MORRISTOWN, N.J., July 2, 2024 -- FirstEnergy Corp. (NYSE: FE) subsidiary Jersey Central Power & Light (JCP&L) is upgrading a transmission substation in Morristown to help prevent or minimize the impact of power outages caused by flooding, particularly during hurricane season.

第一能源公司(NYSE:FE)的子公司新泽西中央电力公司(JCP&L)正在升级位于莫里斯敦的变速器变电站,以帮助预防或减轻由洪水引起的电力中断影响,特别是在飓风季节期间。

The $78 million project will raise equipment within the facility to keep it above floodwaters, enhancing service reliability for 23,000 JCP&L customers in northern New Jersey. The Whippany River, which runs along the northeastern border of the property, has become more flood prone in recent years.

这项7800万美元的项目将提高设施内的设备,使其高于洪水,为新泽西北部的23,000名JCP&L客户提供增强的服务可靠性。在这些年中,沿着财产东北边界流经的Whippany River变得更容易发生洪水。

Doug Mokoid, FirstEnergy's President, New Jersey: "This project is a major undertaking that will help ensure that our customers continue to receive the safe, reliable service they expect from us even as our state sees increasing impacts from Mother Nature. We appreciate the support we've received from local officials as we work to make these vital upgrades to a historic facility."

第一能源公司新泽西州总裁道格·莫科伊德表示:“这个项目是一项重要任务,将确保我们的客户继续从我们这里获得安全、可靠的服务,即使我们的州因为自然灾害而受到越来越大的影响。我们感谢当地官员的支持,因为我们一直在努力对一个历史悠久的设施进行这些必要的升级改造。”

The site, originally purchased in 1928, now sits along a busy residential and commercial thoroughfare. As part of this project, JCP&L has agreed to beautify the property's exterior with shade trees, ornamental trees, decorative pavers and sculptural benches. A screening wall will provide an additional visual barrier, as well as enhanced security around substation equipment, which required a variance from the town for height restrictions. Work is expected to be completed by December 2025.

这个地点最初是在1928年购买的,现在它坐落在一个繁忙的住宅和商业要道上。作为这个项目的一部分,JCP&L已经同意美化庭院外观,种植阴影树、装饰性树、装饰性铺路石和雕塑长凳。一个屏幕墙将提供一个额外的视觉障碍,以及更强大的安全围绕变电站的设备,需要一个城镇的变型从高度限制。工作预计将在2025年12月完成。

The substation functions as a central point for providing local distribution service to nearby neighborhoods and businesses. Additionally, it plays a significant role in connecting other substations in northern New Jersey, as the Morristown facility's high-voltage lines supply power that is later converted for distribution to neighborhood power lines at those locations.

变电站作为向附近社区和企业提供局部配电服务的中心点。此外,它在连接新泽西北部的其他变电站方面扮演着重要的角色,因为莫里斯敦设施的高电压线路提供之后转换为分配到这些位置的邻里电线的能量。

JCP&L serves 1.1 million customers in the counties of Burlington, Essex, Hunterdon, Mercer, Middlesex, Monmouth, Morris, Ocean, Passaic, Somerset, Sussex, Union and Warren. Follow JCP&L on X, formerly known as Twitter, @JCP_L, on Facebook at facebook.com/JCPandL or online at jcp-l.com

JCP&L服务于伯灵顿、埃塞克斯、亨特登、默瑟、米德尔塞克斯、蒙莫斯、莫里斯、欧申、帕萨伊克、萨默塞特、苏塞克斯、联合和沃伦等12个县,可为110万个客户提供服务。关注X以前的Twitter(@JCP_L)或在facebook.com/JCPandL上关注JCP&L,或在jcp-l.com上查看。,FirstEnergy致力于诚信、安全、可靠和运营卓越,其电力分配公司组成了美国最大的投资家有电力系统之一,为俄亥俄州、宾夕法尼亚州、新泽西州、西佛吉尼亚州、马里兰州和纽约州的超过600万客户提供服务。该公司的输电子公司运营着将中西部和中大西洋地区连接起来的大约24,000英里的输电线路。在网站FirstEnergyCorp.com关注FirstEnergy,在X上关注@FirstEnergyCorp。

FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. The company's transmission subsidiaries operate approximately 24,000 miles of transmission lines that connect the Midwest and Mid-Atlantic regions. Follow FirstEnergy online at and on X at @FirstEnergyCorp.

资讯媒体联系人:克里斯·霍尼格,(609)350-8599或投资者关系联系人:吉娜·卡斯基,(330)607-0157

News Media Contact: Chris Hoenig, (609) 350-8599 or Investor Relations Contact: Gina Caskey, (330) 607-0157