LUCA PROVIDES UPDATE ON CAMPO MORADO PERFORMANCE AND COMMENCEMENT OF STAGE 3 OF IMPROVEMENT PROJECT
LUCA PROVIDES UPDATE ON CAMPO MORADO PERFORMANCE AND COMMENCEMENT OF STAGE 3 OF IMPROVEMENT PROJECT
VANCOUVER, BC, Oct. 10, 2024 /PRNewswire/ - Luca Mining Corp. ("Luca" or the "Company") (TSXV: LUCA) (OTCQX: LUCMF) (Frankfurt: Z68) is pleased to announce the successful implementation of the first two stages of the Campo Morado Improvement Project (CMIP) and commencement of Stage 3.
温哥华,卑诗省,2024年10月10日 / PRNewswire/ - Luca Mining Corp.("Luca"或"公司")(TSXV: LUCA)(OTCQX: LUCMF)(Frankfurt: Z68)很高兴宣布成功实施Campo Morado改进项目(CMIP)的头两个阶段,并启动第3阶段。
In Q4 2023 the Company partnered with Ausenco México S. de R.L. de C.V. ("Ausenco") to implement a staged improvement project designed to increase metallurgical performance, mill throughput, sustaining plant performance and operating cash flow. The initial phase of the project (Stage 1) included a comprehensive geometallurgical program focused on sampling, training and procedures as well as optimizing the process controls in the plant. The primary goal of Stage 2 was sustainable operations and improving plant reliability. Stage 3 will now build on the improvements to date and implement a new flow sheet with modest modifications to the plant with the goal of producing three high-quality, saleable concentrates of copper, lead and zinc.
2023年第4季度,该公司与Ausenco México S. de R.L. de C.V.("Ausenco")合作,实施了一个分阶段的改进项目,旨在提高冶金性能,磨机 through 吞吐量,维持性工厂性能和经营现金流。该项目的初始阶段(第1阶段)包括一个专注于取样、培训和程序的全面地球冶金计划,以及优化工厂中的流程控制。第2阶段的主要目标是可持续经营和提高工厂可靠性。第3阶段现在将基于迄今为止的改进,并通过将工厂略微改进的方式实施新的流程图,目标是生产三种高质量、可销售的铜、铅和锌精矿。
The CMIP has already delivered significant financial benefits to the Campo Morado operation with only minor changes to the process plant. These benefits have mostly come from higher copper recovery which has improved by 53% over the same period in 2023. Copper recovery to the bulk concentrate year-to-date (YTD)1 is 68.5% compared to 44.7% during the same period in 2023. Figure 1 below shows bulk concentrate copper grade and Figure 2 shows copper recovery over the last 21 months. This has resulted in an estimated 10% increase of revenue per milled tonne2 over the same period year-on-year assuming constant metals prices.
CMIP已经为Campo Morado的运营带来了显著的财务收益,只对工厂流程进行了轻微改动。这些收益主要来自较高的铜回收率,在2023年同期的基础上提高了53%。截至目前(YTD)1,粗精矿铜回收率为68.5%,而2023年同期为44.7%。下面的图1显示了粗精矿铜品位,图2显示了过去21个月的铜回收率。这导致估计每吨磨矿2的收入同比增加了10%,假设金属价格保持不变。
Work has begun on Stage 3 of the CMIP project which consists of modest but important modifications to the processing plant, including:
CMIP项目的第3阶段工作已经开始,包括对处理设备的轻微但重要的修改,具体包括:
- Revised metallurgical sampling systems.
- Modernization of reagent dosing systems.
- New flotation cell air flow monitoring and control.
- Installation of next generation pH/ORP probes.
- New bulk rougher concentrate surge tank. Modifications to the bulk regrind circuit to operate with 2-stage regrinding.
- 修订后的冶金取样系统。
- 试剂剂量系统的现代化。
- 新的浮选电池气流监控和控制。
- 安装下一代pH/ORP探头。
- 新的粗选精矿浮渣槽。对散矿重新粉磨电路进行改造,以便进行两级再磨操作。
Completion of Stage 3 will increase the degree of liberation of the copper and lead minerals, allowing for collection in two separate concentrates through a sequential flotation process. In conjunction with the refurbishment of equipment and a new mine-to-mill strategy, it is anticipated that the CMIP will deliver more robust revenues for the Campo Morado operation. The Company expects to test the copper-lead separation process by the end of the year, with full project completion by Q2 2025.
第3阶段的完成将提高铜和铅矿物的解离程度,通过顺序浮选工艺将其分别收集到两个独立的浓缩体中。结合设备翻新和新的从矿到磨策略,预期CMIP将为Campo Morado运营提供更强大的营业收入。公司预计将在年底之前测试铜铅分离工艺,并计划在2025年第二季度完成整个项目。
The Company, together with Ausenco, has demonstrated that the Campo Morado mine and mill are capable of sustained profitable operations and future work will continue to enhance the value of the asset.
公司与Ausenco一起证明了Campo Morado矿山和磨的持续盈利运营能力,未来的工作将继续增加资产价值。
CEO Dan Barnholden commented, "The improvements at Campo Morado have been an outstanding success to date and moving to Stage 3 of this program demonstrates Luca's commitment to ongoing improvement at our assets.
首席执行官丹·巴恩霍尔登评论说:“迄今为止,在Campo Morado的改进取得了巨大成功,进入该项目的第3阶段显示了Luca对我们资产持续改进的承诺。
We intend to produce three clean, fully saleable and higher value concentrates of copper, zinc, and lead, which will have an immediate, positive impact on revenues and, ultimately, cash flow."
我们打算生产三种纯净、完全可销售且价值更高的铜、锌和铅浓缩物,这将立即对营业收入产生积极影响,并最终对现金流产生影响。”
- YTD includes preliminary production data up to and including September 2024.
- It is noted that this calculation is approximate given that total revenue received in any given period is based on several factors including but not limited to head grade, recovery and prices of multiple, marketable metals over time.
- YTD包括截至2024年9月的初步生产数据。
- 请注意,此计算是近似值,因为在任何给定期间收到的总营业收入基于包括但不限于含金量、回收率和多种可交易金属的价格等多个因素。
About Ausenco
Ausenco is a global company redefining what is possible. The team is based across 26 offices in 15 countries, delivering services worldwide. Combining deep technical expertise with a 30-year track record, Ausenco delivers innovative, value-add consulting studies, project deliver, asset operations and maintenance solutions to the minerals and metals and industrial sectors (www. ausenco.com)
关于Ausenco
Ausenco是一家全球公司,正在重新定义可能性。团队分布在15个国家的26个办事处,为全球提供服务。Ausenco将深厚的技术专长与30年的记录相结合,为矿产、金属和工业领域提供创新、增值的咨询研究、项目交付、资产运营和维护解决方案(www.ausenco.com)。
About Luca Mining Corp.
Luca Mining (TSX-V: LUCA, OTCQX: LUCMF, Frankfurt: Z68) is a diversified Canadian mining company with two 100%-owned producing mines within the prolific Sierra Madre mineralized belt in Mexico which hosts numerous producing and historic mines along its trend. The Company produces gold, copper, zinc, silver and lead from these mines that each have considerable development and resource upside.
关于 Luca Mining Corp.,Luca Mining(TSX-V: LUCA,OTCQX: LUCMF,Frankfurt: Z68)是一家多元化的加拿大矿业公司,在墨西哥拥有两个100%持有的生产矿山。该公司从这些矿山产出金属、铜、锌、白银和铅,均具有相当的开发和资源潜力。其中,Campo Morado 矿是墨西哥显示的采矿地点,是一个地下作业,它以金属铜、铅和锌的精矿为主,并且有贵金属信贷。目前,该矿正在进行优化,已经产生了回收率、品位、效率和现金流方面的显着提高。该公司预计,其业务将在2024年开始产生正现金流。Luca Mining 着眼于增长,以最大化股东的回报。
Luca Mining(TSX-V: LUCA,OTCQX: LUCMF,Frankfurt: Z68)是一家多元化的加拿大矿业公司,在墨西哥繁盛的西尔拉马德雷矿化带内拥有两个100%自有的生产矿山,该地区拥有多处生产和历史悠久的矿山。该公司从这些矿山生产黄金、铜、锌、白银和铅,每个矿山都有相当的发展和资源增长潜力。
The Campo Morado mine, is an underground operation located in Guerrero State. It produces copper-zinc-lead concentrates with precious metals credits. It is currently undergoing an optimization program which is already generating significant improvements in recoveries and grades, efficiencies, and cashflows.
Campo Morado矿山是位于格雷罗州的一个地下控件,生产含有贵金属信贷的铜锌铅精矿。目前,该矿山正在进行优化方案,已经在提高回收率和品位、效率和现金流方面取得显著改善。
The Tahuehueto Gold, Silver Mine is a new underground operation in Durango State. which hosts numerous producing and historic mines along its trend. The Company is commissioning its mill and is expected to achieve commercial production by the end of the year.
Tahuehueto金银矿是杜兰戈州的一个新的地下控件,沿着其走向分布着众多生产和历史悠久的矿山。公司正在启动铣机,并计划在年底前实现商业生产。
On Behalf of the Board of Directors
(signed) "Dan Barnholden"
Dan Barnholden, Chief Executive Officer
董事会代表
(签字) "丹·巴恩霍尔登"
丹·巴恩霍尔登,首席执行官
For more information, please visit:
欲知详情,请访问:
Qualified Persons
合格人员
The technical information contained in this News Release has been reviewed and approved by Mr. Chris Richings, Vice-President Technical at Luca Mining as the Qualified Person for the Company as defined in National Instrument 43-101.
本新闻稿中所包含的技术信息已由Luca Mining的技术副总裁Chris Richings先生作为该公司的独立合格人员(如《43-101国家规定》定义)进行审查并获得批准。
Cautionary Note Regarding Forward-Looking Statements
关于前瞻性声明的谨慎说明
It should be noted that Luca declared commercial production at Campo Morado prior to completing a feasibility study of mineral reserves demonstrating economic and technical viability. Accordingly, readers should be cautioned that Luca's production decision has been made without a comprehensive feasibility study of established reserves such that there is greater risk and uncertainty as to future economic results from the Campo Morado mine and a higher technical risk of failure than would be the case if a feasibility study were completed and relied upon to make a production decision. Luca has completed a preliminary economic assessment ("PEA") mining study on the Campo Morado mine that provides a conceptual life of mine plan and a preliminary economic analysis based on the previously identified mineral resources (see news releases dated November 8, 2017, and April 4, 2018).
应注意的是,Luca在完成矿区储量的经济和技术可行性证明之前即宣布Campo Morado开始商业生产。因此,读者应当注意,Luca的生产决策是在没有全面的储量可行性研究的情况下做出的,因此,与完成并依赖于完整的可行性研究进行生产决策相比,未来Campo Morado矿产的经济结果存在更高的风险和不确定性以及更高的技术风险。Luca已对Campo Morado矿进行了初步经济评估(PEA)采矿研究,该研究基于先前确定的矿物资源进行概念性终身规划和初步经济分析(详见2017年11月8日和2018年4月4日的新闻稿)。
Statements contained in this news release that are not historical facts are "forward-looking information" or "forward-looking statements" (collectively, "Forward-Looking Information") within the meaning of applicable Canadian securities laws. Forward Looking Information includes, but is not limited to, disclosure regarding the anticipated revenue increases as a result of CMIP; other possible events, conditions or financial performance that are based on assumptions about future economic conditions and courses of action; the timing and costs of future activities on the Company's properties, including Stage 3 of CMIP. In certain cases, Forward-Looking Information can be identified using words and phrases such as "plans," "expects," "scheduled," "estimates," "forecasts," "intends," "anticipates" or variations of such words and phrases. In preparing the Forward-Looking Information in this news release, the Company has applied several material assumptions, including, but not limited to, that copper recoveries will be as assumed; that metals prices will remain constant; that the current exploration, development, environmental and other objectives concerning the Campo Morado Mine can be achieved; the program to improve mining operations at Campo Morado will proceed as planned; the continuity of the price of gold and other metals, economic and political conditions, and operations. Forward-Looking Information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the Forward-Looking Information. There can be no assurance that Forward-Looking Information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on Forward-Looking Information. Except as required by law, the Company does not assume any obligation to release publicly any revisions to Forward-Looking Information contained in this news release to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events.
本新闻稿中包含的非历史事实的陈述为“前瞻信息”或“前瞻性声明”(统称“前瞻性信息”),属于适用加拿大证券法的意义内。前瞻性信息包括但不限于披露有关预期营业收入增加的CMIP结果;可能基于未来经济状况和行动方针假设的其他可能事件、情况或财务表现;涉及公司资产未来活动的时间和成本,包括CMIP的第3阶段。在某些情况下,可以使用“计划”、“预期”、“安排”、“估计”、“预测”、“意图”、“预期”或类似词语和短语来识别前瞻性信息。在本新闻稿中准备前瞻性信息时,公司已经应用了几项实质假设,包括但不限于铜回收率将如假设的那样;金属价格将保持恒定;有关Campo Morado矿山的当前勘探、开发、环境和其他目标能够实现;改善Campo Morado矿山开采操作的计划将按计划进行;黄金及其他金属价格的持续、经济和政治条件以及业务的价格连续性。前瞻性信息涉及已知和未知的风险、不确定因素和其他可能导致公司实际结果、业绩或成就与前瞻性信息所表达或暗示的任何未来结果、业绩或成就大不相同的因素。不能保证前瞻性信息将被证实准确,因为实际结果和未来事件可能与此类声明中预期的结果大不相同。因此,读者不应过于依赖前瞻性信息。除法律要求外,公司不承担任何义务公开发布本新闻稿中包含的前瞻性信息的修订,以反映本日期后发生的事件或情况,或反映未经预料的事件的发生。
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
TSX tsx Venture交易所及其监管服务提供商(如TSX Venture交易所的政策中所定义的那样)不承担此发布的充分性或准确性的责任。
SOURCE Luca Mining Corp.