TeraWulf Stock Is Trading Higher Today: What's Going On?

TeraWulf Stock Is Trading Higher Today: What's Going On?

TeraWulf股票今天交易上涨:发生了什么?
Benzinga ·  12/04 23:36

TeraWulf Inc (NASDAQ:WULF) shares are trading higher Wednesday. The company announced a production and operations update for November. Here's what you need to know.

TeraWulf公司(纳斯达克:WULF)股价周三上涨。该公司宣布了11月的生产和运营更新。以下是您需要了解的内容。

What To Know: TeraWulf said it mined 115 Bitcoin (CRYPTO: BTC) in November, with an average daily production rate of approximately 3.8 bitcoin. The company said it achieved an average power cost of $41,190 per bitcoin mined.

要点:TeraWulf表示,11月挖掘了115比特币(加密货币:BTC),平均每日产量约为3.8比特币。该公司称,其挖掘的比特币的平均成本为每枚41,190美元。

TeraWulf maintained 8.4 EH/s of operational self-mining capacity during the month, up 68% year-over-year. The company noted that November's average hash rate was 5.9 EH/s due to planned outages for electrical upgrades.

TeraWulf在该月保持了8.4 EH/s的自有挖矿能力,同比增长68%。该公司指出,由于计划的电力升级停机,11月的平均哈希率为5.9 EH/s。

"November marked a pivotal month for Lake Mariner as we completed significant upgrades to our electrical infrastructure. These enhancements will ensure reliable and redundant power delivery to CB-1, CB-2, and future HPC hosting loads, positioning us to meet the increasing demand for Tier 3 HPC infrastructure," said Sean Farrell, COO of TeraWulf.

“11月对Lake Mariner来说是一个关键月份,因为我们完成了对电力基础设施的重大升级。这些增强措施将确保Cb-1、Cb-2和未来的HPC托管负载可靠且冗余的电力传输,使我们具备满足Tier 3 HPC基础设施不断增长需求的能力,”TeraWulf的首席运营官肖恩·法瑞尔(Sean Farrell)表示。

TeraWulf's operational bitcoin mining capacity was 195 MW at the Lake Mariner facility as of Nov. 30. The company's self-mining hash rate is expected to reach approximately 9.7 EH/s upon completion of miner repairs and fleet upgrades.

截至11月30日,TeraWulf在Lake Mariner设施的运营比特币挖矿能力为195兆瓦。预计该公司的自有挖矿哈希率在矿工维修和舰队升级完成后将达到约9.7 EH/s。

TeraWulf also said it continues to make progress on its large-scale HPC hosting initiative. Dry cooler installation is now complete for the 20 MW CB-1 facility, which is on track for completion in the first quarter of 2025. The company said it remains on track to deliver 72.5 MW of HPC hosting capacity by the end of the second quarter of 2025.

TeraWulf还表示,其大型HPC托管计划正在持续取得进展。20兆瓦的Cb-1设施现已完成干式冷却器安装,并计划于2025年第一季度完成。该公司表示,将在2025年第二季度末前按计划交付72.5兆瓦的HPC托管容量。

"Additionally, our onsite repair teams are on track to restore 1.3 EH/s of mining equipment under warranty by year-end. Construction of MB-5 is proceeding on schedule, with conduit installation complete and foundation pours and structural steel assembly underway," Farrell said.

“此外,我们的现场维修团队计划在年底前恢复1.3 EH/s的设备保修内的挖矿设备。Mb-5的施工按计划进行,导管已安装完毕,基础浇筑和结构钢组装正在进行中,”法瑞尔表示。

WULF Price Action: TeraWulf shares were up 3.23% at $7.47 at the time of publication, according to Benzinga Pro.

WULF股价表现:根据Benzinga Pro的数据,TeraWulf股价涨幅为3.23%,报7.47美元。