Bitdeer Announces December 2024 Production And Operations Update; 145 Bitcoins Mined; 594 Bitcoins Held; Production Of ~35 EH/s Of SEALMINER A2s Through Q3 2025 Remains On Track
Bitdeer Announces December 2024 Production And Operations Update; 145 Bitcoins Mined; 594 Bitcoins Held; Production Of ~35 EH/s Of SEALMINER A2s Through Q3 2025 Remains On Track
Production and Operations Summary
生产和运营摘要
Metrics | Dec 2024 | Nov 2024 | Dec 2023 |
Total hash rate under management1 (EH/s) | 21.6 | 20.7 | 21.0 |
- Proprietary hash rate | 8.9 | 8.8 | 8.4 |
• Self-mining | 8.5 | 8.2 | 6.7 |
• Cloud Hash Rate | 0.0 | 0.2 | 1.7 |
• Delivered but not hashing | 0.4 | 0.4 | - |
- Hosting | 12.7 | 11.9 | 12.6 |
Mining machines under management | 175,000 | 178,000 | 215,000 |
- Self-owned2 | 85,000 | 86,000 | 86,000 |
- Hosted | 90,000 | 92,000 | 129,000 |
Bitcoins mined (self-mining only) | 145 | 150 | 434 |
Bitcoins held3 | 594 | 443 | 43 |
指标 | 2024 年 12 月 | 2024 年 11 月 | 2023 年 12 月 |
管理下的总哈希率1 (EH/s) | 21.6 | 20.7 | 21.0 |
-专有哈希率 | 8.9 | 8.8 | 8.4 |
• 自挖矿 | 8.5 | 8.2 | 6.7 |
• 云哈希率 | 0.0 | 0.2 | 1.7 |
• 已送达但未进行哈希处理 | 0.4 | 0.4 | - |
-托管 | 12.7 | 11.9 | 12.6 |
管理下的采矿机 | 175,000 | 178,000 | 215,000 |
-自有2 | 85,000 | 86,000 | 86,000 |
-托管 | 90,000 | 92,000 | 129,000 |
开采的比特币(仅限自采) | 145 | 150 | 434 |
持有的比特币3 | 594 | 443 | 43 |
1 Total hash rate under management as of December 31, 2024 across the Company's three primary business lines: Self-mining, Cloud Hash Rate, and Hosting.
1 截至2024年12月31日,公司三个主要业务领域管理的总哈希率:自挖矿、云哈希率和托管。
- Self-mining refers to cryptocurrency mining for the Company's own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end. However, throughout the month, the Cloud Hash Rate may transition to Self-mining hash rate if customers opt to not make their monthly electricity payments for various reasons.
-
Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.
- 自我挖矿是指对公司自己的账户进行加密货币挖矿,这使其能够直接捕捉加密货币的高升值潜力。
- Cloud Hash Rate提供哈希率订阅计划,并根据某些安排与客户分享采矿收入。上述云哈希率反映了月底与客户签订的合同哈希率。但是,如果客户出于各种原因选择不按月支付电费,则在整个月中,云哈希率可能会过渡到自挖哈希率。
- 托管包括一站式采矿机托管解决方案,包括用于高效加密货币挖矿的部署、维护和管理服务。
2 Self-owned mining machines are for the Company's self-mining business and Cloud Hash Rate business.
3 Bitcoins held do not include the Bitcoins from deposits of the customers.
2 台自有采矿机用于公司的自采业务和云哈希率业务。
3 持有的比特币不包括客户存款中的比特币。
Infrastructure Construction Update
基础设施建设最新情况
Rockdale, Texas – 100 MW Hydro-cooling conversion to be energized in phases in Q1 2025:
德克萨斯州罗克代尔——100 兆瓦水冷转换将于 2025 年第一季度分阶段通电:
- Cooling system will be delivered and installed in phases in Q1 2025.
- Planning for phased energization between January and March 2025.
- 冷却系统将于 2025 年第一季度分阶段交付和安装。
- 计划在 2025 年 1 月至 3 月之间分阶段通电。
Tydal, Norway – 175 MW site expansion anticipated to be fully energized by mid-2025:
挪威泰达尔——预计到2025年中期,175兆瓦的场地扩建将全面通电:
- Installation of the transformers has been completed, with the delivery and installation of electrical equipment currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are underway, and drainage systems construction is ongoing.
- Tydal, Norway Phase 1 40 MW expansion pending regulatory approval. Energization of the full 175 MW site is reasonably expected to be no later than mid-2025.
- 变压器的安装已经完成,电气设备的交付和安装目前正在进行中。此外,集装箱和水冷系统的采购和交付正在进行中,排水系统的建设也在进行中。
- 挪威泰达尔第一阶段 40 兆瓦扩建项目正在等待监管部门的批准。合理地预计,整个175兆瓦的电站将不迟于2025年中期的通电。
Massillon, Ohio – 221 MW site construction has begun ahead of schedule:
俄亥俄州马西隆——221兆瓦的场地建设已提前开始:
- Substation construction is underway and is expected to be completed in Q3 2025.
- Building design is completed and construction has begun earlier than expected, estimated to be completed in phases between Q3 and Q4 2025.
- Estimated energization timeline remains on track for mid-to-late 2025.
- 变电站建设正在进行中,预计将于2025年第三季度完成。
- 建筑设计已经完成,施工开始的时间比预期的要早,预计将在2025年第三季度至第四季度之间分阶段完成。
- 预计的2025年中后期的通电时间表仍在按计划进行。
Jigmeling, Bhutan – 500 MW site is progressing well, with the following key milestones achieved:
不丹吉格梅林——500兆瓦的发电厂进展顺利,实现了以下关键里程碑:
- Construction of transformer and container foundations in progress and will be completed in phases, with the last phase expected by the end of February 2025.
- 132kb/140MW and 220kv/360MW substation designs are completed with construction anticipated to be ready by the end of Q1 2025.
- Orders for the procurement of transformers and electrical equipment have been placed, with delivery and installation work to be completed in phases over Q1 and Q2 2025.
- Procurement and delivery of containers and hydro-cooling systems are in progress, with completion in phases by the end of Q1 2025.
- 变压器和集装箱基础的建设正在进行中,将分阶段完成,最后阶段预计将于2025年2月底完成。
- 132kb/140mW 和 220kV/360mW 变电站设计已经完成,预计施工将在2025年第一季度末准备就绪。
- 变压器和电气设备的采购订单已经下达,交付和安装工作将在2025年第一季度和第二季度分阶段完成。
- 集装箱和水冷系统的采购和交付正在进行中,将于2025年第一季度末分阶段完成。
Site / Location | Capacity (MW) | Status | Timing4 |
Electrical capacity | |||
- Rockdale, Texas | 563 | Online | Completed |
- Knoxville, Tennessee | 86 | Online | Completed |
- Wenatchee, Washington | 13 | Online | Completed |
- Molde, Norway | 84 | Online | Completed |
- Tydal, Norway | 50 | Online | Completed |
- Gedu, Bhutan | 100 | Online | Completed |
Total electrical capacity | 8955 | ||
Pipeline capacity | |||
- Tydal, Norway Phase 1 | 40 | In progress | Pending Regulatory Approval |
- Tydal, Norway Phase 2 | 135 | In progress | Mid 2025 |
- Massillon, Ohio | 221 | In progress | Mid-to-late 2025 |
- Clarington, Ohio Phase 1 | 266 | In progress | Q3 2025 |
- Clarington, Ohio Phase 2 | 304 | Pending approval | Estimate 2026 |
- Jigmeling, Bhutan | 500 | In progress | Mid-to-late 2025 |
- Rockdale, Texas | 179 | In planning | Estimate 2026 |
Total pipeline capacity | 1,645 | ||
Total global electrical capacity | 2,540 |
地点/位置 | 容量 (MW) | 状态 | 时机 4 |
电气容量 | |||
-德克萨斯州罗克代尔 | 563 | 在线 | 已完成 |
-田纳西州诺克斯维尔 | 86 | 在线 | 已完成 |
-华盛顿州韦纳奇 | 13 | 在线 | 已完成 |
-挪威莫尔德 | 84 | 在线 | 已完成 |
-挪威泰达尔 | 50 | 在线 | 已完成 |
-不丹 Gedu | 100 | 在线 | 已完成 |
总电容量 | 8955 | ||
管道容量 | |||
-挪威泰达尔第一阶段 | 40 | 进行中 | 待监管部门批准 |
-挪威泰达尔第二阶段 | 135 | 进行中 | 2025 年中期 |
-俄亥俄州马西隆 | 221 | 进行中 | 2025 年中后期 |
-俄亥俄州克拉灵顿第一阶段 | 266 | 进行中 | 2025 年第三季度 |
-俄亥俄州克拉灵顿第二阶段 | 304 | 待批准 | 估计 2026 |
-不丹吉格梅林 | 500 | 进行中 | 2025 年中后期 |
-德克萨斯州罗克代尔 | 179 | 在规划中 | 估计 2026 |
管道总容量 | 1,645 | ||
全球总电力容量 | 2,540 |
4 Indicative timing. All timing references are to calendar quarters and years.
5 Figures may not add up due to rounding.
4 指示性时机。所有时间参考均指日历季度和年份。
5 由于四舍五入,数字相加可能不一致。