Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) provides an update to the Guanacevi primary ball mill trunnion failure that was reported on August 12, 2024.

Endeavour Silver Corp.(“Endeavour”或“公司”)(纽交所:EXk,TSX:EDR)就2024年8月12日报告的Guanacevi一级球磨机小臂故障提供了更新。

Processing has resumed at the Guanacevi mine site. Temporary modifications have been completed within the plant to re-purpose one of the regrind mills as the primary ball mill which is currently milling at a rate of 400 tonnes per day (tpd). While the grinding circuit is being closely monitored, there is potential for the plant to operate near 500 tpd or close to half of its planned production capacity of 1,200 tpd during this temporary phase.

在Guanacevi矿区的处理已经恢复。在这个临时阶段内,已经完成了工厂内的临时更改,将一个再磨磨机重新用作主球磨机,目前的磨矿速率为每天400吨。虽然磨矿回路正在被密切监视,但是在这个临时阶段内,工厂能够接近半数运营,可能达到其1200吨/天的计划产能的一半。

During this time, mining operations will continue at a reduced rate without comprising safety or the long-term viability of the ore body. The operations will focus on feeding the highest-grade ore to the mill and stockpiling the remaining material. Contract mining activities and local third-party material purchases will cease until the process plant operations have returned to full capacity. These temporary solutions are intended to manage cash flows until the primary mill is fully operational. Using current metal prices, the preliminary estimate indicates a cash shortfall could be limited to during this period of reduced processing is less than US$5 million over an estimated 15-week period. This cash outflow includes accumulating ore stockpile with self-mining activities.

在此期间,采矿将以降低的速率继续进行,同时不影响矿体的安全性和长期可行性。操作将专注于将最高品位的矿石进料到磨机并堆储其余物料。自采矿活动的第三方地方材料购买将停止,直到流程工厂运营恢复到满负荷状态。这些临时解决方案旨在管理现金流,直到主磨机完全投入运营。根据当前的金属价格,初步估计表明,在预计的15周减产期间,现金短缺可能仅限于不到500万美元的现金流出。这笔现金流出包括使用自采矿活动积累的矿石库存。

Constructive discussions have been held with our workforce, communities and suppliers to address the potential implications and broader social impact of these temporary measures.

我们已与工作人员、社区和供应商进行了建设性的讨论,以应对这些临时措施可能带来的潜在影响和更广泛的社会影响。

Initial quotes for the trunnion fabrication and installation have been obtained with an estimated fabrication cost of US$0.5 million and a period of 16-weeks to installation. Management is assessing several alternatives to shorten the estimated downtime of the primary ball mill.

小臂制造和安装的初始报价已经获得,估计制造成本为50万美元,安装需要16周时间。管理层正在评估几种缩短主球磨机估计停机时间的替代方案。

During this reduced processing period, Guanacevi production is estimated to decrease by 0.9 million to 1.1 million silver ounces and by 2,000 to 3,000 gold ounces compared to its original operating plan. Annual consolidated silver production for 2024 is expected to range from 4.4 to 4.6 million ounces, and gold production is expected to be between 36,000 ounces and 38,000 ounces. Silver equivalent production for 2024 is now forecast to total between 7.3 million and 7.6 million ounces. We achieved 4.4 million silver equivalent ounces in the first half of the year.

在这个减产期间,Guanacevi的产量预计会下降90万至110万盎司的白银和2000至3000盎司的金,与其原始营运计划相比。2024年的年度综合白银产量预计在440万至460万盎司之间,黄金产量预计在36,000盎司至38,000盎司之间。2024年的银相当产量现预计总计为730万至760万盎司。我们在上半年实现了440万盎司的银相当产量。

Due to the reduced operating capacity for 15 weeks, operating costs and all in sustaining cost metrics will be higher than originally guided for 2024. Due to the number of variables, estimates and remaining uncertainties, management is withdrawing its cost guidance at this time.

由于15周的减产,运营成本和全部衡量成本指标将高于2024年的原始指导水平。由于变量、估计和剩余的不确定性很多,管理层此时撤回其成本指引。