Minera Alamos Provides Sabre Gold Acquisition and Operations Update
Minera Alamos Provides Sabre Gold Acquisition and Operations Update
Santana Phase 2 Pad Expansion Preparations Underway
桑塔纳二期停机坪扩建准备工作正在进行中
Toronto, Ontario--(Newsfile Corp. - November 18, 2024) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide an interim corporate update to follow its recent announcement (see news release of October 28th, 2024) of the acquisition of Sabre Gold ("Sabre") and its flagship Copperstone gold project in Arizona.
安大略省多伦多--(Newsfile Corp.,2024年11月18日)——Minera Alamos Inc.(多伦多证券交易所股票代码:MAI)(“公司” 或 “Minera Alamos”)很高兴提供临时公司最新情况,以继其最近宣布(见2024年10月28日新闻稿)收购亚利桑那州的Sabre Gold(“Sabre”)及其旗舰铜石黄金项目之后。
Copperstone Gold Project Developments
Copperstone 黄金项目开发
Following the recent Sabre Gold acquisition announcement, the Company and Sabre are moving quickly to finalize the transaction, with the Sabre shareholder meeting now set for January 14th, 2025, in parallel with the initiation of project development activities. To date, this includes:
继最近宣布收购Sabre Gold之后,该公司和Sabre正在迅速采取行动完成交易,Sabre股东大会现定于2025年1月14日举行,同时启动项目开发活动。迄今为止,这包括:
- On November 11th, Sabre announced the repurchase of a 1.5% existing net smelter royalty ("NSR") on the Copperstone project in exchange for a non-core 0.5% NSR right held by the company on the 3 Aces project being explored by Seabridge Gold Inc. The completion of the transfer further reduces the historical royalty levels attached to the Copperstone project.
- The Company is preparing updated process models and flowsheets for the construction of the new Copperstone processing facility. This work is expected to be completed before year-end.
- Underground development plans are being reworked and are expected to reduce some of the reliance on higher operating cost mining methods while providing improved operational flexibility in order to more effectively maintain mining rates as envisioned in the 2023 Preliminary Economic Assessment ("PEA") for the project.
- Work is underway to finalize the preparation of the Company's existing grinding and flotation equipment for shipment to Copperstone, so it is available at site early in 2025 in advance of the start of the process plant construction.
- 11月11日,Sabre宣布回购Copperstone项目1.5%的现有净冶炼厂特许权使用费(“NSR”),以换取该公司在Seabridge Gold Inc正在勘探的3 Aces项目中持有的0.5%的非核心NSR权利。转让的完成进一步降低了与Copperstone项目相关的历史特许权使用费水平。
- 该公司正在为建造新的Copperstone加工设施准备更新的工艺模型和流程表。这项工作预计将在年底前完成。
- 地下开发计划正在重新制定中,预计将减少对较高运营成本采矿方法的依赖,同时提高运营灵活性,从而更有效地维持该项目2023年初步经济评估(“PEA”)中设想的采矿率。
- 目前正在完成公司现有研磨和浮选设备的准备工作,以便运往Copperstone,因此该设备将在加工厂建设开始之前于2025年初在现场投入使用。
In the coming months the Company will be able to more fully quantify the positive impact various current Minera initiatives will have on the overall Copperstone project economics as compared to those summarized in the 2023 PEA completed by Sabre.
在接下来的几个月中,与Sabre完成的2023年PEA中总结的相比,公司将能够更全面地量化当前各种Minera计划对Copperstone项目整体经济的积极影响。
Santana Operations
桑塔纳运营
Mining and stacking operations during the first full quarter (Q3-2024) of production from the new Nicho Main Zone pit reached 3,800 ounces of gold which is in line with Company forecasts for the period, an amount that surpasses the total ounces mined and stacked for the entirety of 2023. As the new Nicho Main pit is expanded in surface area, access for mining operations continues to improve and two additional trucks were added to the mining fleet as anticipated.
在第一个完整季度(Q3-2024)中,新的Nicho Main Zone矿的采矿和堆放业务的黄金产量达到3,800盎司,这与公司对该期间的预测一致,这一数量超过了2023年全年开采和堆放的总盎司。随着新的Nicho Main矿地表面积的扩大,采矿作业的通道不断改善,并且如预期的那样,采矿车队中又增加了两辆卡车。
- Gold grades of the mineralized material mined in the quarter averaged approximately 0.6 g/t with a strip ratio of 1.84:1 (waste to mineralized material). Average grades remain reasonably in line with those predicted from the current resource model.
- The Company is completing final preparations for the Phase 2 leach pad expansion at Santana which will increase the area available for site leaching operations by 40%. This leach pad expansion will allow for more efficient leaching activities as the ramp up of mining operations continues into 2025 with a better separation of the active leaching areas from newly mined material. The larger Phase 3 pad expansion is awaiting Permit Amendment approval that will allow the Company to execute on the larger future planned expansion of activities at Santana.
- A local contractor group has been selected to perform rehabilitation work on the Company's previously acquired crushing and transfer equipment. Final detailed engineering work is underway to install this equipment adjacent to the current leach pad facilities in order to improve the preparation and handling of mineralized material to be stacked on the expanded leach pad areas.
- Following a return to more active mine operations, the Company has embarked on a number of community projects including road maintenance and upgrade activities.
- 该季度开采的矿化材料的黄金品位平均约为0.6 g/t,带材比为1. 84:1(废物与矿化材料)。平均成绩与当前资源模型预测的水平保持合理一致。
- 该公司正在完成桑塔纳第二阶段浸出场扩建的最后准备工作,这将使现场浸出作业的可用面积增加40%。随着采矿业务的扩大将持续到2025年,活性浸出区与新开采的材料更好地分离,渗滤区的扩建将允许更高效的浸出活动。较大的第三阶段停机坪扩建项目正在等待许可证修正案的批准,这将使公司能够执行桑塔纳未来计划的大规模扩建活动。
- 已选定一个当地承包商集团对该公司先前收购的破碎和输送设备进行修复工作。最后的详细工程工作正在进行中,将该设备安装在当前的渗滤垫设施附近,以改善堆叠在扩大的渗滤垫区域的矿化材料的制备和处理。
- 在恢复更加活跃的采矿业务之后,该公司已启动了许多社区项目,包括道路维护和升级活动。
Cerro de Oro Project Developments
Cerro de Oro 项目开发
Engineering work continues for the Cerro de Oro project in advance of final permit receipt.
在收到最终许可证之前,Cerro de Oro项目的工程工作仍在继续。
- Detailed engineering focused on the long-lead areas of the new site infrastructure facilities as required for the issuance of proposal requests related to these work/equipment items.
- Discussions are ongoing with potential contractors suitable for the rehabilitation of existing equipment (crushing/screening) to be utilized at Cerro de Oro
- Continued technical correspondence with the relevant authorities as the permit review continues to advance.
- 详细工程侧重于发布与这些工作/设备项目相关的提案请求所需的新场地基础设施的长距离区域。
- 目前正在与适合修复将在塞罗德奥罗使用的现有设备(压碎/筛分)的潜在承包商进行讨论
- 随着许可证审查的继续推进,继续与有关当局进行技术通信。
Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the technical content of this press release under National Instrument 43-101.
Minera Alamos首席执行官达伦·科宁根先生是负责National Instrument 43-101下本新闻稿技术内容的合格人员。
Cautionary Statement
警示声明
The Company made its production decision at the Santana gold mine without having completed a feasibility study demonstrating economic and technical viability. As such, there may be increased uncertainty of achieving planned production levels, estimated recovery of gold, the costs associated with such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.
该公司在没有完成证明经济和技术可行性的可行性研究的情况下做出了桑塔纳金矿的生产决定。因此,实现计划产量水平、预计的黄金回收率、与这种回收相关的成本,包括与开发商业可开采矿床相关的风险增加的不确定性可能会增加。从历史上看,此类项目发生经济和技术故障的风险要高得多。
For Further Information Please Contact:
欲了解更多信息,请联系:
Minera Alamos
阿拉莫斯矿工
Doug Ramshaw, President
Tel: 604-600-4423
Email: dramshaw@mineraalamos.com
道格·拉姆肖,总裁
电话:604-600-4423
电子邮件:dramshaw@mineraalamos.com
Victoria Vargas de Szarzynski, VP Investor Relations
Tel: 289-242-3599
Email: vvargas@mineraalamos.com
维多利亚·瓦尔加斯·德·萨钦斯基,投资者关系副总裁
电话:289-242-3599
电子邮件:vvargas@mineraalamos.com
Website:
网站:
About Minera Alamos Inc.
关于 Minera Alamos Inc.
Minera Alamos is a gold production and development Company. The Company has a portfolio of high-quality Mexican assets, including the 100%-owned Santana open-pit, heap-leach mine in Sonora that is currently going through the start-up of operations at the new Nicho Main deposit. The 100%-owned Cerro de Oro oxide gold project in northern Zacatecas has considerable past drilling and metallurgical work completed and the proposed mining project is currently being guided through the permitting process by the Company's permitting consultants. The La Fortuna open pit gold project in Durango (100%-owned) has a positive, robust preliminary economic assessment (PEA) completed, and the main Federal permits are in place. Minera Alamos is built around its operating team that together brought three open pit heap leach gold mines into successful production in Mexico over the last 13 years.
阿拉莫斯矿业公司是一家黄金生产和开发公司。该公司拥有大量高质量的墨西哥资产,包括位于索诺拉州的桑塔纳露天堆浸矿,该矿目前正在新的Nicho Main矿床启动运营。位于萨卡特卡斯州北部的Cerro de Oro氧化金项目过去已经完成了大量的钻探和冶金工作,拟议的采矿项目目前正在公司的许可顾问的指导下完成许可程序。杜兰戈的La Fortuna露天黄金项目(100% 持股)已经完成了积极、稳健的初步经济评估(PEA),主要的联邦许可证已经到位。Minera Alamos是围绕其运营团队建立的,在过去的13年中,该团队共同使墨西哥的三个露天堆浸金矿成功生产。
The Company's strategy is to develop very low capex assets while expanding the projects' resources and continuing to pursue complementary strategic acquisitions.
该公司的战略是开发非常低的资本支出资产,同时扩大项目资源并继续进行补充性战略收购。
Caution Regarding Forward-Looking Statements
关于前瞻性陈述的注意事项
This news release may contain forward-looking information and Minera Alamos cautions readers that forward-looking information is based on certain assumptions and risk factors that could cause actual results to differ materially from the expectations of Minera Alamos included in this news release. This news release includes certain "forward-looking statements", which often, but not always, can be identified by the use of words such as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". These statements are based on information currently available to Minera Alamos and Minera Alamos provides no assurance that actual results will meet management's expectations. Forward-looking statements include timing, cost estimates and statements with respect to Minera Alamos' future plans, objectives and goals with respect to the Cerro de Oro gold mine including the receipt of permits and construction timeline, and the satisfaction by the Company of the closing conditions to draw the Remaining Amount. Since forward-looking statements are based on assumptions and address future events and conditions that, by their very nature involve inherent risks and uncertainties. Actual results relating to, among other things, results of exploration, the economics of processing methods, project development, reclamation and capital costs of Minera Alamos' mineral properties, the ability to complete a preliminary economic assessment which supports the technical and economic viability of mineral production could differ materially from those currently anticipated in such statements for many reasons. Minera Alamos' financial condition and prospects could differ materially from those currently anticipated in such statements for many reasons such as: an inability to finance and/or complete an updated resource and reserve estimate and a preliminary economic assessment which supports the technical and economic viability of mineral production; changes in general economic conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation, legislative, environmental and other judicial, regulatory, political and competitive developments; technological and operational difficulties encountered in connection with Minera Alamos' activities; and other matters discussed in this news release and in filings made with securities regulators. This list is not exhaustive of the factors that may affect any of Minera Alamos' forward-looking statements. These and other factors should be considered carefully, and readers should not place undue reliance on Minera Alamos' forward-looking statements. Minera Alamos does not undertake to update any forward-looking statement that may be made from time to time by Minera Alamos or on its behalf, except in accordance with applicable securities laws.
本新闻稿可能包含前瞻性信息,Minera Alamos提醒读者,前瞻性信息基于某些假设和风险因素,这些假设和风险因素可能导致实际业绩与本新闻稿中对Minera Alamos的预期存在重大差异。本新闻稿包括某些 “前瞻性陈述”,这些陈述通常但并非总是可以通过使用 “相信”、“预期”、“期望”、“估计”、“可能”、“可能”、“将”、“将” 或 “计划” 等词语来识别。这些声明基于Minera Alamos目前获得的信息,Minera Alamos并不能保证实际业绩将符合管理层的预期。前瞻性陈述包括时机、成本估算和与Minera Alamos有关Cerro de Oro金矿的未来计划、目的和目标的陈述,包括许可证的获得和施工时间表,以及公司对提取剩余金额的成交条件的满意程度。由于前瞻性陈述基于假设,涉及未来的事件和状况,这些事件和条件本质上涉及固有的风险和不确定性。与勘探结果、加工方法的经济学、阿拉莫斯矿产地产的项目开发、开垦和资本成本以及完成支持矿物生产技术和经济可行性的初步经济评估的能力等相关的实际结果可能与此类声明中目前的预期存在重大差异,原因有很多。Minera Alamos的财务状况和前景可能与此类报表中目前的预期存在重大差异,原因有很多,例如:无法融资和/或完成最新的资源和储量估算以及支持矿产生产技术和经济可行性的初步经济评估;总体经济状况和金融市场状况的变化;矿产需求和价格的变化;诉讼、立法、环境和其他司法、监管、政治和竞争情况事态发展;与Minera Alamos的活动相关的技术和运营困难;以及本新闻稿和向证券监管机构提交的文件中讨论的其他事项。该清单并未详尽列出可能影响Minera Alamos任何前瞻性陈述的因素。应仔细考虑这些因素和其他因素,读者不应过分依赖Minera Alamos的前瞻性陈述。除非根据适用的证券法,否则Minera Alamos不承诺更新Minera Alamos或代表其不时发表的任何前瞻性陈述。
The Company does not have a feasibility study of mineral reserves, demonstrating economic and technical viability for the Santana project, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.
该公司没有矿产储量可行性研究,这表明桑塔纳项目的经济和技术可行性,因此,实现任何特定矿产回收水平或回收成本的不确定性可能会增加,包括与开发商业可开采矿床相关的风险增加。从历史上看,此类项目发生经济和技术故障的风险要高得多。
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
多伦多证券交易所及其监管服务提供商(该术语在多伦多证券交易所风险投资交易所的政策中定义)均不对本新闻稿的充分性或准确性承担责任。