Bunker Hill Announces Updated Forecast for Mine Restart and Revised Financing Plan
Bunker Hill Announces Updated Forecast for Mine Restart and Revised Financing Plan
KELLOGG, Idaho and VANCOUVER, British Columbia , Dec. 13, 2024 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. ("Bunker Hill" or the "Company") (TSXV:BNKR |OTCQX:BHLL) announces that the Bunker Hill Mine restart project, which is approximately 64% complete with 98% of procurement completed, has undergone a strategic review resulting in an updated timeline and capital requirements.
爱达荷州基洛格和不列颠哥伦比亚省温哥华,2024年12月13日(环球新闻)— Bunker Hill Mining Corp.(“Bunker Hill”或“公司”)(TSXV:BNKR |OTCQX:BHLL)宣布,Bunker Hill矿重新启动项目已完成约64%,采购完成率为98%,经过战略审查,更新了时间表和资本需求。
Pursuant to this review, the Company now forecasts a total restart expenditure (excluding working capital) of $103 million, up from the previously forecasted $67 million and the $56 million in the 2022 Pre-Feasibility Study (the "PFS"), with the restart project anticipated to be delayed by up to four months. To provide sufficient project finance for the ongoing development of the Bunker Hill Mine, the Company intends to draw down on the $21 million standby facility (the "Standby Facility") provided by Sprott Private Resource Streaming and Royalty Corp. and finalize the ongoing discussions with its strategic partners for potential offtake or similar financing for an additional $30 million.
根据这项审查,公司现在预测总的重启支出(不包括流动资金)为$10300万,较之前预测的$6700万和2022年可行性研究(“PFS”)中的$5600万有所上升,预计重启项目将延迟最多四个月。为了为Bunker Hill矿的持续开发提供足够的项目融资,公司打算提取Sprott私人资源流媒体和特许权使用费公司的$2100万备用资金(“备用资金”),并最终确定与其战略合作伙伴的正在进行的讨论,以寻求额外$3000万的预购或类似融资。
Sam Ash, President and CEO, commented: "This revised plan takes full account of the many challenges facing the project and the rest of the US mining industry. Work onsite continues round the clock at the highest intensity possible to complete mechanical installation and commissioning and deliver the demanding restart plan. The adjustment we're announcing reflects the outcome of weeks of intense work by the small Bunker team, Gypsy LLC, our procurement, construction, and management contractor and their many supporters to counter the worst effects of inflation, scope changes since the PFS, and an unplanned contractor change. We are pleased to be able to draw upon the Standby Facility and conclude offtake and associated financing discussions to ensure that profitable and sustainable operations may commence by the revised start date of Q2 2025. We wish to thank our partners at Sprott Private Resource Streaming and Royalty Corp. and our many skilled contractors working on this critical US project for their steadfast and enduring support."
公司总裁兼首席执行官Sam Ash评论道:“这个修订计划充分考虑了项目以及美国矿业行业面临的众多挑战。现场工作正在以尽可能高的强度进行,努力完成机械安装和调试,以实施严格的重启计划。我们正在宣布的调整反映了Bunker小团队、Gypsy LLC、我们的采购、施工和管理承包商及其众多支持者经过数周深入工作的结果,以应对通货膨胀的最坏影响、自PFS以来的范围变化以及计划外的承包商更换。我们很高兴能够依靠备用资金的支持,完成预购和相关融资的讨论,以确保在修订后的2025年第二季度开始日期前能够启动盈利和可持续的运营。我们感谢Sprott私人资源流媒体和特许权使用费公司的合作伙伴以及为这个关键美国项目工作的许多熟练承包商的坚定和持久支持。”
STRATEGIC REVIEW – ACTIVITY AND CONCLUSIONS
战略审查 – 活动与结论
Over the past eight weeks, the Company has reviewed the impact of the following key factors on the restart plan, seeking ways to mitigate them and incorporate them within the revised forecast:
在过去的八周里,公司审查了以下关键因素对重启计划的影响,寻求减轻这些影响并纳入修订后的预测中:
-
Input Cost Inflation—As widely reported across the US Mining Industry, the cost of skilled construction labor (specifically electricians) has increased by 53% over the last 12 months, from an average of $75/hour to $114/hour. The cost of structural steel has also increased by 40%, copper (a proxy for electrical fittings) by 40%, and concrete by 20%. These are extraordinary numbers that deeply impact every aspect of the project.
With labor being the primary input cost in the project's mechanical installation and commissioning phases, this has been the most challenging to mitigate. Efforts have been made to bring some of this work in-house, but these have not significantly impacted total cost projections, particularly given the impact of steel, concrete, electrical and other inflation (as crystallized in the recent and final procurement orders).
- 输入成本通胀——正如美国采矿行业广泛报道的那样,熟练施工劳动力(特别是电工)的成本在过去12个月中增加了53%,从平均每小时75美元上涨到114美元。结构钢的成本也增加了40%,铜(电气配件的代表)增加了40%,混凝土增加了20%。这些都是深刻影响项目各个方面的非凡数字。
由于劳动力是项目机械安装和调试阶段的主要输入成本,因此这是最难以减轻的方面。尽管已努力将部分工作内包,但这些努力对总成本预测的影响并不显著,尤其是考虑到钢材、混凝土、电气及其他通胀的影响(如近期和最终的采购订单中所体现)。
-
Filter Press Scope Change - As reported in the news release dated May 21, 2024 the Company chose to change the Tailings Management System envisaged in the 2022 PFS and starting budget, in order to improve long-term efficiency and sustainability, following tailings filtration testing. The more effective and expensive filter press (as compared to the $5 million disk filter system described in the 2022 PFS) passed the 90% engineering milestone in October 2024. This final design and associated inflation-effected procurement through November resulted in the final cost forecast increase from $10 million to $18 million.
-
Specialist Contractor Walk-Out - In August 2024, the specialist contractor conducting the auger-cast deep piers for the tailings filter press demobilized unexpectedly to pursue other work in North America. Given the tight market for this specialty construction work, securing and mobilizing a replacement contractor for this deep pier construction onto the mine site was challenging passing on delays to the construction timeline.
To mitigate this unexpected schedule delay, the Company conducted an engineering study to consider the deferral of the construction of the Tailings Filter Press into 2026, with tailings instead being pumped directly from the Kellogg Yard to the paste plant in the Wardner operating base and into voids underground at start-up. After conducting trade-off analysis, it was determined that this phased solution was not workable and that it would be more prudent to continue the complete construction as planned, albeit on a delayed timeline. It was judged to be far better to have the optimal system at restart geared to serving the 1,800 tons per day plan, than a potentially risky work-around that would put initial cash flow at risk.
- 滤压机范围变更 - 如2024年5月21日的新闻发布中所报道,公司选择更改2022年PFS中构想的尾矿管理系统和起始预算,以在尾矿过滤测试后提高长期效率和可持续性。与2022年PFS中描述的500万Disk滤网系统相比,更有效且成本更高的滤压机于2024年10月通过了90%的工程里程碑。最终设计及受通胀影响的采购在11月的最终成本预测从1000万上涨至1800万。
- 专业承包商撤离 - 在2024年8月,为尾矿过滤机进行螺旋钻深柱施工的专业承包商意外撤离,前往北美寻求其他工作。由于这一专业施工工作的市场紧张,找到并动员一个替代承包商进入矿区进行深柱施工相当具有挑战性,这导致了施工时间表的延误。
为了缓解这一意外的时间表延误,公司进行了工程研究,考虑将尾矿过滤机的施工推迟到2026年,而尾矿则直接从凯洛格院输送至沃德纳运营基地的浆料厂,并在启动时填充地下空洞。经过权衡分析,确定这一阶段性解决方案不可行,继续按计划完成整体施工更为明智,尽管时间表有所延迟。被认为比一个可能存在风险的替代方案更好的是,在重启时拥有一个能够服务于每天1,800吨计划的最佳系统,而不是一个可能危及初始现金流量的暂时解决方案。
Taking account of these key factors and any mitigating actions, the review determined that the project restart would be delayed until at least Q2 2025 and that the total project expenditure (including working capital) is expected to increase by approximately $50 million.
考虑到这些关键因素和任何减轻措施,审查确定项目重启将至少推迟到2025年第二季度,预计总项目支出(包括营运资金)将增加约5000万美元。
RESTART PLAN UPDATE
重启计划更新
Processing Plant - 66% complete. The mechanical installation of the final elements of the processing plant is continuing, with the phased commissioning of the circuit starting by the end of December 2024 following the plant's connection to the grid power via the Bunker Hill transformer. The external conveyor network is being installed connecting the crusher, ore silo, plant and concentrate load-out facility. Inside the main building piping, pumps, electrical infrastructure and working mezzanine platforms are installed in stages.
处理厂 - 完成66%。处理厂最后元素的机械安装正在继续,电路的分阶段调试将在2024年12月底前开始,届时工厂将通过班克希尔变压器与电网电力连接。外部输送系统正在安装中,连接破碎机、矿石筒仓、工厂和精矿装卸设施。主建筑内部管道、泵、电气基础设施和工作夹层平台也在分阶段安装中。
Figure 1: Conveyor installation
图1:传送带安装
Figure 2: Mezzanine floor and equipment installation
图2: mezzanine 楼层和设备安装
Tailings Filter Press - 38% Complete. The concrete foundations for the tailings filter press are laid in stages upon the deep piers. This is concurrent with the construction of the tailings storage tank and associated infrastructure and off-site, the final construction of the various components of the facility.
尾矿压滤机 - 完成38%。尾矿压滤机的混凝土基础按照深桩分阶段铺设。这与尾矿储罐及其相关基础设施的施工并行,同时,在场外,设施中各个元件的最终施工也在进行中。
Figure 3: Rendering of the final tailings filter press design
图3:最终尾矿压滤机设计效果图
Figure 4: Tailings storage tank construction (December 2024)
图4:尾矿储存罐施工(2024年12月)
Underground - 80% Complete. Conducted from the Wardner Operating Facility, the underground development continues to be on track and budget. Access to five mining stopes has already been prepared in the underground area of the mine. These are ready to be mined now. Refurbishment of the access ramp to level 8 mining areas is 75% complete. Work is currently focused on improving the ramp's geotechnical strength as it cuts through the Cate Fault; and thereby enable longer life mining than that envisaged in the 2022 PFS. Stockpiling of ore underground during the ramp refurbishment will commence by the end of 2024.
地下 - 完成80%。从Wardner运营设施进行,地下开发仍然按计划和预算进行。矿井的地下区域已经准备好了五个采矿停放点。这些停放点现已准备好开采。通往8级采矿区域的坡道翻新已完成75%。当前工作的重点是提高坡道的岩土强度,因为它穿过凯特断层;从而实现比2022年PFS中设想的更长的开采寿命。在坡道翻新的过程中,将于2024年底开始对地下矿石进行堆存。
Figure 5: Steel Sets supporting ramp through Cate Fault
图5:支持穿过凯特断层的坡道的钢铁支架
Mine Planning - This revised forecast incorporates the Company's optimization efforts conducted over the prior months to ensure the most sustainable and profitable restart operation possible while mitigating the impact of cost increases. The plan update includes an adjusted mine plan to maximize cash flows from year one.
矿山规划 - 此次修订的预测包含了公司在前几个月所开展的优化工作,旨在确保尽可能可持续和盈利的重启操作,同时减轻成本增加的影响。计划更新包括调整的矿山计划,以最大化第一年的现金流。
Resource and Reserve Expansion - This revised forecast incorporates more drilling and technical work into the plan. Specifically, it incorporates the identified silver targets in the upper part of the mine into the early mine plan and technical studies for Bunker 2.0: the move to 2,500 tons per day. The Company is processing the data gathered from the 2024 drilling campaign and intends to issue a Resource and Reserve update as planned in Q1 2025, as well as provide periodic updates on these results over the next few weeks.
资源和储备扩展 - 此修订预测将更多的钻探和技术工作纳入计划中。具体来说,它将矿山上部识别出的白银目标纳入早期矿山计划和Bunker 2.0的技术研究:向每日2,500吨的转变。公司正在处理2024年钻探活动中收集的数据,并打算在2025年第一季度按照计划发布资源和储备更新,并在接下来的几周内提供这些结果的定期更新。
FINANCING PLAN
融资计划
The Company intends to commence drawing in tranches upon the Standby Facility provided from December 12, 2024. The first tranche will provide $5 million in working capital. The ongoing negotiations with various financing partners to secure a $30 million financing package are expected to be concluded by the end of January 2025.
公司计划于2024年12月12日起开始分期提款,使用待命融资额度。第一期将提供500万美元的营运资金。与各融资合作伙伴的持续谈判旨在确保3000万美元的融资方案,预计将于2025年1月底前完成。
Concurrent with this, the Company will continue to advance the process required to unlock the $150 million facility from US EXIM by the end of 2025 which the Company would utilize to refinance the existing debt and increase the mine's expected production capacity to 2,500 tons per day.
与此同时,公司将继续推进解锁15000万美元美国进出口银行额度的进程,预计在2025年底之前使用该额度进行现有债务的再融资,并将矿山的预期生产能力提高到每日2,500吨。
Even with the Company's plans to secure the necessary financing for the project restart pursuant to the updated forecast, there is no certainty that the Company will be able to raise the funds required to complete the necessary development work needed to restart operations and advance the ongoing mine plan adjustments. While the Company anticipates operations to commence in the second quarter of 2025, there is no certainty that this will be the case.
尽管公司计划根据更新的预测为项目重启获取必要的融资,但仍无法确保公司能够筹集到完成重启操作和推进正在进行的矿山计划调整所需的资金。虽然公司预计将在2025年第二季度开始运营,但对此并没有确定性。
CORPORATE UPDATE WEBINAR
公司更新网络研讨会
The Company will host a webinar on Friday, December 13, 2024 at 9:00am PST/12:00pm EST featuring a presentation from Bunker Hill's President and CEO Sam Ash, Executive Chairman Richard Williams and CFO Gerbrand Van Heerden. A recording of the webinar will be available on the Company's website.
公司将于2024年12月13日(星期五)上午9:00 PST/下午12:00 EST举办网络研讨会,届时将有Bunker Hill的总裁兼首席执行官Sam Ash、执行董事会主席Richard Williams和首席财务官Gerbrand Van Heerden的演讲。该网络研讨会的录音将在公司网站上提供。
Attendees can register for the webinar using the following link:
与会者可以使用以下链接注册网络研讨会:
ABOUT BUNKER HILL MINING CORP.
BUNKER HILL MINING CORP.简介
Under Idaho-based leadership, Bunker Hill intends to sustainably restart and develop the Bunker Hill Mine as the first step in consolidating and then optimizing a number of mining assets into a high-value portfolio of operations, centered initially in North America. Information about the Company is available on its website, www.bunkerhillmining.com, or within the SEDAR+ and EDGAR databases.
在爱达荷州领导下,Bunker Hill 打算可持续地重启和开发 Bunker Hill 矿山,作为整合和优化多个矿产资产为高价值运营组合的第一步,最初集中在北美。关于公司的信息可以在其网站 www.bunkerhillmining.com 或 SEDAR+ 和 EDGAR 数据库中找到。
On behalf of the Board of Directors of Bunker Hill Mining Corp.
代表 Bunker Hill Mining Corp. 董事会。
Sam Ash
President and Chief Executive Officer
山姆·阿什
总裁兼首席执行官
For additional information, please contact:
如需更多信息,请联系:
Brenda Dayton
Vice President, Investor Relations
T: 604.417.7952
E: brenda.dayton@bunkerhillmining.com
布伦达·戴顿
副总裁,投资者关系
电话: 604.417.7952
邮箱: brenda.dayton@bunkerhillmining.com
Cautionary Statements
警示声明
Neither the TSX Venture Exchange (the "TSX-V") nor its Regulation Services Provider (as that term is defined in the policies of the TSX-V) accepts responsibility for the adequacy or accuracy of this news release.
无论是TSX创业公司交易所("TSX-V")还是其监管服务提供商(此术语在TSX-V的政策中有定义),均不对本资讯发布的充分性或准确性承担责任。
Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such forward-looking statements are within the meaning of that term in Section 27A of the Securities Act and Section 21E of the U.S. Securities Exchange Act of 1934, as amended, as well as within the meaning of the phrase 'forward-looking information' in the Canadian Securities Administrators' National Instrument 51-102 – Continuous Disclosure Obligations (collectively, "forward-looking statements"). Forward-looking statements are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", "plan" or variations of such words and phrases.
本资讯发布中的某些陈述具有前瞻性,并涉及多个风险和不确定性。这些前瞻性陈述属于《证券法》第27A条和《1934年美国证券交易法》第21E条中该术语的含义,以及加拿大全国证券管理局《国家仪器51-102-持续披露义务》中“前瞻性信息”一词的含义(统称为"前瞻性陈述")。前瞻性陈述不由历史事实构成。前瞻性陈述包括估计和描述公司未来计划、目标或目标的声明,包括表明公司或管理层预计某一条件或结果将发生的词语。前瞻性陈述可通过诸如“相信”、“预期”、“预计”、“估计”、“可能”、“可以”、“将”、“计划”或此类词语和短语的变体来识别。
Forward-looking statements in this news release include, but are not limited to, statements regarding: the Company's objectives, goals or future plans, including the restart and development of the Bunker Hill Mine and the updated timeline and forecast and anticipated capital requirements in connection therewith; the achievement of future short-term, medium-term and long-term operational strategies and objectives and the expected timing thereof, including with respect to planned production; the Company raising the required funds for the planned project restart through its project finance initiatives, including by way of debt, equity, offtake or similar financings; and the expected budget and estimated completion time for the underground development of the Bunker Hill Mine. Forward-looking statements reflect material expectations and assumptions, including, without limitation, expectations and assumptions relating to: Bunker Hill's ability to receive sufficient project financing for the restart and development of the Bunker Hill Mine on acceptable terms or at all; the revised forecast, capital requirements and updated timeline for the project restart resulting in planned production by Q2 2025; the future price of metals; and the stability of the financial and capital markets. Factors that could cause actual results to differ materially from such forward-looking statements include, but are not limited to, those risks and uncertainties identified in public filings made by Bunker Hill with the U.S. Securities and Exchange Commission (the "SEC") and with applicable Canadian securities regulatory authorities, and the following: the Company's ability to operate as a going concern and its history of losses; the Company's ability to raise sufficient project financing for the restart and development of the Bunker Hill Mine on acceptable terms or at all, including through equity or debt financings, concentrate offtake financings or otherwise; the Company requiring more capital expenditures than anticipated in the updated forecast, resulting in delays in the updated timeline; the fluctuating price of commodities; capital market conditions; restrictions on labor and its effects on international travel and supply chains; failure to identify mineral resources; failure to convert estimated mineral resources to reserves; the preliminary nature of metallurgical test results; the Company's ability to restart and develop the Bunker Hill Mine and the risks of not basing a production decision on a feasibility study of mineral reserves demonstrating economic and technical viability, resulting in increased uncertainty due to multiple technical and economic risks of failure which are associated with this production decision including, among others, areas that are analyzed in more detail in a feasibility study, such as applying economic analysis to resources and reserves, more detailed metallurgy and a number of specialized studies in areas such as mining and recovery methods, market analysis, and environmental and community impacts and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit, with no guarantee that production will begin as anticipated or at all or that anticipated production costs will be achieved; failure to commence production would have a material adverse impact on the Company's ability to generate revenue and cash flow to fund operations; failure to achieve the anticipated production costs would have a material adverse impact on the Company's cash flow and future profitability; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; political risks; changes in equity markets; uncertainties relating to the availability and costs of financing needed in the future; the inability of the Company to budget and manage its liquidity in light of the failure to obtain additional financing, including the ability of the Company to complete the payments pursuant to the terms of the agreement to acquire the Bunker Hill Mine complex; inflation; changes in exchange rates; changes in labor costs and availability of skilled labor and specialists; fluctuations in commodity prices; delays in the development of projects; and capital, operating and reclamation costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry. Although the Company believes that the assumptions and factors used in preparing the forward-looking statements in this news release are reasonable, undue reliance should not be placed on such statements or information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all, including as to whether or when the Company will achieve its project finance initiatives, or as to the actual size or terms of those financing initiatives or as to whether and when the Company will achieve its operational and construction targets. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
本资讯发布中的前瞻性陈述包括但不限于关于公司的目标、目标或未来计划的声明,包括Bunker Hill矿的重启和开发,以及与此相关的更新时间表和预期资本需求;实现未来短期、中期和长期运营策略和目标的预期时间,包括计划生产的相关内容;公司通过其项目融资计划筹集所需资金以实现计划项目重启,包括债务、股权、货物销售或类似融资方式;以及Bunker Hill矿地下开发的预期预算和预计完成时间。前瞻性陈述反映了重大期望和假设,包括但不限于与以下内容有关的期望和假设:Bunker Hill获得足够的项目融资以接受可接受条款或完全重启和开发Bunker Hill矿的能力;修订后的预测、资本需求和更新时间表使2025年第二季度实现计划生产;金属的未来价格;以及金融和资本市场的稳定性。可能导致实际结果与此类前瞻性陈述存在重大差异的因素包括但不限于Bunker Hill向美国证券交易委员会("SEC")和相关加拿大证券监管机构提交的公开文件中披露的风险和不确定性,具体如下:公司的持续经营能力及其亏损历史;公司筹集足够项目融资以接受可接受条款或完全重启和开发Bunker Hill矿的能力,包括通过股权或债务融资、浓缩货物销售融资或其他方式;公司在更新预测中所需的资本支出超出预期,导致更新时间表的延迟;商品价格波动;资本市场状况;劳动限制及其对国际旅行和供应链的影响;未能识别矿产资源;未能将估计的矿产资源转化为储量;冶金测试结果的初步性质;公司重启和开发Bunker Hill矿的能力及其未能基于展示经济和技术可行性的矿产储量的可行性研究作出生产决策的风险,因此可能由于与此生产决策相关的多重技术和经济失败风险而增加了不确定性,包括在可行性研究中更详细地分析的领域,例如对资源和储量进行经济分析、冶金数据细化以及在采矿和回收方法、市场分析以及环保和社区影响等方面进行多项专业研究,因此,最终可能会增加对实现任何特定水平的矿产回收或其回收成本的不确定性,包括与开发可商业开采的矿床相关的风险增加,未必保证生产会如预期开始,也可能不达到预期的生产成本;未能开始生产将对公司产生营业收入和现金流以资助运营的能力造成重大不利影响;未能实现预期生产成本将对公司的现金流和未来盈利能力造成重大不利影响;在获得或未能获得要求的政府、环保或其他项目审批方面的延迟;政治风险;股权市场变化;与未来所需融资的可用性和成本有关的不确定性;公司未能在未能获得额外融资的情况下进行预算和管理流动性的能力,包括公司在收购Bunker Hill矿综合体的合同项下完成付款的能力;通货膨胀;汇率变化;劳动成本及熟练劳动和专业人员的可用性变化;商品价格波动;项目开发延迟;以及资本、运营和恢复成本与估算存在显著差异和矿产勘探和开发行业的其他风险。虽然公司相信在准备本资讯发布中的前瞻性陈述时所使用的假设和因素是合理的,但不应对这些陈述或信息给予过度依赖,仅适用本资讯发布的日期,亦无法保证这些事件将在所披露的时间框架内发生或完全发生,包括关于公司是否会实现其项目融资计划,或这些融资计划的实际规模或条款,以及公司是否会实现其运营和施工目标。除法律规定外,公司不承诺或义务更新或修改任何前瞻性信息,无论是由于新信息、未来事件还是其他原因。没有任何证券交易所、证券委员会或其他监管机构批准或否定此处所包含的信息。
Readers are cautioned that the foregoing risks and uncertainties are not exhaustive. Additional information on these and other risk factors that could affect the Company's operations or financial results are included in the Company's annual report and may be accessed through the SEDAR+ website () or through EDGAR on the SEC website (www.sec.gov).
读者被提醒,上述风险和不确定性并非详尽无遗。有关这些及其他可能影响公司运营或财务结果的风险因素的更多信息已包含在公司的年度报告中,并可通过SEDAR+网站()或SEC网站的EDGAR(www.sec.gov)进行访问。
Photos accompanying this announcement are available at:
随此公告发布的照片可在以下位置获取: