Greater Houston Resiliency Initiative Progress Update: CenterPoint Energy Makes Significant Advances on Critical Resiliency Actions
Greater Houston Resiliency Initiative Progress Update: CenterPoint Energy Makes Significant Advances on Critical Resiliency Actions
Company has installed or replaced nearly 4,600 stronger storm-resilient poles; cleared more than 800 miles of higher-risk vegetation; undergrounded more than 100 miles of power lines; and installed dozens of new, intelligent grid switching devices
公司已安装或更换了近4600个更坚固的抗风桩;清理了超过800英里高风险植被;地下化了超过100英里的输电线路;并安装了几十个新的智能电网开关设备
HOUSTON, Nov. 19, 2024 /PRNewswire/ -- CenterPoint Energy today released the first of its public progress updates on the actions being taken throughout the Greater Houston 12-county area as part of Phase Two of its Greater Houston Resiliency Initiative (GHRI). In the first two months of the program, and in preparation for the 2025 hurricane season, CenterPoint has installed nearly 4,600 storm-resilient poles designed to better withstand extreme winds; installed more than 100 miles of power lines underground to reduce the impact of extreme weather; cleared more than 800 miles of hazardous vegetation to improve reliability; and installed more self-healing automation devices to help improve overall restoration times. CenterPoint is taking all of these actions and enhancements as part of the company's goal of building the most resilient coastal grid in the nation.
"This summer, we accomplished a significant level of increased system hardening in the first phase of the Greater Houston Resilience Initiative. Since then, as we have been fully engaged in delivering the additional set of actions in our second phase of GHRI, we continue to make significant progress as we work toward our ultimate goal of becoming the most resilient coastal grid in the country. Now, and in the months to come, we will remain laser-focused on completing these critical resiliency actions and building the more reliable and more resilient energy system our customers expect and deserve," said Darin Carroll, CenterPoint Energy Senior Vice President of CenterPoint Energy's Electric Business.
GHRI Phase Two: Progress Update
CenterPoint announced on September 30 the launch of Phase Two of the GHRI, which included a series of actions to strengthen resiliency, enable a self-healing grid and reduce the duration and impact of power outages. Through early November, significant progress has been made across its service area, including:
休斯敦,2024年11月19日/美通社/ - 中点能源今天发布了其大休斯敦12县地区的“大休斯敦弹性计划”(GHRI)第二阶段行动的最新公共进展。在该计划的最初两个月内,为备战2025年飓风季节,中点能源已安装了近4600个设计更能抵御极端风的抗风桩;将超过100英里的输电线路埋入地下,以减少极端天气的影响;清理了超过800英里的危险植被以提高可靠性;并安装了更多的自愈自动化设备,帮助改善整体恢复时间。中点能源正在采取所有这些行动和增强措施,作为公司建设全国最具弹性沿海电网的目标的一部分
“今年夏天,我们在大休斯敦弹性计划的第一阶段中取得了显著的系统加固水平。自那时以来,随着我们全力以赴地开展在GHRI第二阶段的额外行动集,我们在朝着成为全国最具弹性沿海电网的最终目标取得了显著的进展。现在以及未来几个月,我们将继续专注于完成这些关键的弹性行动,建设更可靠、更具弹性的能源系统,这是我们的客户期望和应得的。”中点能源的中点能源电业务高级副总裁达林·卡萝说
GHRI第二阶段:进展更新
中点于9月30日宣布了GHRI第二阶段的启动,其中包括一系列加强弹性、实现自愈电网并减少停电持续时间和影响力的行动。截至11月初,在整个服务区域已取得了重大进展,包括: