Toyo Ventures Holdings Berhad has provided more updates on the development of "Song Hau 2 Thermal Power Plant Project" in Vietnam which has now been terminated by the Vietnamese government.

东洋创业控股有限公司就越南“松侯2号热电厂项目”的开发提供了更多更新,该项目现已被越南政府终止。

The group which announced recently on a loan facility of over RM4.6 billion for the project has received a letter from its legal counsel i-Power Solutions Pte Ltd, citing since the Project now stands terminated, there is no longer any applicable purpose for the Equipment Facility of United States Dollar Nine Hundred and Eighty million (USD980,000,000) granted.

集团最近宣布贷款超过46亿令吉用于该项目,已收到法律顾问i-Power Solutions Pte Ltd的一封信,称由于该项目现已终止,因此授予的9.8亿美元的设备贷款已不再适用。

additionaly, the was also news that Export-Import Bank of Malaysia Berhad of being appointed Mandated Lead Arranger for a funding raising exercise of up to USD2.68 billion, one of the biggest of its kind to be raised by a Malaysian bank for an overseas project.

此外,还有消息称,马来西亚出口-进口银行已被委任为募集最高26.8亿美元的筹资行动的主导安排方之一,这是马来西亚银行为海外项目筹集的最大规模之一。

This project, to be undertaken by the Toyo Ventures, Song Hau Power 2 Company Ltd, was suppose to be constructed by an EPCC consortium made up of Sunway Construction Sdn Bhd and Vietnam's Power Engineering Consulting Joint Stock Company 2. PECC2, is a subsidiary of Electricity of Vietnam, the state-owned enterprise, is also the appointed O&M for the plant throughout the concession period,

东洋创业的子公司Song Hau Power 2 Company Ltd将承担该项目,由Sunway Construction Sdn Bhd和越南能源工程咨询股份有限公司2组成的EPCC联合体负责建造。 PECC2是越南电力公司的子公司,在特许期内还被任命为该电厂的运营和维护。

Toyo Ventures said that the SH2P is in the midst of finalising the syndicated financing facilities for the Project.

东洋创业表示,SH2P正在完成项目的银团融资设施。