Vancouver, British Columbia--(Newsfile Corp. - August 30, 2024) - Nicola Mining Inc. (TSXV: NIM) (OTCQB: HUSIF) (FSE: HLIA) (the "Company" or "Nicola") is pleased to provide updates on operations and exploration at its Merritt Mill, New Craigmont Copper Project and Treasure Mountain Mine.

尼科拉矿业公司(TSXV:NIM)(OTCQB:HUSIF)(FSE:HLIA)很高兴向大家提供有关其梅里特磨坊、新克雷格蒙特铜矿项目和宝山矿山运营和勘探的最新进展。

Merritt Mill
The Company continues to produce gold concentrate with mill feed from Talisker Resources Ltd. (TSX: TSK) (OTCQX: TSKFF) ("Talisker"), as announced on April 9, 2024. Because Bralorne mill feed contains free gold, Nicola reinstalled a gravity separator circuit for production. Gold concentrate is currently being stockpiled and prepared for sale, initial sale is expected to occur in September.

梅里特磨坊
公司继续利用来自塔利斯克资源有限公司(TSX:TSK)(OTCQX:TSKFF)的磨坊饲料生产金精矿,正如2024年4月9日宣布的那样。由于布拉罗恩磨坊的饲料含有自由金,尼科拉重新安装了一个用于生产的重力分离器电路。金精矿目前正在被储存并准备出售,预计首次销售将在九月份进行。


Nicola's Merritt Mill is the only facility in the Province of British Columbia permitted to accept third party gold and silver mill feed from throughout the province.


尼科拉的梅里特磨机是卑诗省唯一获得接受本省各地第三方金银矿石物料的许可的设施。

New Craigmont Copper Project 2024 Exploration
The first phase of the 2024 drilling exploration program commenced at the never-drilled-before West Craigmont-WP Zone and has progressed with the drilling of four holes (the last of which is still in progress), totaling ~1,500m of the 5000m program. Zone targets were generated by using geophysical models and outcrop maps. Drill hole locations hope to establish a framework for the subsurface geology and reconcile the geophysical anomalies with geological features, with the goal of refining the targeting of a potential porphyry copper system in the region. Initial results are aiding in delineating the Nicola-Guichon contact and local structures. The observed alteration and mineralization are encouraging, aligning with the expectations for the periphery of a porphyry system. These findings will be further analyzed to vector for a potential nearby deposit. Notably altered fault blocks featuring quartz-sericite-pyrite ± chalcopyrite is of particular interest, supporting the need for additional drilling at this target.

2024年新克雷格蒙特铜矿项目勘探
2024年勘探工程的第一阶段开始于尚未钻探过的西克雷格蒙特-WP区,并在钻探四个孔洞的过程中得到了进展(最后一个孔洞仍在进行中),总计为500000万的计划完成了约150000万的工作。通过使用地球物理模型和露头图生成了区域目标。钻孔位置希望建立地下地质的框架,并调和地球物理异常与地质特征,以精确定位地区可能的斑岩铜体系的目标。初步结果有助于界定尼科拉-圭冲接触带和当地地质构造。观察到的蚀变和矿化情况令人鼓舞,与斑岩体系外围的预期相一致。这些发现将进一步分析以确定潜在附近矿床。特别值得注意的变质断块具有石英-白云母-黄铁矿±黄铜黄铁矿,这引起了特别的关注,支持需要在该目标处进行更多钻探的需求。


Hole WP-24-001: Designed to test the largest IP chargeability anomaly in the area, detected by the 2024 IP survey. Significant pyrite mineralization, with trace chalcopyrite, was encountered between 59.6 and 108.0m. The mineralization is hosted within faulted Nicola volcanic rocks, which exhibit intense sericite-quartz alteration.
The photo displays pyrite mineralization with sericite-quartz alteration.


孔洞WP-24-001:旨在测试该区域最大的IP可充电异常,该异常是由2024年IP勘测发现的。在59.6和10800万之间发现了重要的黄铁矿化,伴有痕量的黄铜黄铁矿。矿化体位于断裂的尼科拉火山岩中,显示出强烈的白云母-石英蚀变。
照片显示了含有绢云母-石英蚀变的黄铁矿化。


Hole WP-24-002 targeted a relatively shallow IP chargeability anomaly. The hole intercepted a similar faulted mineralization zone as WP-24-001, with pyrite and trace chalcopyrite mineralization in sericite-quartz altered Nicola volcanic rocks from 47.1 to 100.9m.
Pyrite mineralization with sericite-quartz alteration is shown in the photo.


WP-24-002孔钻探的目标是一个相对较浅的IP电荷异常。该孔穿过了与WP-24-001相似的断层矿化带,其中含有黄铁矿和微量黄铜矿,岩石为绢云母-石英蚀变的尼古拉火山岩,层位为47.1至10090万。
照片中显示了含有绢云母-石英蚀变的黄铁矿化。


Hole WP-24-003 was drilled at a shallow angle to further investigate the largest IP chargeability anomaly targeted by WP-24-001. This hole encountered fault-hosted pyrite (+/- chalcopyrite) mineralization intervals between 298.8m and 316.3m and 358.9m to 365.4m. Notably, chalcopyrite and bornite blebs were observed throughout the hole.
Quartz vein hosted chalcopyrite-bornite mineralization is circled in red.


WP-24-003孔以较浅的角度钻进,以进一步调查WP-24-001目标的最大IP电荷异常。该孔遇到了由断层容纳的黄铁矿(+/-黄铜矿)矿化间隔,层位为29880万至31630万和35890万至36540万。值得注意的是,整孔中观察到了黄铜矿和黝铜矿斑点。
石英脉容纳的黄铜矿-黝铜矿矿化被用红色圈出。

Upon completion of WP-24-004A, the drill rig will likely begin the second phase of the 2024 exploration program, drilling on the MARB-CAS target (before possibly moving back to West Craigmont-WP). This target was identified through bedrock mapping and surface geology observations, with some contribution from geophysical modeling. The planned drilling aims to develop a framework for the subsurface geology and assess mineralization potential beneath the MARB showing.

在WP-24-004A完成后,钻机可能会开始2024年勘探计划的第二阶段,在MARb-CAS目标上进行钻探(可能会回到West Craigmont-WP)。此目标是通过基岩映射和地表地质观察确定的,并在一定程度上受到地球物理模拟的影响。计划的钻探旨在发展地下地质框架,并评估MARb展示下方的矿化潜力。

Treasure Mountain Ten Year Mine Lease Extension
The Company is pleased announce that it has receive a very important ten-year mining lease extension (the "Extension") for its wholly owned Treasure Mountain Mine (the "Treasure Mountain"), which is located approximately 27 km to the east-northeast of Hope, BC, Canada (Figure 1). The Extension is good through April 26, 2032. Treasure Mountain is comprised of a total 30 mineral claims (2178.3 ha) and 1 mining lease (335 ha) and (Figure 2).

宝藏山矿场十年租赁延期
公司高兴地宣布,其全资拥有的宝藏山矿场(“宝藏山”)已获得了一项非常重要的十年采矿租赁延期(“延期”),该矿场位于加拿大BC省Hope市东北东约27公里处(图1)。 延期有效至2032年4月26日。 宝藏山由总共30个矿权(2178.3公顷)和1个矿业租赁(335公顷)组成(图2)。


Figure 1: Overview of the location of the Treasure Mountain Project


图1:宝山项目的位置概览


Figure 2: Mineral Claims and Mining Leases the Treasure Mountain Property


图2:宝山财产的矿权和采矿租约

Treasure Mountain Mine, which was first discovered in 1892 and operated intermittently since being first recognized. From 1930-1932, onsite milling operations processed ~4,000 tonnes that yielded 39,558 oz Ag, 379,532 lbs Pb, and 88,455 lbs Zn. Between 1987 and 1989, mine development at four levels occurred and 407 tonnes of partially sorted material was shipped to Cominco and Asarco smelters.

宝山矿,于1892年首次发现并自那时开始间歇运营。从1930年到1932年,现场精矿作业处理了约4,000吨矿石,产出了39,558盎司的银、379,532磅的铅和88,455磅的锌。在1987年至1989年期间,宝山开发了四个级别,并运送了407吨部分分选的材料给Cominco和Asarco冶炼厂。

The Company received a Mines Act Permit approving the production for 60,000 tonnes of material per annum for Treasure Mountain on May 18, 2012: Permit M-239. The Extension of Permit M-239 provides Nicola the option of reopening Treasure Mountain and could expedite permitting approval for new mineralized bodies, if discovered.

公司于2012年5月18日收到了一项矿山法许可证,批准在宝山每年生产60,000吨的材料:许可证m-239。许可证m-239的延期为尼科拉提供了重新开采宝山的选择,并且如果发现了新的矿化体,可以加速许可证的批准。

A June 15th, 2009 NI 43-101-compliant technical report disclosed that the total vein Indicated Resource above a 10.0 oz/t Ag cut-off was estimated to be 33,000 tonnes with 24.2 oz/t silver, 4.16% lead and 3,80% zinc. The total vein Inferred Resource above a 10.0 oz/t Ag cut-off was estimated to be 120,000 tonnes with 27.0 oz/t silver, 2.79% lead and 4.36% zinc. The company retains the option to reopen Stope 2 on Level 1 (Figure 3), which remains in-situ.

根据2009年6月15日的一份符合NI 43-101标准的技术报告披露,估计以上10.0盎司/吨的银为截止点,总共有33,000吨脉石资源,含银24.2盎司/吨、铅4.16%和锌3.80%。估计以上10.0盎司/吨的银为截止点,总共有120,000吨脉石资源,含银27.0盎司/吨、铅2.79%和锌4.36%。公司保留了重新开采第1级别的第2堵采场的选项(图3),该采场仍在原地。


Figure 3: Section view of the Treasure Mountain underground workings (Level 1, 2, 3 with stope projections)


图3:宝山地下工程的剖面图(1级别、2级别、3级别以及采场估计)

Mr. Peter Espig, CEO of Nicola Mining Inc., commented, "We are extremely excited about our current operations and ongoing exploration. The Merritt Mill is a state-of-the-art facility that garners interest from high grade gold projects throughout the province because of its location and flexible permitting that can expedite project cashflow. In addition to procuring the ten-year mine lease extension for Treasure Mountain, we have also submitted a multi-year area-based exploration permit application for the project. The synergistic combination of the Merritt Mill and Treasure Mountain was the basis of a $200 million market capitalization back in 2012; however, the latter seems to be somewhat forgotten since its placement into care and maintenance and because of Nicola's subsequent consolidation of its ownership in the New Craigmont Project. Management continues to recognize the standalone potential of Treasure Mountain and remains excited about the exploration prospects of the project. Finally, we are pleased with the 2024 Exploration Program at our flagship asset, New Craigmont Copper Project and are currently completing initial exploration at the West Craigmont-WP target prior to drilling MARB and CAS. Drilling at the MARB and CAS will commence early September and will change from one to two crews to expedite results."

尼科拉矿业有限公司首席执行官彼得·埃斯皮格评论道:“我们对目前的运营和持续的勘探工作非常兴奋。美里特磨矿厂是一个先进设施,因其地理位置和灵活的许可证,吸引了整个省份高品位黄金项目的兴趣,可以加速项目现金流。除了为宝山获得了为期十年的矿山租约延期外,我们还为该项目提交了基于区域的多年期勘探许可证申请。美里特磨矿厂与宝山的协同组合是2012 年市值为2千万美元的基础;然而,由于宝山的保守维护和尼科拉随后对新克雷格蒙特项目所有权的整合,宝山似乎有些被忘记了。管理层继续认识到宝山独立的潜力,并对该项目的勘探前景保持兴奋。最后,我们对我们的旗舰资产新克雷格蒙特铜矿项目的2024年勘探计划感到满意,并目前正在西克雷格蒙特-WP目标区进行初步勘探,然后将进行MARb和CAS的钻探。MARb和CAS的钻探将于9月初开始,并将从一个团队转为两个团队,以加速结果的获取。”

Qualified Person
William Whitty, P. Geo., the Company's VP Exploration, is the Qualified Person as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects and supervised the preparation of, and has reviewed and approved, the technical information in this release.

合格人士
William Whitty, P.Geo.,公司的勘探副总裁,是《43-101矿产项目披露标准》规定的有资格人员,并监督了本发布的技术信息的编制、复审和批准。

About Nicola Mining
Nicola Mining Inc. is a junior mining company listed on the Exchange and Frankfurt Exchange that maintains a 100% owned mill and tailings facility, located near Merritt, British Columbia. It has signed Mining and Milling Profit Share Agreements with high grade gold projects. Nicola's fully permitted mill can process both gold and silver mill feed via gravity and flotation processes.

关于Nicola Mining
Nicola Mining Inc.是一家上市交易所和法兰克福交易所的初创矿业公司,拥有一个100%拥有的磨矿厂和尾矿设施,位于不列颠哥伦比亚省的Merritt附近。它已与高品位黄金项目签署了矿业和磨矿利润分成协议。 Nicola的完全许可的工厂可以通过重力和浮选工艺加工金银矿石。

The Company owns 100% of the New Craigmont Project, a high-grade copper property, which covers an area of over 10,800 hectares along the southern end of the Guichon Batholith and is adjacent to Highland Valley Copper, Canada's largest copper mine. The Company also owns 100% of the Treasure Mountain Property, which includes 30 mineral claims and a mineral lease, spanning an area exceeding 2,200 hectares.

公司拥有New Craigmont项目的100%股权,这是一个高品位铜金属矿产,覆盖了南部Guichon岩体的超过10,800公顷区域,毗邻加拿大最大的铜矿Highland Valley Copper。公司还拥有Treasure Mountain Property的100%股权,包括30个矿权和1个矿业租约,涵盖超过2,200公顷的区域。

On behalf of the Board of Directors

谨代表董事会

"Peter Espig"

“Peter Espig”

Peter Espig
CEO & Director

Peter Espig
CEO&董事

For additional information

获取更多信息,请联系:

Contact: Peter Espig
Phone: (778) 385-1213
Email: info@nicolamining.com
URL:

联系人:Peter Espig
电话:(778) 385-1213
邮箱:info@nicolamining.com
URL:

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

TSX Venture Exchange及其监管服务提供者(如TSX Venture Exchange的政策所定义的那样)对此发布的充分性或准确性不承担任何责任。

声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发