American Pacific Reports Results From First Drill Holes at Madison: Including 38.25 Metres of 1.28% Copper and 1.22 G/t Gold and 32.71 Metres of 3.15 G/t Gold

American Pacific Reports Results From First Drill Holes at Madison: Including 38.25 Metres of 1.28% Copper and 1.22 G/t Gold and 32.71 Metres of 3.15 G/t Gold

美国太平洋报告麦迪逊第一口钻孔结果:包括铜1.28%和金1.22克每吨的38.25米,以及金3.15克每吨的32.71米
newsfile ·  2024/09/04 07:00

Vancouver, British Columbia--(Newsfile Corp. - September 4, 2024) - American Pacific Mining Corp (CSE: USGD) (OTCQX: USGDF) (FSE: 1QC1) ("American Pacific" or "the Company") is pleased to report assay results from the first three (3) holes of the Company's seven (7) hole Phase I drill program at its Madison Copper-Gold Project in Montana. The Phase I drilling program, which is now complete, focused on extending mineralization near previously mined areas with the goal of demonstrating significant gold and copper mineralization beyond the historical mine workings.

温哥华,英属哥伦比亚--(新闻发布 - 2024年9月4日) - 美国太平洋矿业公司(CSE: USGD)(OTCQX: USGDF)(FSE: 1QC1)("美国太平洋"或"公司")很高兴地报告了在蒙大拿州麦迪逊铜金项目进行的第一阶段(7个)钻探计划的前三个(3)个钻孔的化验结果。阶段I钻探计划已经完成,重点是延伸矿化区域,以证明在历史开采区域周围存在重要的黄金和铜矿化。

Highlights:

亮点:

  • APMMAD24-02: 38.25 m of 1.28% Cu and 1.22 g/t Au (2.34% Cu Eq)**, including 2.08% Cu and 2.43 g/t Au over 7.86 m (see Figure 1)

  • APMMAD24-05: 32.71 m of 3.15 g/t Au, including 7.32 m of 9.90 g/t Au; and 45.45 m of 0.96% Cu, including 16.00 m of 2.02 % Cu

  • APMMAD24-01: 1.04 g/t Au over 17.04 m within a broader mineralized envelope of 32 m at 0.76 g/t Au. Multiple zones of Cu mineralization with 0.43% Cu over 17.37 m, including 1.39% Cu over 3.05 m

  • APMMAD24-02: 3825万吨,铜含量1.28%和金含量1.22克/吨(2.34%铜当量),包括786万吨,铜含量为2.08%,金含量为2.43克/吨(见图1)

  • APMMAD24-05: 3271万吨,金含量3.15克/吨,包括732万吨,金含量9.90克/吨;4545万吨,铜含量0.96%,包括1600万吨,铜含量2.02%

  • APMMAD24-01: 1.04克/吨金,包括1704万吨,在较广泛的矿化包体内,含金量为0.76克/吨,3200万吨。多个铜矿化带,包括0.43%铜,1737万吨,含1.39%铜,3.05米

*Notes: m = metres; g/t = grams per tonne; Au = gold; Cu = copper

*注:m = 米; g/t = 每吨克拉; Au = 黄金; Cu = 铜

**The copper equivalence estimate used for APMMAD24-02 is assumed to be in-situ using US$2,350 per ounce gold and $3.95 per pound copper. There has not been sufficient metallurgical work completed to determine or apply a metal recovery for this estimate.

**APMMAD24-02的铜当量估算假定采用座和US$2,350每盎司黄金和每磅$3.95铜。尚未完成足够的冶金工作来确定或应用此估算的金属回收率。

"These initial results have demonstrated that significant amounts of gold and copper mineralization extend well beyond the historical mined areas. In addition, the broader than expected intervals highlight the potential for mineralization left behind from historical mining that operated at a much higher cut-off grade," commented CEO, Warwick Smith. "We eagerly await further assay results, which we expect will continue to demonstrate the opportunity to define significant concentrations of both copper and gold."

"这些初步结果表明,大量的黄金和铜矿化扩展到历史开采区域之外。此外,比预期更广的区间突显了历史开采留下的矿化的潜力,其操作的截止品位要高得多,"首席执行官沃里克·史密斯评论道。"我们迫切期待进一步的化验结果,我们期望继续证明定义大量的铜和金浓集的机会。"

Figure 1. Plan map showing gold and copper results from Holes 1, 2 and 5

图1. 显示1号、2号和5号钻孔的金和铜结果的平面图

Initial Observations and Interpretations

初步观察和解读

Past mining practices were heavily based on metallurgy, visual mining, and processing capabilities at that time. Substantial high-grade copper and gold mineralization, that was not included in the previous operator's mine plan, remains in close proximity to mine workings. This Phase I drill program offers both near-mine exploration potential and expansion opportunities, but more importantly helps vector the Company into a more focused district-scale evaluation. Future targeting for Phase II drilling will focus on a possible expansion to the west and at depth (see Figure 2) where targets remain open and untested.

过去的采矿实践严重依赖于冶金学、目视采矿和当时的加工能力。大量高品位的铜和金矿化物未包括在先前运营商的矿山计划中,仍与矿山工作区域相邻。该I期钻探项目既具有靠近矿山的勘探潜力和扩展机会,更重要的是帮助该公司进入一个更具重点的区域规模评估。II期钻探的未来目标将集中在可能的西部和深部扩展(参见图2),其中目标仍然开放和未经测试。

Figure 2. Section showing multiple copper and gold intervals from APMMAD24-05

图2. 显示APMMAD24-05的多个铜和金区间的截面图

Table 1. Gold and copper drill results from Phase I (See "Notes" below)

表1. I期钻孔的金和铜钻探结果(见下面的“注释”)

Hole ID From (m) To (m) Interval (m) Au g/t Cu %
APMMAD24-05 29.6 62.3 32.71 3.15 0.01
including 48.8 56.1 7.32 9.90 0.01
and 110.9 124.4 13.44 1.12 2.11
and 93.6 139.0 45.45 0.45 0.96
including 106.7 122.7 16.00 1.11 2.02
also including 110.9 113.7 2.74 1.94 7.10

APMMAD24-02 97.1 135.3 38.25 1.22 1.28
including 98.3 106.2 7.86 2.43 2.08

APMMAD24-01 19.0 37.9 18.93 0.24 0.00
and 59.1 91.1 32.00 0.76 0.35
including 72.7 89.7 17.04 1.04 0.16
and 62.0 74.2 12.22 0.54 0.44
including 62.0 67.1 5.06 0.42 0.70
and 85.3 102.7 17.37 0.49 0.43
including 87.5 90.5 3.05 0.64 1.39
孔ID 从(m) 到(m) 间隔(米)。 Au克/吨 Cu %
项目的分析方法包括: 29.6 62.3 32.71美元 3.15 0.01
包括 48.8 56.1 7.32 9.90 0.01
110.9 124.4 13.44 1.12 2.11
93.6 139.0 45.45 0.45 0.96
包括 106.7 122.7 16.00 1.11 2.02
including 110.9 2.74 1.94 7.10

预计在接下来的几周内将有进一步的一期计划结果。 97.1 135.3 38.25 1.22 1.28
包括 98.3 106.2 7.86 2.43 2.08

为确保可靠性和准确性,严格遵循QAQC协议,包括: 19.0 $37.9万 18.93 0.24 0.00
59.1 91.1 32.00 0.76 0.35
包括 72.7 89.7 17.04 1.04 0.16
62.0 74.2 12.22 0.54 0.44
包括 62.0 67.1 5.06 0.42 0.70
85.3 102.7 17.37 0.49 0.43
包括 87.5 90.5 3.05 0.64 1.39


Notes: Sufficient work has not been completed to determine true widths for the intervals reported. All intervals are reported as core length.

Additional results from the Phase I program are expected in the coming weeks.

Madison Project Sampling and Analysis Quality Assurance and Quality Control Statement

At the Madison Project, the Company is committed to maintaining high standards of accuracy and reliability in our sampling and analysis procedures. The following Quality Assurance and Quality Control (QAQC) measures are employed in our sampling and analysis processes.

Analytical Methods for the project include:

  1. 50AR-MS - 50 Element Suite using a 0.5g Aqua Regia (AR) digestion followed by ICP-MS (Inductively Coupled Plasma Mass Spectrometry)

  2. AUAG-GR30 - Au and Ag Analysis with a 30g fire assay with a gravimetric finish

  3. Au-FA30 - Au Analysis using a 30g fire assay combined with AQR digestion, followed by Atomic Absorption Spectroscopy (AAS) or Optical Emission Spectroscopy (OES)

  4. OLAR-OES - Over limits Aqua Regia Digestion & Analysis in instances where elemental concentrations exceed standard ranges

  5. PA-AU02 - PhotonAssay to duplicate gold assays

  6. S-LECO - Total Sulfur Analysis using the LECO method

Sampling Methodology:

Whole core sampling has been adopted in specific contexts to mitigate the effects of sample variability and reduce any "nuggetting" effect.

Quality Control Measures:

To ensure reliability and accuracy stringent QAQC protocols are followed including:

  • Use of Certified Reference Materials (CRMs) at a rate of 1:20

  • Replicate Analysis are performed to ensure accuracy

  • Blanks are inserted at a rate of 1:20

Qualified Person

资格人员

Technical aspects of this press release have been reviewed and approved by the designated Qualified Person under National Instrument 43-101, Managing Director of Exploration, Eric Saderholm, P.Geo.

About American Pacific Mining Corp.

American Pacific Mining Corp. is a precious and base metals explorer and developer focused on opportunities in the Western United States. The Company has two flagship assets: the Palmer Project, a Volcanic Massive Sulphide-Sulphate (VMS) project in Alaska, under joint-venture partnership with Dowa Metals & Mining, owner of Japan's largest zinc smelter; and the Madison Project, a past-producing copper-gold project in Montana. For the Madison transaction, American Pacific was selected as a finalist in both 2021 and 2022 for 'Deal of the Year' at the S&P Global Platts Metals Awards, an annual program that recognizes exemplary accomplishments in 16 performance categories. Also, in American Pacific's asset portfolio are high-grade, precious metals projects located in key mining districts in Nevada, USA, including the Ziggurat Gold project and the Tuscarora Gold-Silver project. The Company's mission is to grow by drill bit and by acquisition.

On behalf of the American Pacific Mining Corp Board of Directors:

Warwick Smith, CEO & Director
Corporate Office: Suite 910 - 510 Burrard Street
Vancouver, BC, V6C 3A8 Canada

公司办事处:510 Burrard Street,910号套房
705.677.3949(加拿大安大略省萨德伯里)公司总部邮编:V6C3A8加拿大温哥华
加拿大BC省温哥华V6C 3A8

Investor relations contact:

投资者关系联系方式:

Kristina Pillon, High Tide Consulting Corp.
604.908.1695 / Kristina@americanpacific.ca

Kristina Pillon,High Tide Consulting Corp。
604.908.1695/Kristina@americanpacific.ca

Media relations contact:

媒体关系联系人:

Adam Bello, Primoris Group Inc.
416.489.0092 / media@primorisgroup.com

Adam Bello,Primoris Group Inc。
416.489.0092/ media@primorisgroup.com

Full disclosure can be found in our NI 43-101 Technical Report for the Madison Project at ().

The Canadian Securities Exchange has neither approved nor disapproved the contents of this news release.