Osisko Development Reports Second Quarter 2024 Results

Osisko Development Reports Second Quarter 2024 Results

Osisko Development报告2024年第二季度业绩
GlobeNewswire ·  08/12 18:00

(All monetary references are expressed in Canadian dollars, unless otherwise indicated)

(所有货币金额均以加元表示,除非另有说明)

MONTREAL, Aug.  12, 2024  (GLOBE NEWSWIRE) -- Osisko Development Corp. (NYSE: ODV, TSXV: ODV) ("Osisko Development" or the "Company") reports its financial and operating results for the three months ended June 30, 2024 ("Q2 2024").

2024年8月12日,蒙特利尔(GLOBE NEWSWIRE)——Osisko Development公司(NYSE:ODV,TSXV:ODV)(“Osisko Development”或“公司”)公布了其截至2024年6月30日(“2024年Q2”)的三个月财务和业务结果。

Q2 2024 HIGHLIGHTS

2024年Q2亮点

Operating, Financial and Corporate Updates:

营运、财务和公司更新:

  • 805 ounces of gold sold by the Company from operating activities in the second quarter, comprising of 790 ounces of gold sold from the Trixie test mine ("Trixie"), and the balance from the Cariboo Gold Project ("Cariboo Gold Project") by processing stockpiles at a third-party facility.

  • $2.6 million in revenues ($10.8 million in Q2 2023) and $2.7 million in cost of sales ($11.4 million in Q2 2023) generated from operating activities.

  • On May 9, 2024, the Company announced, as part of its regular annual remuneration program, the granting of an aggregate of 283,250 deferred share units ("DSU") of the Company to its independent directors in accordance with the DSU Plan of the Company

  • On May 30, 2024, Maggie Layman departed from her position as Vice President, Exploration to pursue another opportunity.

  • On June 3, 2024, the Company announced that in connection with the terms of the Company's previously completed acquisition in May 2022 of a 100% ownership interest in the Tintic Project, it had satisfied the second of five deferred payments to the sellers. The deferred consideration of US$2,500,000 was settled by the issuance of 1,228,394 common shares.

  • On June 10, 2024, the Company entered into an amending agreement to the credit agreement (the "Amendment") with National Bank of Canada made as of March 1, 2024, providing for a US$50 million delayed draw term loan (the "Credit Facility"). The Amendment provides for, among other things:  

    • An 8-month extension to the maturity date to October 31, 2025 (from March 1, 2025). The extension is subject to the completion of a capital raise of at least US$20 million prior to October 31, 2024, otherwise the maturity date reverts to February 28, 2025.

    • Reduction in the mandatory prepayment amount to 50% of each incremental dollar raised in excess of US$25 million in respect of certain financings, allowing the Company to preserve 50% of such proceeds. There are no mandatory prepayment requirements for amounts up to US$25 million.

  • 公司在第二季度的营业活动中销售了805盎司的黄金,其中790盎司的Gold来自Trixie试验矿(“Trixie”),剩余的黄金来自Cariboo Gold Project(“Cariboo Gold Project”)通过在第三方设施处理库存堆积。

  • 营业活动产生了260万美元的收入(2023年Q2为1080万美元)和270万美元的销售成本(2023年Q2为1140万美元)。

  • 2024年5月9日,公司作为其常规年度薪酬计划的一部分,根据公司DSU计划向独立董事授予了合计283,250个推迟的股票单位(“DSU”)。

  • 2024年5月30日,Maggie Layman离开其副总裁,探险的职务,去追寻另一份机会。

  • 2024年6月3日,为按照公司于2022年5月完成的已完成收购的条款,向出售方支付的五个递延付款中的第二个付款。递延考虑价值为250万美元,通过发行1,228,394股普通股来解决。

  • 2024年6月10日,公司与加拿大国家银行签订了一份信贷协议修改协议(“修订案”),根据2024年3月1日签署的协议,提供了一项5000万美元的延迟提款期贷款(“信贷设施”)。议定书包括以下内容:

    • 将到期日推迟8个月,到2025年10月31日(从2025年3月1日)。此次展期的前提是在2024年10月31日之前完成至少2000万美元的融资,否则到期日将恢复为2025年2月28日。

    • 有关某些融资方面,强制预先支付金额降低为超过2500万美元的每个增量美元的50%,允许公司保留50%的收益。对于2500万美元以下的金额,没有强制预先支付要求。

  • As at June 30, 2024, the Company had approximately $33.7 million in cash.

  • 截至2024年6月30日,公司的现金约为3370万美元。

Cariboo Gold Project – British Columbia, Canada (100%-owned)

加拿大不列颠哥伦比亚省的Cariboo Gold Project(100%拥有)

  • Permitting Progress. Receipt of the EA Certificate in October 2023 successfully concluded the EA process for the Cariboo Gold Project (see Figure 1).  

    • The BC Mines Act and Environmental Management Act permits have been drafted, and are currently under review by the Company and the Mine Review Committee.

    • The Company anticipates completing its permit application referral and receiving final construction and operating permits in Q3 2024.

    • The Company continues to explore funding options, including fully-funded solutions for the Cariboo Gold Project.

  • 许可进展。2023年10月收到EA证书成功完成了对Cariboo Gold Project的EA过程(见图1)。

    • BC Mines Act和Environmental Management Act的许可已草拟,并正在由公司和矿山审查委员会审查。

    • 公司预计在2024年Q3完成其许可申请转介并获得最终的建设和运营许可证。

    • 公司继续探索资金筹集方案,包括Cariboo Gold Project的全面资助方案。

Figure 1: Cariboo Gold Project – Permitting Timeline Summary

图1:Cariboo Gold Project-许可证时间线摘要

  • Pre-Construction Activities. During Q1 2024, under an existing provincial permit, the Company commenced an underground development drift from the existing Cow Portal into the Cariboo Gold Project's mineral deposit at the Lowhee Zone. The objective of the bulk sample work program is to reach the ore body and extract a 10,000 tonne bulk sample of mineralized material for ore sorter, heavy equipment and mining testing.  

    • To date, approximately 510 meters of development has been completed, with another 660 meters remaining to reach the target area.

    • The Company anticipates completing the bulk sample in Q4 2024.

  • 建设前活动。在现有省级许可证的规定下,公司在2024年Q1开始从现有的Cow Portal(牛门)向Lowhee区域的Cariboo Gold Project矿床开展地下开发隧道。散样工作计划的目标是到达矿体并提取10000吨矿化物材料进行矿石分选,重型机械和采矿测试。

    • 截至目前,开发了约510米,还需660米才能到达目标区域。

    • 公司预计在2024年Q4完成散样。

  • Wildfire Response. On July 22, 2024, the Company temporarily paused non-essential activities at its Cariboo Gold Project following a wildfire evacuation order that included the Project. The wildfire evacuation order was lifted on July 25, 2024, and normal course operations and site activities at the Cariboo Gold Project resumed on July 26, 2024, following the return of non-essential employees to site. The mine site infrastructure was unaffected by the wildfires.

  • 野火应急响应。2024年7月22日,公司根据山火疏散令暂停了Cariboo Gold Project的非必要活动。山火疏散令于2024年7月25日解除,Cariboo Gold Project的正常活动和现场活动于2024年7月26日恢复,非必要员工返回现场。矿山基础设施未受山火影响。

Tintic Project – Utah, U.S.A. (100%-owned)

Tintic项目-美国犹他州(100%所有权)

  • Big Hill Porphyry Target Drilling. Two surface diamond drill holes totalling approximately 2,920 meters ("m") (9,581 feet ("ft")) have been completed at the Big Hill target area in May 2024 testing for copper-gold-molybdenum porphyry mineralization potential.  

    • Both drill holes intersected porphyry systems defined by at least three late-mineral monzonite porphyritic intrusive phases and an intrusion breccia.

    • Although anomalous copper and molybdenum mineralization was encountered, including low visible presence of chalcopyrite, tennantite, and molybdenite, no significant intercepts of copper, gold or molybdenum were observed. The porphyries encountered to date are considered to lack evidence for the major fluid paths required to be the source of mineralization in the Tintic District.

    • Big Hill West Target. The results of the recent and historical drill holes suggest that the early and potentially better mineralized intrusive phase could be in an untested area immediately west and southwest of the area drilled at Big Hill.

  • Trixie West Porphyry Target Drilling. One diamond drill hole was completed from underground testing porphyry-style mineralization down plunge of the mineralized structures below Trixie to a depth of 759.6 m (2,492 ft) when it crossed the Eureka Lily fault to the east and out of the prospective alteration zone.  

    • These results suggest that the western hanging wall block of the Eureka Lilly fault (west of Trixie) is potentially more conducive for porphyry-style mineralization.

    • Anomalous mineralization was encountered in the drill hole; however, no significant intercepts of gold, copper or molybdenum were encountered.

  • Zuma High-Potential Porphyry Target. Based on the results to date, the Zuma area has been identified as a good porphyry target that merits initial drill testing and may represent one of the causative porphyry centres of the East Tintic district.

  • Lower Quartzite CRD Target. Based on the compilation of geological, drilling, and historical data, a potential large scale carbonate replacement deposit ("CRD") may be located below the footwall of the East Tintic thrust fault. A recommended drill program has been proposed that targets downdip extensions of known mineralization at Burgin.

  • Trixie Underground Chip Sampling. The Company disclosed chip sample assays from new development areas at Trixie. Select assay highlights included (see news release dated August 7, 2024):  

    • 11.07 grams per tonne ("g/t") gold ("Au") and 25.45 g/t silver ("Ag") over 6.10 m in CH01716 (0.32 troy ounces per short ton ("oz/t") Au and 0.74 oz/t Ag over 20 ft).

  • Big Hill斑岩靶向钻探。2024年5月两个地表钻孔共计2920米(9581英尺)已完成,测试铜-金-钼斑岩成矿潜力。

    • 两个钻孔都通过至少三个晚期矿物质石英闪长岩和侵入物角砾岩定义的斑岩系统。

    • 尽管遇到了异常的铜和钼矿化物,包括低水平的黄铜矿,钝辉铜矿和黄钼矿的可见性,但没有观察到铜,黄金或钼的重要拦截。迄今为止遇到的埃迪克岩被认为缺乏证据以成为Tintic区矿化物的来源的主要流体路径。

    • Big Hill West靶区。最近和历史钻孔结果表明,早期和潜在更好的矿化侵入相位可能在Big Hill钻探区域的西部和西南部未经测试的区域。

  • Trixie West斑岩靶区钻探。从地下进行了一次钻孔,测试了Trixie下行矿化构造的流向似斑岩矿化到达了75960万(2,492英尺)深度,穿过了Eureka Lily断层并向东、远离可能的变质带。

    • 这些结果表明,Eureka Lilly断层(Trixie以西的西侧密挂墙)可能更有助于斑岩状矿化。

    • 在该钻孔中遇到了异常矿化,但未遇到金、铜或钼的显著拦截。

  • 祖马高潜靶区。根据迄今的结果,确定了祖马地区是一个不错的斑岩靶目,在东廷蒂克区域可能代表了一个原因斑岩中心之一,值得进行初步钻探测试。

  • 下部石英岩CRD靶区。根据地质、钻探和历史数据的汇编,可能位于东廷蒂克逆冲断层的基底下方一个潜在的大规模碳酸盐置换矿床(“CRD”)。建议了一个钻探计划,以瞄准在Burgin已知矿化的向下延伸。

  • Trixie地下走样。公司披露了来自Trixie新开发区域的走样化验结果。选择的化验亮点包括(请参见2024年8月7日的新闻发布):CH01716中的11.07克/吨(“g/t”)黄金(“Au”)和25.45g/t的银(“Ag”,610万个长度为0.32特洛伊盎司每短吨(“oz/t”)Au和0.74 oz/t Ag超过20英尺)。

    • 在CH01716,每吨610万克,含金11.07克/吨("Au"),含银25.45克/吨("Ag"),长度20英尺,每短吨0.32金衡制盎司("oz/t")Au,每短吨0.74盎司Ag。

San Antonio Gold Project – Sonora State, Mexico (100%-owned)

圣安东尼奥金矿项目-墨西哥索诺兰州(100%所有权)

  • The San Antonio Gold Project remains in care and maintenance, with no production anticipated henceforth.

  • The Company awaits next steps from the government of Mexico with respect to the permitting process and the status of open pit mining in the country. The approval process for environmental permits for mining may resume after the new president takes office in October 2024.

  • Strategic Review. The Company is conducting a strategic review of the project and has engaged a financial advisor in connection thereof. The strategic review includes, among others, exploring the potential for a financial or strategic partner in the asset or for a full or partial sale of the asset.

  • 圣安东尼奥金矿项目仍处于维护状态,无生产预期。

  • 公司正在等待墨西哥政府有关许可进程和该国露天采矿状态的下一步计划。获得有关采矿环境许可的批准进程可能会在2024年10月新总统上台后恢复。

  • 战略评估。公司正在对该项目进行战略评估,并已聘请一家财务顾问进行联系。其战略评估包括考虑为该资产寻找财务或战略伙伴,或对该资产进行全部或部分出售,以及其他方面的探索。

SUBSEQUENT TO Q2 2024

2024年第二季度后。

  • On July 5, 2024, the Company announced that effective July 4, 2024, as part of its annual compensation review, the Board of Directors approved the grant of an aggregate of 2,797,400 incentive stock options and an aggregate of 371,800 restricted share units to certain senior officers of the Company in accordance with the terms of the Company's Option and RSU plans.

  • 在2024年7月5日,公司宣布,在其年度薪酬评估的一部分,董事会批准向公司某些高级职员授予总计279,740股激励股票和总计37,180个受限股份单位,根据公司的期权和RSU计划条款。

KEY UPCOMING MILESTONES

关键即将到来的里程碑

Key Project
Milestones

Expected Timing
of Completion

Anticipated
Remaining Costs*

Cariboo Gold Project(1)

Bulk Sample

Q4 2024

$6.8 million

Water and Waste Management

Q4 2024

$0.1 million

Electrical and Communication

Q4 2024

$0.6 million

Management, environmental, and other pre-permitting work

Q3 2024

$5.2 million

Detailed engineering and permitting(2)

Q4 2024

$1.3 million

Tintic Project

Regional Drilling

Completed – Q2 2024

$nil

关键项目 里程碑

预计时间
完成时间

预期
剩余成本*

Cariboo金矿项目(1)

大样品

2024年第四季度

$6.8 million美元

水和废物管理

2024年第四季度

$100,000

电气和通讯

2024年第四季度

0.6百万美元

管理、环保母基、和其他预许可工作

2024年第三季度

520万美元

详细工程和许可(2)

2024年第四季度

$130万美元

廷蒂克项目

区域钻探

2024年第二季度完成

$nil

_____________________________
*as at June 30, 2024

_____________________________
*截至2024年6月30日

Notes:

注意:

(1)

The expenditures disclosed in this table include amounts approved by the Board of Directors up until the end of August 2024. Additional expenditures will be required to complete certain of the milestones and are subject to approval by the Board of Directors.

(2)

These activities are contributing towards the completion of permitting, which are presently expected to be completed in Q3 2024. Additional costs and time relating to engineering, including water and waste management and electrical and communication, will be required in the construction phase (subject to a positive construction decision and completion of project financing).

(1)

此表中披露的支出包括董事会批准的金额直至2024年8月底。完成某些里程碑需要额外支出,并且需经董事会批准。

(2)

这些活动有助于许可完成,目前预计将在2024年第三季度完成。在施工阶段(前提是做出积极的施工决策并完成项目融资),需要额外的工程费用和时间,包括水和废物管理以及电气和通讯。