Fortescue Faces Pipeline Leaks
Fortescue Faces Pipeline Leaks
Fortescue Metals' (ASX:FMG) troubled Iron Bridge export magnetite iron ore mine in WA's Pilbara continues to cause problems and is nowhere near planned capacity at this stage.
位於西澳大利亞州皮爾巴拉的Fortescue Metals(澳大利亞證券交易所股票代碼:FMG)陷入困境的鐵橋出口磁鐵礦繼續造成問題,目前還遠未達到計劃產能。
Cost overruns, technical problems, management changes, and budget blowouts saw a $US1 billion pre-tax impairment in the June 30, 2023 year, as Fortescue battled to rightsize the budget and the operation of the project.
隨着Fortescue努力調整預算和項目運營,成本超支、技術問題、管理層變動和預算井噴在2023年6月30日造成了10億美元的稅前減值。
But now there are leaks in a vital piece of infrastructure - a 220-kilometer water supply pipeline, where more than 30% (approximately 65 kilometers) of steel pipe will need replacing.
但是現在,一條長達220公里的供水管道——一條至關重要的基礎設施出現了泄漏,其中超過30%(約65千米)的鋼管需要更換。
This problem alone could cost Fortescue more than $A1.3 billion in lost sales revenue and extra costs to fix the leaks.
僅這個問題就可能使Fortescue損失超過13億澳元的銷售收入和修復泄漏的額外成本。
It's the second time in 10 months this pipeline has disrupted the project - in March, it delayed the final work on Iron Bridge for around three months.
這是該管道在10個月內第二次中斷該項目——3月,它將Iron Bridge的最後工程推遲了大約三個月。
But according to Fortescue, Iron Bridge is doing okay, which does seem a bit at odds with the pipeline problems and the huge cost to fix it - close to $A200 million.
但是根據Fortescue的說法,Iron Bridge表現不錯,這似乎與管道問題和修復管道的巨大成本——接近2億澳元——有些矛盾。
"Iron Bridge commissioning activities continue to progress well. A second shipment of Iron Bridge Concentrate was achieved during Q2 FY24, and three shipments in January 2024."
“Iron Bridge的調試活動繼續進展順利。Iron Bridge 濃縮物的第二批出貨是在24財年第二季度實現的,三批於2024年1月發貨。”
"Iron Bridge FY24 shipments guidance has been revised due to the performance of the Raw Water Pipeline. Work is underway to resolve the performance issues.
“由於原水管道的表現,鐵橋24財年的出貨指導已修訂。解決性能問題的工作正在進行中。
Fortescue had already trimmed expected exports from Iron Bridge from 7 million tonnes in its June 30, 2023 announcement to 5 million in its September quarter production and sales report.
Fortescue已經將Iron Bridge的預期出口量從2023年6月30日公告中的700萬噸削減至9月季度產量和銷售報告中的500萬噸。
But Thursday's December quarter saw yet another cut to a range of 2 to 4 million tonnes for the year to June 30 - in other words, the original 7 million tonne estimate for the year to June 30, 2024, has been slashed by more than 70% at worst.
但是,週四的12月季度在截至6月30日的年度中再次削減至200萬至400萬噸——換句話說,截至2024年6月30日的年度最初估計的700萬噸,最壞的情況已經下調了70%以上。
The explanation was detailed in the quarterly report with the project's 61.9% owner, Fortescue, up for an estimated $US100 million (or more than $A150 million) to fix the leaks.
季度報告中詳細介紹了這一解釋,該項目61.9%的所有者Fortescue估計需要1億美元(合1.5億澳元以上)來修復泄漏問題。
"While the performance of the Canning Basin Raw Water Pipeline improved relative to the prior quarter, further leaks were detected during Q2 FY24, which impacted the flow rate and uptime.
“儘管坎寧盆地原水管道的性能與上一季度相比有所改善,但在24財年第二季度發現了進一步的泄漏,這影響了流量和正常運行時間。
"Work is underway to evaluate options to de-risk and improve the performance of the high-pressure section (65 kilometers) of the Raw Water Pipeline, where the leaks have occurred.
“正在評估各種備選方案,以降低發生泄漏的原水管道高壓部分(65千米)的性能,並改善其性能。
"It is anticipated that replacing this section of the Pipeline would not materially impact Iron Bridge's ramp-up schedule and would require an investment of approximately US$100 million (Fortescue's share)," Fortescue said.
Fortescue說:“預計更換這段管道不會對Iron Bridge的擴建計劃產生重大影響,並且需要投資約1億美元(Fortescue的份額)。”
The loss is substantial for Fortescue - if it had been able to make the 7 million tonnes of exports from Iron Bridge, it would have added another $US1 billion to annual revenue by June 30 (that's at the $US144 a tonne the Iron Bridge concentrates were sold, according to the latest quarterly report).
Fortescue的損失是巨大——如果它能夠從Iron Bridge出口700萬噸,到6月30日,其年收入將再增加10億美元(根據最新的季度報告,鐵橋精礦的銷售額爲每噸144美元)。
If they manage to ship 2 million tonnes by June 30, Fortescue could forgo $US700 million of revenue. Selling four million tonnes would see the company miss revenues of more than $US400 million.
如果他們設法在6月30日之前出貨200萬噸,Fortescue可能會放棄7億美元的收入。出售400萬噸將使該公司損失超過4億美元的收入。
Those leaks are an expensive headache in more ways than one.
這些泄漏在許多方面都是一個代價高昂的頭疼問題。