share_log

West Red Lake Gold Outlines 2024 Madsen Mine Plans

West Red Lake Gold Outlines 2024 Madsen Mine Plans

West Red Lake黄金公司概述了2024年马德森矿区的计划。
GlobeNewswire ·  06/05 07:00

VANCOUVER, British Columbia, June 05, 2024 (GLOBE NEWSWIRE) -- West Red Lake Gold Mines Ltd. ("West Red Lake Gold" or "WRLG" or the "Company") (TSXV: WRLG) (OTCQB: WRLGF) is pleased to outline some of the key mine infrastructure and development projects the Company plans to undertake at the Madsen Mine in the near to medium term with the funds from its recent financings.

West Red Lake Gold Mines Ltd.("西红湖黄金矿业"或"WRLG"或"公司")(TSXV: WRLG)(OTCQB: WRLGF)很高兴地概述了公司计划从最近融资中获得的资金实现在Madsen矿井进行的一些关键矿山基础设施和开发项目的近中期阶段。

West Red Lake Gold has a goal to restart the high-grade Madsen gold mine in the second half of 2025. The company is working on a pre-feasibility study detailing that restart plan, which is targeted for release in early 2025.

西红湖黄金矿业有一个重启高品位Madsen金矿的目标,计划于2025年下半年实现。该公司正在制定一份详细的可行性研究计划,该计划旨在于2025年初发布。

West Red Lake Gold has identified the mine site projects of scale that will be critical to the restart plan. The Company will be commencing work on these critical path projects in the coming weeks and months, alongside the consistent drilling, exploration, and engineering work that is informing the prefeasibility study and outlining potential project enhancements in the future.

西红湖黄金矿业已经确定了矿区的规模项目,这些项目对于重启计划至关重要。公司将在未来几周和几个月内开始这些关键路径项目的工作,与持续的钻探、勘探和工程工作一起,这些工作正在为前期可行性研究提供信息,并大致说明未来潜在项目的增强点。

Shane Williams, President & CEO, stated, "With the funds raised in our recent financings, including $10 million in Canadian Development Expense flow-through funding, we are excited to get started on these important projects. With a year of work under our belts at Madsen, we know what needs to be procured, built, and developed at the mine site over the next six to twelve months to achieve our goal of restarting the mine in 2025. We look forward to keeping investors up to date on key milestones as this work progresses."

总裁兼首席执行官Shane Williams表示:"通过我们最近的融资计划筹集到的资金,包括1,000万加元的加拿大开发费用流向资金,我们很高兴开始这些重要的项目。在Madsen工作了一年之后,我们知道接下来的六到十二个月需要在矿区采购、建造和开发哪些项目才能实现2025年重新启动矿区的目标。我们期待着随着这些工作的进展向投资者公布关键里程碑。"

KEY MINE INFRASTRUCTURE AND DEVELOPMENT PROJECTS:

关键矿山基础设施和开发项目:

  • Connection Drift: 1,200-meter haulage way to connect the East and West portals/declines at the Madsen Mine, to increase material hauling efficiency, ventilation, and safety. The Company's recent financing (see press release West Red Lake Gold Announces Closing $33 Million Bought Deal Public Offering Including The Full Exercise Of The Overallotment Option, dated May 16th) raised $33 million. Of that total, $10 million were flow-through funds raised for use under the Canadian Development Expense category; that amount is in line with the company's cost forecast for this project. The company is pleased to be able to use flow-through funds of this type to fund development of this key haulage way in the Madsen mine.
  • Primary Crusher: Install a permanent primary crusher as part of the Madsen mill, which previously relied on a temporary leased crusher.
  • Test Mining: Initiate a test mining program to assess longhole stoping and cut-and-fill mining methods on the range of mining environments at Madsen. This will be an essential step in further de-risking the asset.
  • Bulk Sample: Analyze samples from the test mining program through a sample tower to determine representative grade of a bulk sample.
  • Camp: Procure and install a mine camp to house 100 workers at the Madsen mine site.
  • Mine Dry: Procure, install, and staff a facility with showers, change areas, and laundry where workers can transition into and out of work shifts.
  • Evaporators: Install two (2) evaporator fans with the ability to manage 2,000 cubic meters of water daily, to increase overall water management capacity at the mine site.
  • Shaft Rehabilitation: Continue the process of dewatering the mine and rehabilitating the existing shaft, which is now certified to move people for the purpose of inspecting shaft conditions.
  • 连接隧道: 1,200米运输通道,连接Madsen矿山的东西入口/下降道,提高物料运输效率、通风和安全性。该公司最近的融资(参见新闻稿 West Red Lake Gold宣布完成3,300万美元认购公开发行,包括完全行使超额配售选择权,日期为5月16日th),筹集了3300万美元。其中,筹集的用于加拿大发展费用类别的流向资金为1000万美元,这与公司的成本预测相符。该公司很高兴能够利用这种类型的流向资金来资助Madsen矿山这一关键运输通道的开发。
  • 主要破碎机: 将一台永久性破碎机安装在Madsen磨机中,这是之前租用设备的替代品。
  • 测试采矿: 对Madsen不同采矿环境的不同采矿方法进行长孔栓击采矿和割填采矿方案的初步评估,这是进一步降低风险的关键步骤。
  • 散样: 通过样品勘探塔分析测试采矿计划的样本,以确定大宗样本的代表性等级。
  • 营地: 采购和安装一个可以容纳Madsen矿山100名工人的矿山营地。
  • 干燥区: 采购、安装和设立一个设有淋浴、更衣区和洗衣房的设施,供工人在工作与休息班次之间过渡。
  • 蒸发器: 安装两个蒸发器,可管理每天2,000立方米的水,以增加矿区整体的水管理能力。
  • 井筒修复: 继续排水治理和修复现有井筒的过程,现有井筒已经获得了用于检查井筒状况的人员的证书。

UNDERGROUND DRILLING:

地下钻探:

As the above site projects progress, West Red Lake Gold will continue its consistent underground drilling work. Over the remainder of 2024 the Company plans to have two (2) diamond drills operating regularly in a program totaling up to 39,000 meters, with two primary objectives:

随着上述项目的推进,西红湖黄金矿业将继续持续开展地下钻探工作。在2024年的其余时间里,公司计划有两台钻石钻机正常运行,总计钻探深度达39,000米,并有两个主要目标:

  • Resource Definition Drilling: 70% of the drilling (approximately 27,000 meters) will be used to increase resource confidence across all known resource domains (Austin, North Austin, South Austin, and McVeigh), in support of the mine restart plan.
  • Resource Expansion Drilling: 30% of the drilling (approximately 12,000 meters) will test the Company's top targets for resource expansion. Expansion drilling is currently focused on the near surface North Austin area. As underground development progresses deeper, other expansion targets will become more accessible and will be incorporated into the drill schedule, such as the Austin extension target between the 12 and 15 levels of the mine and the 8 Zone down plunge extension target
  • 资源定义钻探: 70%(约27,000米)的钻探将用于增加所有已知资源领域(奥斯汀,北奥斯汀,南奥斯汀和麦克韦)的资源信心,支持矿山重新启动计划。
  • 资源扩展钻探: 30%(约12,000米)的钻探将测试公司资源扩展的首要目标。资源扩展钻探目前侧重于近地表的北奥斯汀区域。随着地下开发向深处推进,其他扩展目标将变得更加易于访问,并将纳入钻井计划中,例如介于矿山12和15层之间的奥斯汀延伸目标和8区向下推展的目标。

"Our updated and refined geologic model has been performing well, as evidenced by our success reporting gold mineralization in both infill and expansion drill holes," stated Will Robinson, VP of Exploration. "We are keen to continue building confidence in the Madsen resource with definition holes ahead of our prefeasibility study, to continue expanding the North and South Austin zones where our drill holes have been stepping out from known domains in recent months, and to test additional high caliber targets close to existing underground infrastructure where historic drill intercepts suggest there is good potential to define additional mineralization, like the 8 Zone."

探矿副总裁威尔·罗宾逊表示:"我们更新的、完善的地质模型表现良好,如我们在填充和扩张钻孔中成功报告的黄金矿化表明。我们热衷于在可行性研究之前进行定义孔,以继续扩大North和South Austin区域。这里是我们近几个月来的趋势。在已知域外扩张的钻孔,并测试靠近现有地下基础设施的其他高品质目标,历史钻探拦截表明,在这些地方定义其他矿化的潜力很大,如8区。"

ONE YEAR ON SITE:

一年驻场综述:

West Red Lake Gold closed its acquisition of the Madsen Mine on June 19, 2023 (see press release dated June 19, 2023). The Company is proud of the significant work accomplished in the last year.

West Red Lake Gold于2023年6月19日完成了收购Madsen矿山的交易(请参阅2023年6月19日的新闻稿)。公司为过去一年取得的重要成果感到自豪。

Personnel: The Company has recruited a management team with significant experience across corporate roles in mining, from finance to technical services. The Company has also hired over 100 personnel in roles at the Madsen mine, from drilling to underground development to environmental monitoring to geology and more.

人员:公司招募了一个具有矿业公司从金融到技术服务的重要角色的管理团队。公司还招聘了100多名员工在Madsen矿井开展各种工作,包括钻探、地下开发、环境监测、地质学等等。

Madsen Drilling: During 2023, the Company drilled a total of 28 Expansion holes for 2,524 meters ("m") and 71 Definition holes for 4,611m from underground at Madsen. In 2024 (as of May 31st), the Company has drilled an additional 62 Expansion holes for 6,076m and 74 Definition holes for 5,803m. Madsen Mine drilling has been directed at two main goals: 1) increasing confidence in the known resource blocks to enable confident detailed mine planning, and 2) testing near-resource targets with potential for new mineralization. The Company has been pleased to issue consistently positive drill results over the last seven months demonstrating progress with both goals.

Madsen钻探:在2023年,公司通过地下钻探共钻探了2524米共28个扩展孔和4611米共71个定义孔。2024年(截至5月31日),公司又钻探了额外的6,076米,共62个扩展孔和5803米共74个定义孔。 Madsen矿山的钻孔方向有两个主要目标:缩小已知资源块的范围,以便进行肯定的详细矿山规划并测试接近资源的目标,这些目标具有新的矿化潜力。公司很高兴能够连续发表积极的钻探结果,证明在这两个目标方面取得了进展。21世纪医疗改革法案矿山重启分析:在确定之前经营者的Madsen矿山中出现的问题时,已做了大量工作--分析潜在的改进措施,确定每个改进措施的时间和成本,并评估修复或更换的最佳方案。这一过程应用于矿山的每个方面,包括地质模型、障碍设计、采矿方法、地下工程和流程、矿石运输、磨机部件、磨机参数、运营监督、设备租赁、工人住宿、水处理厂增强等等。

Mine Restart Analysis: Significant work has been done identifying the issues that arose at the Madsen mine under the prior operator - analyzing potential improvements, determining the time and cost of each improvement, and assessing the best course of action as to repair or replace. This process has been applied across every aspect of the mine, including the geologic model, stope designs, mining methods, underground engineering and flow, ore haulage, mill components, mill parameters, operations oversight, equipment leases, worker accommodations, water treatment plant enhancements, and more.

地下开发:公司在Madsen矿山完成了1488米的地下开发工作,以获取新的钻探站、为测试采矿做准备和改善通风情况。该公司还对旧工程进行了修复和清理,使它们适合于现代矿山设备。

Underground Development: The Company has completed 1,488 meters of underground development at the Madsen mine to access new drill stations, prepare for test mining, and improve ventilation. The Company has also completed rehabilitation and slashing on older workings to make them suitable for modern mining equipment.

升降机:逆水至12层的1,275米的升降机机构已经得到修复。Madsen矿山目前放水至12层,并已逐步修复升降机,以至笼子现在可以用于检查升降机。

Shaft: The hoist mechanism for the 1,275-meter shaft has been refurbished. The Madsen mine is currently dewatered to the 12-level and the company has progressively rehabilitated the shaft, such that the cage is now certified to move personnel for the purpose of inspecting the shaft.

环保与社区:West Red Lake Gold很高兴能在Treaty #3领土上运营。公司致力于与Red Lake所有利益相关者建立良好的关系,并乐于支持当地的各项计划。West Red Lake Gold很荣幸能够参加Red Lake Anishinaape Pow Wow Circle(6月8日至9日)。

Environment and Community: West Red Lake Gold is pleased to be operating in Treaty #3 Territory. The Company has worked to develop good relations with all Red Lake stakeholders and is pleased to support local initiatives. West Red Lake Gold is honoured to be participating the Red Lake Anishinaape Pow Wow Circle this weekend (June 8-9).

关于West Red Lake Gold Mines:West Red Lake Gold Mines Ltd是一家公开交易的矿产勘探公司,专注于推进和开发其旗舰Madsen黄金矿和相关47平方公里的高度潜力土地包,位于安大略省的Red Lake地区。加拿大西北部富有成果的Red Lake金矿区从高品位区域中产生了超过3000万盎司的黄金,还拥有世界上最丰富的金矿床。WRLG还拥有位于Red Lake的全部拥有Rowan属性,包括三个生产过黄金的矿山,即Rowan、Mount Jamie和Red Summit。

ABOUT WEST RED LAKE GOLD MINES

关于West Red Lake黄金矿业公司

West Red Lake Gold Mines Ltd. is a mineral exploration company that is publicly traded and focused on advancing and developing its flagship Madsen Gold Mine and the associated 47 km2 highly prospective land package in the Red Lake district of Ontario. The highly productive Red Lake Gold District of Northwest Ontario, Canada has yielded over 30 million ounces of gold from high-grade zones and hosts some of the world's richest gold deposits. WRLG also holds the wholly owned Rowan Property in Red Lake, with an expansive property position covering 31 km2 including three past producing gold mines – Rowan, Mount Jamie, and Red Summit.

West Red Lake Gold Mines Ltd.是一家矿产勘探公司,以推进和开发在安大略省雷德湖区Madsen金矿和相关的47平方公里高度潜力土地包为主。剖面丰产的加拿大西北红湖金矿区已经从高品位区开采出超过3000万盎司的黄金,并拥有世界上最丰富的金矿床。WRLG在雷德湖拥有一个占地31平方公里的拥有Rowan道具的全部产权,包括三个以往制作过黄金的矿山-Rowan、Mount Jamie和Red Summit。

ON BEHALF OF WEST RED LAKE GOLD MINES LTD.

代表West Red Lake黄金矿业有限公司。

"Shane Williams"

“Shane Williams”

Shane Williams
President & Chief Executive Officer

Shane Williams
董事长兼首席执行官

FOR FURTHER INFORMATION, PLEASE CONTACT:

如需更多信息,请联系:

Freddie Leigh
Investor Relations

Freddie Leigh
投资者关系

Tel: (604) 609-6132

电话:(604) 609-6132

Email: investors@wrlgold.com or visit the Company's website at

邮箱:investors@wrlgold.com或访问公司网站

The technical information presented in this news release has been reviewed and approved by Will Robinson, P.Geo., Vice President of Exploration for West Red Lake Gold and the Qualified Person for exploration at the West Red Lake Project, as defined by NI 43-101 "Standards of Disclosure for Mineral Projects".

该新闻稿所提供的技术信息已由West Red Lake Gold Mine探勘副总裁Will Robinson,P.Geo.审查并核准,并是唯一探勘NI 43- 101标准下的West Red Lake项目的合格人员。

The technical information presented in this news release has been reviewed and approved by Maurice Mostert, P.Eng., Vice President of Technical Services for West Red Lake Gold and the Qualified Person for technical services at the West Red Lake Project, as defined by NI 43-101 "Standards of Disclosure for Mineral Projects".

本新闻稿中提供的技术信息已由West Red Lake Gold矿业技术服务副总裁Maurice Mostert,P.Eng审查并批准,并被定义为NI 43-101《矿产项目披露标准》下的West Red Lake项目的技术服务合格人员。

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

tsxv的监管服务提供商(在其政策中定义该术语)对本公告的充分性或准确性不承担责任。

FORWARD-LOOKING INFORMATION

前瞻性信息

Certain statements contained in this news release may constitute "forward-looking information" within the meaning of applicable securities laws. Forward-looking information generally can be identified by words such as "anticipate", "expect", "estimate", "forecast", "planned", and similar expressions suggesting future outcomes or events. Forward-looking information is based on current expectations of management; however, it is subject to known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from the forward-looking information in this news release and include without limitation, statements relating to plans for the potential restart of mining operations at the Madsen Mine, such as expectations regarding the preparation and timing of a pre-feasibility study; the identification and execution of the critical path items needed to be procured, built and developed at the mine site; the drilling, exploration, and engineering work, and the potential benefits thereof; the use of funds (including flow-through funds), the performance of the updated and refined geological model; the increase in confidence in the existing resource; the identification of additional mineralization; the identification of, and proposed fixes for, issues identified under the prior operator; the success of the rehabilitation work completed; and achieving and maintaining good relations with Red Lake stakeholders. Readers are cautioned not to place undue reliance on forward-looking information.

本新闻稿中所含信息可能构成“前瞻性资讯”,即适用证券法的意义。前瞻性资讯一般可通过表明未来结果或事件的措辞,例如“预计”、“期望”、“估计”、“预测”、“计划”和类似表述来识别。前瞻性资讯基于管理层当前的期望,然而,它受到已知和未知的风险、不确定因素和其他因素的影响,这些因素可能导致本新闻稿中的前瞻性资讯与实际结果存在重大差异,包括但不限于计划重新启动马德森矿的采矿操作的计划,如关于预可行性研究的准备和时间安排; 为采矿现场采购、建设和开发所需的关键路径项目的识别和执行; 钻探、勘探和工程工作及其潜在的益处; 资金的用途 (包括流动资金)、更新和精细化的地质模型的表现; 对现有资源信心的提高; 附加矿化的识别; 对以前运营商发现的问题的识别和拟议的解决方案; 完成的修复工作的成功;以及实现和维护与 Red Lake 利益相关方的良好关系。请注意,读者不应过分依赖前瞻性资讯。

Forward-looking information involve numerous risks and uncertainties and actual results might differ materially from results suggested in any forward-looking information. These risks and uncertainties include, among other things, market volatility; the state of the financial markets for the Company's securities; fluctuations in commodity prices; timing and results of the cleanup and recovery at the Madsen Mine; and changes in the Company's business plans. Forward-looking information is based on a number of key expectations and assumptions, including without limitation, that the Company will continue with its stated business objectives and its ability to raise additional capital to proceed. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such forward-looking information. Accordingly, readers should not place undue reliance on forward-looking information. Readers are cautioned that reliance on such information may not be appropriate for other purposes. Additional information about risks and uncertainties is contained in the Company's management's discussion and analysis for the year ended November 30, 2023, and the Company's annual information form for the year ended November 30, 2023, copies of which are available on SEDAR+ at .

前瞻性信息涉及多种风险和不确定因素,实际结果可能与任何前瞻性信息所暗示的结果有所不同。这些风险和不确定因素包括但不限于市场波动性;公司证券的金融市场状况;大宗商品价格波动;马德森矿的清理和恢复的时间和结果,以及公司业务计划的变更。前瞻性信息基于许多关键期望和假设,包括但不限于公司将继续实行其声明的业务目标以及筹集额外资本以继续前进的能力。尽管公司管理层已试图确定可能导致实际结果与前瞻性信息有重大不同之重要因素,但可能还有其他因素导致结果不如预期、估计或预期的那样。不能保证此类前瞻性信息将被证明是准确的,因为实际结果和未来事件可能与前瞻性信息中所暗示的不同。因此,读者不应过分依赖前瞻性信息。读者应注意,依赖这种信息可能不适合其他目的。公司的风险和不确定因素的附加信息在公司于2023年11月30日的管理层讨论和分析中,以及公司于2023年11月30日的年度信息表中均有涉及,拷贝可在Sedar+获取。

The forward-looking information contained herein is expressly qualified in its entirety by this cautionary statement. Forward-looking information reflects management's current beliefs and is based on information currently available to the Company. The forward-looking information is made as of the date of this news release and the Company assumes no obligation to update or revise such information to reflect new events or circumstances, except as may be required by applicable law.

本文中所包含的前瞻性信息明确受到本警告声明的限制。前瞻性信息反映了管理层当前的信念,并基于当前对公司可获得信息的理解。前瞻性信息是根据本新闻稿的日期制作的,公司假定不具备将更新或修订此类信息以反映新事件或情况的义务,除非适用法律要求。

For more information on the Company, investors should review the Company's continuous disclosure filings that are available on SEDAR+ at .

有关公司的更多信息,投资者应查阅在Sedar+上公开的公司连续披露文件。.

A photo accompanying this announcement is available at

此公告附有一张照片,请前往


声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发