The Scarborough Energy Project has passed another significant milestone with the final Pluto Train 2 modules arriving at the Pluto LNG facility in Karratha, Western Australia.

斯卡伯勒能源项目又跨越了另一个重要的里程碑,最后一批冥王星列车2号模块抵达了位于西澳大利亚州卡拉萨的冥王星液化天然气设施。

The successful completion of the Pluto Train 2 module program advances the Scarborough Energy Project towards the targeted delivery of first LNG in 2026.

Pluto Train 2模块计划的成功完成使斯卡伯勒能源项目朝着在2026年交付第一批液化天然气的目标迈进。

Since February 2024, a total of 51 modules, weighing a combined 56,000 metric tonnes, have been shipped to Karratha from the module yard in Batam, Indonesia, where they were built.

自2024年2月以来,共有51个模块,总重量为56,000公吨,已从印度尼西亚巴淡岛的模块厂运往卡拉萨,它们是在那里制造的。

Expanding the Pluto LNG facility to include a second LNG processing train provides an efficient way to process gas from the offshore Scarborough field.

扩建冥王星液化天然气设施以包括第二套液化天然气处理列车,为处理来自斯卡伯勒海上气田的天然气提供了一种有效的方式。