

Year 1-10

LOM

Plant Feed Grade

Cu

%

0.41

0.35

Au

g/t

0.08

0.07

Ag

g/t

1.86

1.59

Cu Equivalent

%

0.48

0.41

Metal Production

Cu

Mlb

3,469

8,026

Au

koz

696

1,674

Ag

Koz

14,978

33,219

Average Process Recovery

Cu

%

89.2

88.2

Au

%

66.4

63.3

Ag

%

58.5

55.3

Physicals

Total in-situ rock

Kt

1,040,399

2,739,133

Waste rock

Kt

588,138

1,562,925

Plant Feed (all grades)

Kt

452,262

1,176,207

Strip Ratio

w:o

1.30

1.33

Average Annual Production

Copper

Ktpa

158

134

公制

计量单位

1-10 年级

LOM

植物饲料等级

%

0.41

0.35

Au

g/t

0.08

0.07

Ag

g/t

1.86

1.59

铜当量

%

0.48

0.41

金属生产

美国职棒大联盟

3,469

8,026

Au

koz

696

1,674

Ag

Koz

14,978

33,219

平均流程恢复率

%

89.2

88.2

Au

%

66.4

63.3

Ag

%

58.5

55.3

体检

原地摇滚总数

kt

1,040,399

2,739,133

废石

kt

588,138

1,562,925

植物饲料(所有等级)

kt

452,262

1,176,207

条带比例

w: o

1.30

1.33

年平均产量

Ktpa

158

134

Project Description

项目描述

The Cañariaco Project is situated within the Province of Ferreñafe, in the Department of Lambayeque, in northwestern Peru, approximately 700 km northwest of Lima, the capital of Peru, and approximately 102 km northeast of the city of Chiclayo. Current access from Chiclayo to the Cañariaco Project is 150 km along a paved road followed by secondary gravel roads.

卡纳里亚科项目位于秘鲁西北部兰巴耶克省费雷纳菲省内,位于秘鲁首都利马西北约700公里处,奇克拉约市东北约102公里处。目前从奇克拉约到卡纳里亚科项目的通道为150公里,沿着铺好的道路行驶,然后是次要的碎石路。

The project area covers moderate elevations ranging from 2,200 to 3,600 metres ("m") above sea level. The copper deposits are situated on the eastern side of the continental divide and infrastructure will be on the top as well as both western and eastern sides of the divide. The topography varies from steep incised valleys at lower elevations to open grassy highlands at upper elevations. There is sufficient suitable land available within the concessions and close to the mining areas for the process plant, ancillary infrastructure and comingled waste rock and dry stack tailings facility.

该项目区域涵盖海拔2,200至3,600米(“m”)的中等海拔。铜矿床位于大陆分界线的东侧,基础设施将位于分界线的顶部以及西侧和东侧。地形各不相同,从海拔较低的陡峭山谷到海拔较高的开阔草地高地。特许权内和矿区附近有足够的合适土地可供加工厂、辅助基础设施以及混合废石和干烟堆尾矿设施使用。

The 2024 PEA contemplates that Cañariaco would be mined using conventional open pit mining equipment followed by crushing, SAG/ball mill grinding and flotation recovery of copper, gold and silver to a copper concentrate.

2024年《PEA》设想,将使用传统的露天采矿设备开采Canariaco,然后进行破碎、SAG/球磨机研磨和浮选回收铜、金和银制成铜精矿。

Cañariaco is estimated to have relatively low project capital and operating costs due to proximity to infrastructure and favourable natural setting with key features as follows:

据估计,由于邻近基础设施和有利的自然环境,卡纳里亚科的项目资本和运营成本相对较低,其主要特征如下:

  • Large scale mining and processing operation to process 120,000 tpd/43.8 million tpa with a currently planned 27 year mine life;
  • Conventional drill and blast mining, large scale electric shovels and haul trucks;
  • Conventional crushing, SAG and ball mill grinding followed by flotation recovery of copper, gold and silver to a copper concentrate;
  • Application of best practice process tailings management through comingled waste rock and filtered dry stack tailings storage;
  • Water resources available in project area exceed project requirements;
  • Low Strip Ratio life of mine of 1.33:1;
  • Power supply from existing Northern Peru power grid with connection point only 57 kms from the project; and
  • Project site located only 24 kms from existing paved highway connecting to the Pan American Highway on the west coast.
  • 大规模的采矿和加工业务,每天可加工12万吨/年4,380万吨,目前计划矿山寿命为27年;
  • 传统的钻探和爆破开采、大型电铲和运输卡车;
  • 传统的破碎、半垂和球磨机研磨,然后浮选回收铜、金和银制成铜精矿;
  • 通过混合废石和经过过滤的干烟囱尾矿储存,应用最佳做法工艺尾矿管理;
  • 项目区域的可用水资源超过项目需求;
  • 矿山带材比率低,寿命为 1. 33:1;
  • 来自秘鲁北部现有电网的电力供应,连接点距离项目仅57公里;以及
  • 项目地点距离连接西海岸泛美公路的现有铺装高速公路仅24公里。

Low Capital Cost Intensity

低资本成本密集度

Importantly, the Cañariaco project has low capital intensity when compared to several other global copper projects currently in the development stage. Key project attributes that reduce the capital cost include the following:

重要的是,与目前处于开发阶段的其他几个全球铜矿项目相比,Canariaco项目的资本密集度较低。降低资本成本的关键项目属性包括:

  • The mineralized material from Cañariaco Norte and Sur deposits are moderately competent with Axb of 53, and moderately soft rock with an average BWI 12.2 kWh/tonne, which enables high throughput utilizing a single comminution line consisting of one primary crusher, one large SAG mill and two ball mills whereas many projects with comparable throughput require two SAG mills and four ball mills;
  • The region receives significant annual rainfall and adequate fresh water is available at site eliminating the need for a desalination plant and pipeline from the coast;
  • Relatively close proximity to the national power grid reduces the capital intensity of power supply infrastructure;
  • Close proximity to an existing major transportation highway reduces access road construction cost and time;
  • Utilization of trucks to transport concentrate along existing highways to the loadout port eliminates the requirement for a concentrate pipeline;
  • The project site is in a sparsely populated area and there is no requirement for community relocation; and
  • Concentrate loadout through an existing port on the west coast of Peru eliminates need to construct a new loadout facility.
  • 来自北加那利和南加那利矿床的矿化材料产量适中,Axb为53,中等软岩为12.2 kWh/吨,利用由一台初级破碎机、一台大型半挂磨机和两台球磨机组成的单条粉碎线实现高吞吐量,而许多吞吐量相似的项目需要两台半自磨机和四台球磨机;
  • 该地区年降雨量大,现场有充足的淡水,因此无需建造海水淡化厂和沿海管道;
  • 相对靠近国家电网降低了电力供应基础设施的资本密集度;
  • 紧邻现有的主要交通高速公路,可减少道路建设成本和时间;
  • 使用卡车沿现有高速公路将浓缩物运送到装卸港,从而无需使用浓缩管道;
  • 项目地点位于人口稀少的地区,不需要社区搬迁;以及
  • 通过秘鲁西海岸的现有港口集中装载,无需建造新的装卸设施。

Figure 4 - Cañariaco possesses a strong production profile with low capital intensity (based on average annual copper equivalent production (1)
(Capital Intensity (US$/t) | Bubble size based on annual production)

图 4-Canariaco 拥有强劲的生产概况,资本密集度低(基于年平均铜当量产量 (1))
(资本强度(美元/吨)| 基于年产量的泡沫大小)

Source/Notes: Technical reports. Capital intensity equals total capex divided by average annual copper equivalent production. | (1) Copper equivalent production calculated using stated metal prices from each project's latest technical report.

来源/注释:技术报告。资本密集度等于总资本支出除以年平均铜当量产量。| (1) 铜当量产量使用每个项目最新技术报告中的规定金属价格计算。

Sustainable and Responsible Mining

可持续和负责任的采矿

The project development concept has utilized best practice technologies and will benefit from several existing external factors which will assist in making Cañariaco a very responsible, desirable and sustainable project.

项目开发理念利用了最佳实践技术,并将受益于一些现有的外部因素,这将有助于使Canáriaco成为一个非常负责任、理想和可持续的项目。

The application of filtered dry stack tailings combined with comingled waste rock storage maximizes the recycling of process water and significantly reduces freshwater requirements. In addition, this technology eliminates the need for wet tailings storage and a major tailing retainment structure and reduces associated seismic risk.

过滤后的干烟道尾矿与混合废石储存相结合,可最大限度地提高工艺用水的回收利用率,并显著减少对淡水的需求。此外,该技术消除了对湿式尾矿储存和主要尾矿保留结构的需求,并降低了相关的地震风险。

Electrical power in Northern Peru is generated predominantly by hydro which is the preferred power source from ecological and carbon emissions perspectives.

秘鲁北部的电力主要由水力发电,从生态和碳排放的角度来看,水力是首选的能源。

Electric powered overland belt conveyors, rather than haul trucks, will transport most of the mill feed and waste rock from the mining areas to the plant as well as the comingled waste and dry stack tailings facility thereby reducing fuel consumption and CO2 emissions.

电动陆上皮带输送机,而不是运输卡车,将把大部分磨机原料和废石从采矿区运送到工厂以及混合的废弃物和干堆尾矿设施,从而减少燃料消耗和二氧化碳排放。

The project is located in a sparsely populated region and at elevations above major agricultural zones.

该项目位于人口稀少的地区,海拔高于主要农业区。

Capital, Sustaining and Operating Costs

资本、维持和运营成本

The initial capital, expensed over the first four years of the Project, amounts to $2.2 billion. The sustaining capital over the remainder of LOM amounts to $526 million. Closure costs are estimated at $216 million. The project financial model incorporates a lease strategy for the purchase of the initial mining equipment whereby 20% of the mining fleet cost is capitalized and the remainder is carried as operating cost. Sustaining costs include construction of a crusher at the Sur deposit and related conveyor system to connect with the primary overland conveyor in year 16 prior to the start of mining operations at Sur.

该项目前四年的初始资本为22亿美元。LOM剩余部分的维持资本为5.26亿美元。关闭费用估计为2.16亿美元。该项目财务模型采用了购买初始采矿设备的租赁策略,根据该策略,采矿机队成本的20%被资本化,其余部分作为运营成本记账。持续成本包括在苏尔矿床建造一台破碎机和相关的输送机系统,以便在苏尔矿床开始采矿作业之前的第16年与主要陆路输送机相连。

A breakdown of capital cost is presented in the table 3 below:

资本成本细目见下表3:

Table 3 - Capital Cost Summary

表 3-资本成本摘要

Cost Area

Initial Capital

Sustaining

Total

Mine

429

193

622

Process Plant

789

25

814

Site Services and Utilities

106

-

106

Internal Infrastructure

151

216

367

External Infrastructure

42

-

42

Total Directs

1,517

434

1,951

Common Construction Facilities and Services

245

14

259

Owner's Cost

30

-

30

Total Indirects

275

14

289

Total Directs and Indirects

1,792

-

1,792

Contingency @ 20.5%

368

78

446

TOTAL

2,160

526

2,686

成本区域

初始资本

维持

总计

我的

429

193

622

加工工厂

789

25

814

站点服务和公用事业

106

-

106

内部基础架构

151

216

367

外部基础架构

42

-

42

直接总数

1,517

434

1,951

公共建筑设施和服务

245

14

259

所有者的成本

30

-

30

间接总次数

275

14

289

直接和间接总数

1,792

-

1,792

应急费用 @ 20.5%

368

78

446

总计

2,160

526

2,686

Table 4 - Life of Mine Operating Costs Summary

表 4-矿山寿命运营成本摘要

Area

Unit

US$

Unit

US$ /lb Cu

On-site Costs

Mining

$/t milled

5.68

lb Cu

0.83

Processing

$/t milled

4.97

lb Cu

0.73

Co-mingle Tailings

$/t milled

0.11

lb Cu

0.01

General & Administration

$/t milled

0.45

lb Cu

0.07

Sub-total Site Costs

$/t milled

11.21

lb Cu

1.64

Off-site Costs

Concentrate Transport

$/t dry concentrate

172.5

lb Cu

0.30

Smelting & Refining

$/t dry concentrate

155.1

lb Cu

0.27

Sub-total Off-site Costs

$/t dry concentrate

327.6

lb Cu

0.57

Total Cost On/Off Site

lb Cu

2.21

Credits (Gold, Silver)

lb Cu

(0.35)

Total Cost

lb Cu

1.86

区域

单位

美元

单位

美元/磅 Cu

现场费用

采矿

$/t 已铣削

5.68

磅 Cu

0.83

处理中

$/t 已铣削

4.97

磅 Cu

0.73

混合尾矿

$/t 已铣削

0.11

磅 Cu

0.01

一般与行政

$/t 已铣削

0.45

磅 Cu

0.07

场地成本小计

$/t 已铣削

11.21

磅 Cu

1.64

场外费用

浓缩物运输

$/t 干浓缩物

172.5

磅 Cu

0.30

熔炼和精制

$/t 干浓缩物

155.1

磅 Cu

0.27

场外费用小计

$/t 干浓缩物

327.6

磅 Cu

0.57

场内/场外总成本

磅 Cu

2.21

积分(金、银)

磅 Cu

(0.35)

总成本

磅 Cu

1.86

Cost Area

Life-of-Mine Cost (US$M)

Unit Cost (US$/t milled)

Mining

6,685

5.68

Process

5,847

4.97

Co-Mingle Facility

116

0.11

G&A

532

0.45

Total

13,180

11.21

成本区域

矿山寿命成本(百万美元)

单位成本(美元/吨)

采矿

6,685

5.68

进程

5,847

4.97

Co-Mingle 设施

116

0.11

G&A

532

0.45

总计

13,180

11.21

Social &Environmental

社会与环境

Alta Copper has been active in the Cañariaco area since 2004 and since that time has developed and established a wide range of relationships with a corporate policy of respect, shared involvement and value, mutual benefit and transparency. Communications with the local communities and public authorities at all levels continues to ensure that key stakeholders are aware of the Cañariaco project status and plans, and that the Company responds to community concerns and requests.

自2004年以来,Alta Copper一直活跃在卡纳里亚科地区,从那时起,通过尊重、共同参与和价值、互惠互利和透明的公司政策,发展和建立了广泛的关系。继续与当地社区和各级公共当局进行沟通,确保主要利益相关者了解Canariaco项目的状况和计划,并确保公司回应社区的关注和要求。

Mining

采矿

The 2024 PEAis based on open pit mining methods with conventional drilling,blasting and material loading with large electric shovels for excavation and haulage to the primary crusher using large capacity haul trucks. Independent and dedicated high-capacity electric conveyor systems will transport plant feed from the primary crusher to the process plant and waste to the comingled waste and dry stack tailings facility.

2024 PEAI 基于露天采矿方法,采用传统的钻探、爆破和装载物料,使用大型电铲进行挖掘,并使用大容量运输卡车运送到主破碎机。独立和专用的大容量电动输送系统将工厂原料从初级破碎机输送到加工厂,将废物输送到混合废物和干堆尾矿设施。

Over the life of the Cañariaco mine, two separate deposits: Cañariaco Norte ("Norte") and Cañariaco Sur ("Sur") will be mined in separate pits, with the bulk of the plant feed coming from Norte. Mining will commence in the Norte pit which will provide 100% of the process plant feed until year 16 at which point mining operations will commence at Sur. Years 17 through 25 will see mining taking place in both Norte and Sur with variable mining rates while maintaining total annual production of 43.8 million tonnes. From year 26 through end of mine life all mining will take place in Sur.

在卡纳里亚科矿的整个生命周期中,两个独立的矿床:北卡纳里亚科(“北方”)和南卡纳里亚科(“苏尔”)将在不同的矿坑中开采,大部分植物饲料来自北方。采矿将从Norte矿坑开始,该矿将提供加工厂100%的饲料,直到第16年,届时苏尔将开始采矿作业。从17年到25年,北方和南方都将进行采矿,采矿率各不相同,同时将年总产量保持在4,380万吨。从26年到矿山寿命结束,所有采矿都将在苏尔进行。

The Cañariaco open pit mining operations will have a mine life of 27 years, operating 365 days a year with a life of mine strip ratio of 1.33:1 (including pre-stripping). The mine production plan is based on mining a total of 2.72 billion tonnes of material, comprised of 1.176 billion tonnes of plant feed and 1.548 billion tonnes of waste rock over the life of the mine. Mining operations will supply the process plant at 120,000 tonnes per day or 43.8 million tonnes per annum. During the life of mine operation, annual cash-flow will vary due to annual and forecast variations in head grade, strip ratio and metal recoveries.

卡纳里亚科露天采矿业务的矿山寿命将为27年,每年运营365天,矿带寿命比为1. 33:1(包括预剥离)。矿山生产计划基于总共开采27.2亿吨材料,包括11.76亿吨植物饲料和15.48亿吨废石。采矿业务将以每天12万吨或每年4,380万吨的速度为加工厂供应。在矿山运营期间,年度现金流将因矿山品位、带材比率和金属回收率的年度和预测变化而变化。

The major mining equipment fleet will include nine (9) blast hole drills, five (5) 38 m3 electric shovels, two (2) 33 m3 front end loaders and thirty-eight (38) 290 tonne capacity haul trucks. A fleet of smaller loaders and trucks will be utilized for early mine access development and initial pre-stripping. Electric shovel major maintenance and mobile equipment replacement are carried in the mining costs. The moderate altitude of the Project avoids the need for de-rating of mine haul truck drive systems.

主要采矿设备舰队将包括九 (9) 台爆破孔钻机,五 (5) 38 m3 电动铲子,两 (2) 33 m3 前端装载机和三十八 (38) 台 290 吨的运输卡车。一支由小型装载机和卡车组成的车队将用于矿山的早期开发和初步预剥离。电铲的主要维护和移动设备的更换计入采矿成本。该项目海拔适中,无需降低矿用运输卡车驱动系统的评级。

Whittle Consulting's Mine Plan Optimization

惠特尔咨询公司的矿山计划优化

A key part of the mining plan development for this 2024 PEA included comprehensive mine plan optimization analysis by Whittle. This analysis includes a very detailed assessment of metal grades, metal prices, metal recoveries, mining and processing costs throughout the deposit, and by applying advanced computational analysis, including by the use of Whittle's proprietary Prober-E software, develops an optimized mining plan to maximize the net economic value of the mining operation. A key aspect of this mine planning strategy is that it brings forward cash flow and optimizes the net present value of the deposit. This approach involves advanced pit phasing techniques and takes advantage of variable mining cutoff grades, plant feed stockpiling and blending strategies during the life of the mine plan.

2024年PEA采矿计划制定的关键部分包括Whittle的全面矿山计划优化分析。该分析包括对整个矿床的金属等级、金属价格、金属回收率、采矿和加工成本进行非常详细的评估,并通过应用先进的计算分析,包括使用惠特尔专有的Prober-E软件,制定优化的采矿计划,以最大限度地提高采矿作业的净经济价值。该矿山规划策略的一个关键方面是,它带来了前期现金流并优化了矿床的净现值。这种方法涉及先进的矿坑分期技术,并在采矿计划生命周期内利用可变的采矿截止等级、植物饲料储存和混合策略。

Metallurgy and Processing

冶金与加工

The Cañariaco project comprises two copper-gold-silver porphyry deposits where the main copper species are primarily sulphides, predominantly chalcopyrite with lesser amounts of bornite and chalcocite. The Sur deposit also contains molybdenum however the levels did not warrant recovery for this 2024 PEA. Extensive metallurgical testwork programs on samples from Norte have been completed over previous years, providing an extensive metallurgical database for Norte. Resource development at Sur is at a much earlier stage than Norte and accordingly the metallurgical testwork completed for Sur is preliminary. However, the testwork results received to date from Sur are very good and comparable to the results for Norte confirming the amenability of conventional flotation recovery for both Norte and Sur.

卡纳里亚科项目包括两个铜金银斑岩矿床,其中主要的铜种主要是硫化物,主要是黄铜矿,其中含有少量的硼砂和辉石矿。苏尔矿床也含有钼,但这一水平并不能保证2024年PEA的回升。在过去的几年中,已经完成了对来自Norte样品的大量冶金测试计划,为Norte提供了广泛的冶金数据库。苏尔的资源开发比北方还处于早期阶段,因此,苏尔完成的冶金测试工作尚处于初步阶段。但是,迄今为止从苏尔收到的测试工作结果非常好,与Norte的结果相当,该结果证实了北方和南方都适合进行常规浮选回收。

The key metallurgical design parameters applied for process design in the 2024 PEA are as follows:

2024 PEA中应用于工艺设计的关键冶金设计参数如下:

  • Mineralized material competency/hardness: Drop Weight Test Parameter Axb 53 (75th percentile), Bond Ball Mill Work Index 12.2 kWh/tonne (75th percentile), moderately competent and moderately soft
  • Grind size P80 for flotation feed: 200 microns
  • Metallurgical recoveries (life of mine): Copper 88.2 %, Gold 63%, Silver 53%
  • Copper concentrate: 26% Copper, 3.7 g/t Gold, 74 g/t Silver.
  • 矿化材料能力/硬度:落锤重量测试参数 Axb 53 (75)th 百分位数),邦德球磨机工作指数 12.2 kWh/吨(75)第四 百分位数),能力适中,软度适中
  • 浮选进料的研磨尺寸 P80:200 微米
  • 冶金回收率(矿山寿命):铜 88.2%,金 63%,银 53%
  • 铜精矿:26% 铜、3.7 克/吨金、74 克/吨银。

Mine haul trucks will transport plant feed material to the crushing station where they will dump the material directly into a large gyratory crusher. From the crusher, plant feed material will be conveyed to a live stockpile ahead of the grinding circuit. Plant feed will be drawn from the stockpile and fed to a single 12.8 m diameter by 8.2 m EGL (Effective Grinding Length) SAG mill. SAG mill discharge will be screened to remove oversize pebbles which will be crushed in pebble crushers and returned to the SAG mill feed. SAG mill screen undersize product will be fed to two parallel 8.5 m diameter by 11.4 m EGL ball mills operating in closed circuit with cyclones to produce floatation feed at 80% minus 200 microns. The floatation circuit will comprise of rougher and cleaner flotation stages, with rougher concentrate regrinding prior to cleaner flotation. Cleaner concentrate will be dewatered using a thickener and pressure filters, then conveyed to the concentrate storage building to await transportation to the port for loadout and shipping to offshore smelters.

矿山运输卡车会将工厂的饲料运送到破碎站,在那里他们将物料直接倾倒到大型回转式破碎机中。工厂的饲料将从破碎机输送到粉碎回路之前的活库中。植物饲料将从库存中抽出,然后由8.2 m EGL(有效研磨长度)SAG 磨机输送到直径为 12.8 米的单个直径 12.8 米。将对SAG磨机的排出物进行筛选,以去除过大的卵石,这些卵石将在卵石破碎机中粉碎并返回到SAG磨机进料中。SAG 磨机筛网尺寸过小的产品将被送入两台直径为 8.5 米的平行 11.4 m 的 EGL 球磨机,这些球磨机采用闭式回路运行,产生 80% 减去 200 微米的浮选进料。浮选回路将包括更粗糙和更清洁的浮选阶段,在清洁浮选之前对更粗糙的浓缩物进行重磨。清洁的浓缩物将使用增稠剂和压力过滤器进行脱水,然后输送到浓缩物储存大楼,等待运送到港口进行装载和运往海上冶炼厂。

Waste and Tailings Handling

废物和尾矿处理

The Cañariaco process flowsheet has included Comingled Dry Stack tailing technology for waste rock and tailings placement. This technology is considered as "Best Practice" and is seeing more application within the global mining industry. The technology offers three key benefits:

卡纳里亚科的工艺流程表包括用于放置废石和尾矿的混合干堆尾矿技术。该技术被视为 “最佳实践”,正在全球采矿业中得到更多应用。该技术具有三个主要优点:

  • increases process water reclaim and recycling;
  • eliminates the requirement for wet tailings containment dams and eliminates related seismic risk,
  • reduces the size of tailing containment system footprint. Dry stack tailings treatment utilizes pressure filters to dewater process tailings to low moisture content with recovered water recycled to the process. The dry tailings filter cake produced are transported by belt conveyor to the tailings management facility where they can be placed or "stacked" with waste rock as a stable pile within the tailings facility. Combining the dry tailings sands with waste rock within the same pile enhances the overall stability of the pile and eliminates the need for two separate facilities.
  • 增加工艺用水的回收和回收利用;
  • 消除了对湿式尾矿封闭坝的要求并消除了相关的地震风险,
  • 减少了尾矿控制系统的占地面积。干堆尾矿处理利用压力过滤器对工艺尾矿进行脱水至低水分含量,并将回收的水回收到工艺中。产生的干尾矿滤饼通过皮带输送机运送到尾矿管理设施,在那里可以将它们作为稳定堆放置在尾矿设施内或与废石 “堆放” 起来。将干尾矿砂与废石混合在同一堆中可增强堆的整体稳定性,并无需两个独立的设施。

Qualified Persons and NI 43-101 Technical Report

合格人员和 NI 43-101 技术报告

The 2024 PEA summarized here for the Cañariaco project was completed by Ausenco Engineering Canada ULC, of Vancouver British Columbia, with mining aspects completed by AGP Mining Consultants Inc.

此处总结的卡纳里亚科项目2024年经济前景评估由位于不列颠哥伦比亚省温哥华的加拿大澳森科工程有限公司完成,采矿方面的工作由AGP矿业顾问公司完成。

The findings of the 2024 PEA will be disclosed in a NI 43-101 Technical Report which will be completed and available on SEDAR+ and Alta Copper's website on or before June 7, 2024.

2024年PEA的调查结果将在NI 43-101技术报告中披露,该报告将于2024年6月7日当天或之前完成并在SEDAR+和Alta Copper的网站上公布。

The qualified persons for the 2024 PEA and this News Release are identified below:

2024 年 PEA 和本新闻稿的合格人员如下:

Mr. Gordon Zurowski, P.Eng. Principal Mining Engineer at AGP Mining Consultants Inc.and an independent Qualified Person as set forth by NI 43-101, is responsible for mine design and mine capital and operating costs. Mr. Zurowski has reviewed the news release against the technical report.

戈登·祖罗夫斯基先生,P.EngAGP Mining Consultants Inc.首席采矿工程师和NI 43-101规定的独立合格人员负责矿山设计以及矿山资本和运营成本。祖罗夫斯基先生对照技术报告审查了新闻稿。

Mr. Kevin Murray, P.Eng. Principal Process Engineer at Ausenco Engineering Canada ULC and an independent Qualified Person as set forth by NI 43-101, is responsible for the financial model as well as mineral processing and metallurgical resting, recovery methods, and process and infrastructure capital and operating costs. Mr. Murray has reviewed the news release against the technical report.

凯文·默里先生,P.Eng加拿大奥森科工程有限公司首席工艺工程师和NI 43-101规定的独立合格人员负责财务模型以及矿物加工和冶金检测、回收方法以及工艺和基础设施的资本和运营成本。默里先生对照技术报告审查了新闻稿。

Mr. Scott Elfen, P.E., Global Lead Geotechnical and Civil Services at Ausenco Engineering Canada ULC and an independent Qualified Person as set forth by NI 43-101, is responsible for the waste management facility and associated capital and operating costs, and the site-wide water management design. Mr. Elfen has reviewed the news release against the technical report.

斯科特·埃尔芬先生,P.E.,加拿大澳森科工程公司岩土工程和民用服务全球主管,NI 43-101规定的独立合格人士,负责废物管理设施和相关的资本和运营成本,以及全场水管理设计。Elfen先生对照技术报告审查了新闻稿。

Mr. James Millard, P.Geo., Director, Strategic Projects at Ausenco Sustainability ULC and an independent Qualified Person as set forth by NI 43-101, is responsible for environmental studies, permitting, and social and community impacts. Mr. Millard has reviewed the news release against the technical report.

Ausenco Sustainability ULC战略项目董事兼NI 43-101规定的独立合格人士,P.Geo. James Millard先生负责环境研究、许可以及社会和社区影响。米拉德先生对照技术报告审查了新闻稿。

Joanne Freeze, P.Geo., President, CEO and Director has reviewed and approved the contents of this release for Alta Copper Corp.

P.Geo. 总裁、首席执行官兼董事Joanne Freeze已审查并批准了阿尔塔铜业公司本新闻稿的内容

About Ausenco

关于 Ausenco

Ausenco is a global company redefining what's possible. The team is based across 26 offices in 15 countries delivering services worldwide. Combining deep technical expertise with a 30-year track record, Ausenco delivers innovative, value-add consulting studies, project delivery, asset operations and maintenance solutions to the minerals and metals and industrial sectors ().

Ausenco 是一家重新定义可能性的跨国公司。该团队在 15 个国家设有 26 个办事处,在全球范围内提供服务。Ausenco将深厚的技术专业知识与30年的往绩相结合,为矿产、金属和工业部门提供创新、增值的咨询研究、项目交付、资产运营和维护解决方案()。

About Whittle

关于惠特尔

Australia-headquartered Whittle Consulting has a 25-year proven track record helping mining companies worldwide improve NPVs and sustainability for their operations and projects. It is comprised of a group of highly experienced industry experts, who have strong technical backgrounds in a range of disciplines including geology, mining engineering, metallurgy, research, mathematics and computing, finance, operational, financial modeling and analysis, sustainability, and a thorough appreciation of practical, organizational, and contextual reality. Whittle Consulting are comfortable with complexity, not being bound by conventional thinking, and by being willing to challenge existing paradigms and conventional wisdom which can conceal the real potential of mining businesses.

总部位于澳大利亚的Whittle Consulting在帮助全球矿业公司改善其运营和项目的NPV和可持续性方面拥有25年的良好记录。它由一群经验丰富的行业专家组成,他们在地质学、采矿工程、冶金、研究、数学和计算、金融、运营、财务建模和分析、可持续性等学科中拥有强大的技术背景,并对实际、组织和背景现实有透彻的理解。Whittle Consulting对复杂性感到满意,不受传统思维的约束,愿意挑战可能掩盖矿业真正潜力的现有模式和传统观点。

About Alta Copper

关于阿尔塔铜业

Alta Copper is focused on the development of its 100% owned Cañariaco advanced staged copper project. Cañariaco comprises 97 square km of highly prospective land located 102 km northeast of the City of Chiclayo, Peru, which includes the advanced stage Cañariaco Norte deposit, Cañariaco Sur deposit and Quebrada Verde prospect, all within a 4 km NE-SW trend in northern Peru's prolific mining district. Cañariaco is one of the largest copper deposits in the Americas not held by a major.

阿尔塔铜业专注于开发其 100% 持股的卡纳里亚科高级分期铜矿项目。卡纳里亚科由97平方千米的极具前景的土地组成,位于秘鲁奇克拉约市东北102公里处,其中包括已晚期的北加纳里亚科矿床、南加纳里亚科矿床和Quebrada Verde矿床,均位于秘鲁北部多产矿区的西北方向4公里以内。卡纳里亚科是美洲最大的非大型铜矿床之一。

Cautionary Note Regarding Forward Looking Statements

关于前瞻性陈述的警示说明

This press release contains forward-looking information within the meaning of Canadian securities laws ("forward-looking statements"). Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, plans, postulate and similar expressions, or are those, which, by their nature, refer to future events. All statements that are not statements of historical fact are forward-looking statements. Forward-looking statements in this press release include, without limitation: the results of the 2024 PEA, including the projected CapEx, the estimated pre-tax and after-tax NPV and IRR, the estimated mine life and estimated concentrate grades; the potential production from and viability of the Cañariaco Project; the risks and opportunities outlined in the 2024 PEA; the potential tonnage, grades and content of deposits; the extent of mineral resource estimates; and estimated production and operating costs. These forward-looking statements are made as of the date of this press release. Although the Company believes the forward-looking statements in this press release are reasonable, it can give no assurance that the expectations and assumptions in such statements will prove to be correct. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and are subject to risks, uncertainties, assumptions and other factors which could cause events or outcomes to differ materially from those expressed or implied by such forward-looking statements. Such factors and assumptions include, among others, variations in market conditions; the nature, quality and quantity of any mineral deposits that may be located; metal prices; other prices and costs; currency exchange rates; the Company's ability to obtain any necessary permits, consents or authorizations required for its activities; the Company's ability to access further funding and produce minerals from its properties successfully or profitably, to continue its projected growth, or to be fully able to implement its business strategies. In addition, there are known and unknown risk factors which could cause our actual results, performance or achievements to differ materially from any future results, performance or achievements expressed or implied by the forward-looking statements.

本新闻稿包含加拿大证券法所指的前瞻性信息(“前瞻性陈述”)。前瞻性陈述通常由以下词语来识别:相信、期望、预测、打算、估计、计划、假设和类似表达,或者是那些本质上指未来事件的词语。所有不是历史事实陈述的陈述均为前瞻性陈述。本新闻稿中的前瞻性陈述包括但不限于:2024年PEA的结果,包括预计的资本支出、估计的税前和税后净现值和内部收益率、估计的矿山寿命和预计的精矿品位;Caníariaco项目的潜在产量和可行性;2024年PEA中概述的风险和机遇;矿产资源估算的范围;以及估计的生产和运营成本。这些前瞻性陈述自本新闻稿发布之日起作出。尽管公司认为本新闻稿中的前瞻性陈述是合理的,但它无法保证此类陈述中的预期和假设将被证明是正确的。公司提醒投资者,公司的任何前瞻性陈述都不能保证未来的业绩或业绩,并且受风险、不确定性、假设和其他因素的影响,这些因素可能导致事件或结果与此类前瞻性陈述所表达或暗示的事件或结果存在重大差异。除其他外,这些因素和假设包括市场条件的变化;可能存在的任何矿床的性质、质量和数量;金属价格;其他价格和成本;货币汇率;公司获得其活动所需的任何必要许可、同意或授权的能力;公司成功或盈利地获得更多资金并从其财产中生产矿物的能力,以继续其预期增长或完全能够开展业务的能力策略。此外,还有一些已知和未知的风险因素可能导致我们的实际业绩、业绩或成就与前瞻性陈述所表达或暗示的任何未来业绩、业绩或成就存在重大差异。

Known risk factors include risks associated with exploration and project development; the need for additional financing; the calculation of mineral resources; operational risks associated with mining and mineral processing; fluctuations in metal prices; title matters; government regulation; obtaining and renewing necessary licenses and permits; environmental liability and insurance; reliance on key personnel; local community opposition; currency fluctuations; labour disputes; competition; dilution; the volatility of our common share price and volume; future sales of shares by existing shareholders; and other risk factors described in the Company's annual information form and other filings with Canadian securities regulators, which may be viewed at . Although we have attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. We are under no obligation to update or alter any forward-looking statements except as required under applicable securities laws.

已知的风险因素包括与勘探和项目开发相关的风险;对额外融资的需求;矿产资源的计算;与采矿和矿物加工相关的运营风险;金属价格的波动;所有权事项;政府监管;获得和续订必要的执照和许可证;环境责任和保险;对关键人员的依赖;当地社区的反对;货币波动;劳资纠纷;竞争;稀释;普通股价格和交易量的波动;未来销售现有股东的股份;以及公司年度信息表和向加拿大证券监管机构提交的其他文件中描述的其他风险因素,可在以下地址查看 。尽管我们试图确定可能导致实际行动、事件或结果与前瞻性陈述中描述的重大差异的重要因素,但可能还有其他因素导致行动、事件或结果与预期、估计或预期不符。无法保证前瞻性陈述会被证明是准确的,因为实际结果和未来事件可能与此类陈述中的预期存在重大差异。因此,读者不应过分依赖前瞻性陈述。除非适用的证券法要求,否则我们没有义务更新或修改任何前瞻性陈述。

Cautionary Note to US Investors

致美国投资者的警示说明

We advise U.S. investors that this news release uses terms defined in the 2014 edition of the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) "CIM Definition Standards on Mineral Resources and Mineral Reserves", as incorporated by reference in Canadian National Instrument 43-101 "Standards of Disclosure for Mineral Projects", for reporting of mineral resource estimates. These Canadian standards, including NI 43-101, differ from the requirements of the United States Securities and Exchange Commission (SEC) as set forth in the mining disclosure rules under Regulation S-K 1300. Regulation S-K 1300 uses the same terminology for mineral resources, but the definitions are not identical to NI 43-101 and CIM Definition Standards. Regulation S-K 1300 uses the term "initial assessment" for an evaluation of potential project economics based on mineral resources. This study type has some similarities to a Preliminary Economic Assessment, but the definition and content requirements of an initial assessment are not identical to the definition and content requirements for a PEA under NI 43-101.

我们建议美国投资者,本新闻稿使用加拿大矿业、冶金和石油协会(CIM)2014年版的 “CIM矿产资源和矿产储量定义标准” 中定义的术语来报告矿产资源估算,该标准以引用方式纳入了加拿大国家仪器43-101 “矿产项目披露标准”。这些加拿大标准,包括NI 43-101,不同于美国证券交易委员会(SEC)在第S-K 1300号法规下的采矿披露规则中规定的要求。第S-K 1300号法规对矿产资源使用相同的术语,但其定义与NI 43-101和CIM定义标准不同。第S-K 1300号法规使用 “初步评估” 一词来评估基于矿产资源的潜在项目经济学。这种研究类型与初步经济评估有一些相似之处,但是初步评估的定义和内容要求与NI 43-101下PEA的定义和内容要求并不相同。

On behalf of the Board of Alta Copper Corp.

代表阿尔塔铜业公司董事会

"Giulio T. Bonifacio", Executive Chair and Director

朱利奥·T·博尼法西奥“,执行主席兼董事

For further information please contact:
Giulio T. Bonifacio, Executive Chair and Director
gtbonifacio@altacopper.com
+1 604 318 6760

欲了解更多信息,请联系:
Giulio T. Bonifacio,执行主席兼董事
gtbonifacio@altacopper.com
+1 604 318 6760

or

要么

Joanne C. Freeze, President, CEO and Director
jfreeze@altacopper.com
+1 604 512 3359

Joanne C. Freeze,总裁、首席执行官兼董事
jfreeze@altacopper.com
+1 604 512 3359

Email: info@altacopper.com

Twitter:
LinkedIn:
Facebook:
Instagram:
YouTube:

电子邮件: info@altacopper.com

推特:
领英:
脸书:
Instagram
YouTube

SOURCE: Alta Copper Corp.

来源:阿尔塔铜业公司


声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发