Ascot Provides Construction Update on the Premier Gold Project

Ascot Provides Construction Update on the Premier Gold Project

Ascot提供Premier Gold項目的施工最新情況
GlobeNewswire ·  02/20 08:57

Figure 1

圖 1

Visible gold in quartz vein found in ore drive 6 at Big Missouri
在大密蘇里州的6號礦石大道中發現了石英礦脈中的可見金

Figure 2

圖 2

TSF overview looking south
TSF 概覽向南看

Figure 3

圖 3

TSF South and Southeast dams complete
TSF 南大壩和東南大壩完工

Figure 4

圖 4

WTP commissioning
WTP 調試

Figure 5

圖 5

WTP MBBR system
WTP MBBR 系統

Figure 6

圖 6

Mill piping over 90% complete
磨機管道已完成 90% 以上

Figure 7

圖 7

Premier underground portal overhead
頭頂的頂級地下門戶

Figure 8

圖 8

Premier underground portal front view
高級地下入口正面視圖

Figure 9

圖 9

Mill area overview
磨機區域概述

VANCOUVER, British Columbia, Feb. 20, 2024 (GLOBE NEWSWIRE) -- Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) ("Ascot" or the "Company") is pleased to provide a construction update on the Company's Premier Gold Project ("PGP" or the "Project"), located on Nisga'a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. Project construction was 86% complete as of December 31, 2023 (approximately 90% as of January 31, 2024) and is currently nearing completion, with first ore delivery to the mill anticipated by the end of March 2024, and first gold pour anticipated in April.

不列顛哥倫比亞省溫哥華,2024年2月20日(GLOBE NEWSWIRE)——阿斯科特資源有限公司(多倫多證券交易所股票代碼:AOT;OTCQX:AOTVF)(“阿斯科特” 或 “公司”)很高興提供該公司位於尼斯的頂級黃金項目(“PGP” 或 “項目”)的最新施工情況ga'a Nation Treaty 位於不列顛哥倫比亞省西北部多產的金三角。截至2023年12月31日,項目建設已完成86%(截至2024年1月31日約爲90%),目前已接近完成,預計第一批礦石將於2024年3月底交付該工廠,首次淘金預計將於4月交付。

Derek White, President and CEO, commented, "With Project construction nearing completion and early commissioning underway, we eagerly anticipate progressing to the production and operations phase at the Premier Gold Mine. The Project also accomplished an impressive safety milestone having surpassed one million hours without a lost time incident, along with another quarterly reduction in total recordable incident frequency. We are also proud to have recently closed an additional financing package which we believe is sufficient for the Company to progress from construction to first gold pour, ramp-up, commercial production and steady-state operations. With the gold price still trading near US$2,000 per ounce, this is an opportune time for us to become Canada's next gold producer."

總裁兼首席執行官德里克·懷特評論說: “隨着項目建設接近完成,早期調試正在進行中,我們熱切期待Premier金礦進入生產和運營階段。該項目還實現了令人印象深刻的安全里程碑,沒有發生損失工時事故超過一百萬小時,同時可記錄的事故總頻率又減少了一個季度。我們還自豪地最近完成了一項額外的一攬子融資計劃,我們認爲這足以讓公司從施工到首次淘金、擴建、商業生產和穩態運營。由於黃金價格仍接近每盎司2,000美元,這是我們成爲加拿大下一個黃金生產國的好時機。”

PROJECT CONSTRUCTION

項目施工

Funding for Construction and Ramp-Up
On February 20, 2024, the Company announced the closing of its financing for a total of US$50 million from Sprott Resource Streaming and Royalty Corp. and/or its affiliates ("Sprott Streaming") and Nebari Natural Resources Credit Fund II, LP ("Nebari"), as further described in the Company's news release dated January 22, 2024. Concurrently, the Company closed its previously announced bought deal private placement financing with a syndicate of underwriters co-led by BMO Capital Markets and Desjardins Capital Markets (together, the "Joint Bookrunners"), and including CIBC World Markets Inc., Raymond James Ltd. and Velocity Trade Capital Ltd. (collectively, with the Joint Bookrunners, the "Underwriters"). Under the bought deal financing, the Company issued a total of 65,343,000 common shares of the Company (the "Common Shares") at a price of C$0.44 per Common Share, for gross proceeds of approximately C$29 million, which included the full exercise of the Underwriters' option.

爲施工和擴建提供資金
2024年2月20日,該公司宣佈完成來自Sprott Resource Streaming and Royalty Corp. 和/或其附屬公司(“Sprott Streaming”)和Nebari自然資源信貸基金II,LP(“Nebari”)的總額爲5000萬美元的融資,該公司在2024年1月22日的新聞稿中對此進行了進一步的描述。同時,該公司與由BMO資本市場和Desjardins資本市場(統稱爲 “聯合賬簿管理人”)共同牽頭的承銷商集團完成了先前宣佈的收購交易私募融資,其中包括加拿大帝國商業銀行世界市場公司、雷蒙德·詹姆斯有限公司和Velocity Trade Capital Ltd.(合稱 “承銷商”)。根據收購交易融資,公司以每股普通股0.44加元的價格共發行了公司65,343,000股普通股(“普通股”),總收益約爲2900萬加元,其中包括承銷商全部行使期權。

Construction Progress Key Performance Indicators ("KPI")

施工進度關鍵績效指標(“KPI”)

At the end of Q4 2023, overall construction excluding mine development was 86% complete (approximately 90% as of January 31, 2024), compared with 66% complete at the end of Q3 2023. Numerous pre-commissioning activities in the mill have commenced. The Company anticipates introducing first ore into the mill by the end of March 2024, and pouring first gold in April.

截至2023年第四季度末,不包括礦山開發在內的總體施工已完成86%(截至2024年1月31日約爲90%),而2023年第三季度末的施工完成率爲66%。該工廠的許多預調試活動已經開始。該公司預計,到2024年3月底將第一塊礦石引入該工廠,並在4月注入第一批黃金。

Capital costs, including mining costs, incurred as of December 31, 2023 were $292 million. As of December 31, 2023, the remaining project construction capital required to complete construction and achieve the first gold pour is approximately $47 million including mine development costs but excluding certain pre-operating costs and working capital. This implies a total project capital cost of $339 million, which is slightly higher than the most recent total project budget of $334 million as reported last quarter. The increase is mainly attributable to the increase in duration of the earthworks and project indirect costs.

截至2023年12月31日,包括採礦成本在內的資本成本爲2.92億美元。截至2023年12月31日,完成施工和實現首次淘金所需的剩餘項目建設資金約爲4700萬美元,其中包括礦山開發成本,但不包括某些運營前成本和營運資金。這意味着項目總資本成本爲3.39億美元,略高於上個季度公佈的最新項目總預算3.34億美元。增加的主要原因是土方工程持續時間延長和項目間接費用。

The Company ended December 2023 with a cash balance of C$27 million. With the aforementioned additional financing of US$50 million from Sprott Streaming and Nebari Credit Fund II, and the equity financing with gross proceeds of C$29 million, the Company believes it is well financed to complete construction of the Project, progress through the ramp-up phase to commercial production and reach nameplate capacity at the Premier Gold Mine.

截至2023年12月,該公司的現金餘額爲2700萬加元。藉助上述來自Sprott Streaming和Nebari Credit Fund II的5000萬美元額外融資,以及總收益爲2900萬加元的股權融資,該公司認爲,其資金充足,可以完成該項目的建設,進入商業化生產的準備階段,並達到Premier金礦的標稱產能。

Safety
The Premier Gold Project reached an important safety milestone in Q4 of 2023: one million hours without lost time incidents ("LTI"). By the end of Q4 2023, this figure reached 1,143,029 hours LTI free. The total recordable incident frequency has been reduced yet again from 0.69 at the end of Q3 2023 to 0.52 by the end of Q4 2023. The frequency of total incidents including property damage, first aid injuries, and near misses, was relatively similar to Q3 2023. Reporting activity continues to improve, and the Company will continue to work on proactive safety training and measures to reduce overall incidents on site, especially with pending transition from construction to the operations phase.

安全
Premier Gold 項目在 2023 年第四季度達到了一個重要的安全里程碑:一百萬小時沒有發生損失工時事件(“LTI”)。到 2023 年第四季度末,這一數字達到了 1,143,029 小時免長期保費。可記錄的總事件頻率已從2023年第三季度末的0.69再次降低到2023年第四季度末的0.52。包括財產損失、急救傷害和險些失誤在內的總事件發生頻率與 2023 年第三季度相對相似。報告活動持續改善,公司將繼續開展積極的安全培訓和措施,以減少現場的總體事故,尤其是在尚待從施工階段過渡到運營階段的情況下。

Processing Plant
In Q3 2023, mechanical and electrical work in the mill was substantially advanced. In Q4 2023, work in the mill focused on piping, systems & controls as well as remaining electrical terminations.

加工廠
2023 年第三季度,工廠的機械和電氣工作大幅推進。2023 年第四季度,工廠的工作重點是管道、系統和控制裝置以及剩餘的電氣終端。

Piping installation included work inside the mill building and also outside connections to the carbon-in-leach ("CIL") tanks, and cyanide destruction and tailings thickener lines. Piping installation at the mill is over 90% complete. Electrical work progressed on completing terminations and installation of the fire detection system. Instrumentation and controls installations are advancing well. Staged commissioning has started on the Ball and SAG mills, CIL circuit, and cyclone feed pumps. As a part of the commissioning process, both Ball and SAG mills have been energized and rotated. The Ball mill has been loaded with water and successfully rotated for an 8-hour period with no issues. The SAG mill has been rotated for several hours and will undergo water load testing this week.

管道安裝包括工廠大樓內部的工程,以及與碳浸出(“CIL”)儲罐的外部連接,以及氰化物銷燬和尾礦增稠劑管線。工廠的管道安裝已完成90%以上。完成火災探測系統的終端和安裝後,電氣工作取得了進展。儀表和控制裝置進展順利。球磨機和 SAG 磨機、CIL 迴路和旋風進料泵的分階段調試已經開始。作爲調試過程的一部分,球磨機和半自磨機均已通電和旋轉。球磨機已經裝滿了水,成功旋轉了 8 小時,沒有出現任何問題。SAG磨機已經旋轉了幾個小時,並將在本週進行水負荷測試。

Tailings Storage Facility ("TSF") Earthworks
With the milder-than-average winter season so far, much work was progressed on the TSF earthworks in Q4 2023 and into early 2024. The South Dam, North Dam, and Southeast Dam have been completed. The minor remaining work is focused on the smaller East Dam and spillway which is expected to complete by mid-March.

尾礦儲存設施(“TSF”)土方工程
由於迄今爲止冬季節低於平均水平,2023年第四季度至2024年初,TSF土方工程取得了許多進展。南壩、北壩和東南大壩已經建成。剩餘的小部分工作集中在較小的東壩和溢洪道上,預計將於3月中旬完工。

Currently the earthworks around the TSF are substantially complete, with some minor works remaining anticipated to be completed by late February.

目前,TSF周圍的土方工程已基本完成,一些小型工程預計將於2月下旬完成。

Water Treatment Plant ("WTP")
Commissioning of the WTP components started in Q4 2023, with most areas being commissioned in isolation. Upon the delivery and installation of two transformers and a buffer tank in December 2023, and the 138 kV power connection in January 2024, the WTP is currently undergoing final commissioning. Normal operation of the WTP is anticipated this month. As of the writing of this release, Ascot can report that the High-Density Sludge ("HDS") plant has been successfully commissioned and is awaiting final test results on the effluent water before discharge into the environment is authorized. The Moving Bed Bio-Reactor ("MBBR") is mechanically and electrically complete and media is being loaded into the tanks. The plant will be brought into service mid-March in time for mill start-up.

水處理廠(“WTP”)
WTP 組件的調試於 2023 年第四季度開始,大多數區域是隔離調試的。在2023年12月交付和安裝兩臺變壓器和一個緩衝罐,以及在2024年1月交付和安裝138千伏電力連接之後,水處理廠目前正在進行最後的調試。預計WTP將於本月正常運行。截至撰寫本新聞稿時,阿斯科特可以報告說,高密度污泥(“HDS”)工廠已成功投入使用,正在等待污水的最終測試結果,然後才獲准排放到環境中。移動牀生物反應器(“MBBR”)的機械和電氣均已完成,介質正在裝入儲罐。該工廠將於3月中旬投入使用,正好趕上工廠的啓動。

Site Infrastructure
During Q3 2023, most of the new electrical substation was mechanically completed, and crews completed the 138kV power line to connect to the power grid less than 500 metres away. In Q4 2023, all 138kV lines were pulled and linked up with the BC Hydro grid. Site electrification was originally planned for mid-December, but three new switches were required. Once these were delivered in early January 2024, site powerup on the 138 kV line was completed on January 14, 2024.

站點基礎架構
在 2023 年第三季度,大部分新變電站已機械完工,工作人員完成了 138kV 的電力線,連接到不到 500 米外的電網。2023 年第四季度,所有 138 千伏線路都已拉開並與不列顛哥倫比亞水電網相連。場地電氣化原計劃於12月中旬進行,但需要三臺新的開關。這些線路於 2024 年 1 月初交付後,這條 138 千伏線路的現場供電於 2024 年 1 月 14 日完成。

Off-Site Infrastructure
On October 3, 2023, the town council of Stewart, B.C. approved a Temporary Use Permit ("TUP") to install a camp facility in the town to provide additional accommodations for workers at the Project. The TUP is for a three-year term with potential to renew for another three years afterwards. The Company quickly mobilized and installed living quarters with an initial capacity of 76 beds in early December. This has alleviated some of the pressure caused by the extended earthworks schedule.

場外基礎設施
2023年10月3日,不列顛哥倫比亞省斯圖爾特市議會批准了臨時使用許可證(“TUP”),在該鎮安裝露營設施,爲該項目的工作人員提供更多住宿。TUP的任期爲三年,之後可能會再續約三年。12月初,公司迅速調動並安裝了起居區,初始容量爲76張牀位。這緩解了土方工程延期所造成的一些壓力。

On September 19, 2023, the Company acquired a full-service laboratory facility ("Assay Lab") in Stewart, BC from Seacan Labs Corp. The Assay Lab will be used to perform the testing required by Ascot for mineral exploration, mining operation, and environmental monitoring. During Q4 2023, the Assay Lab was re-commissioned for use and is currently ramping up toward full capacity of 250-300 samples per day with a 24-hour turnaround.

2023年9月19日,該公司從Seacan Labs Corp. 手中收購了位於不列顛哥倫比亞省斯圖爾特的全方位服務的實驗室設施(“化驗實驗室”)。該化驗實驗室將用於進行阿斯科特要求的礦產勘探、採礦作業和環境監測的測試。在 2023 年第四季度,化驗實驗室重新投入使用,目前正逐步提高到每天 250-300 個樣本的滿負荷容量,週轉時間爲 24 小時。

Mine Development
In Q3 2023, the Company's underground mining contractor Procon began their initial mobilization to site and deployed senior project management personnel to coordinate storage and laydown areas ahead of operating crew mobilization.

礦山開發
2023 年第三季度,該公司的地下采礦承包商 Procon 開始了對現場的初步調動,並在動員運營人員之前部署了高級項目管理人員來協調儲存和佈局區域。

In Q4 2023, once the Big Missouri Portal infrastructure and mine services were re-established, underground development was re-commenced. Procon advanced underground waste and ore development including the decline, which will eventually connect to the Silver Coin deposit. In advance of mill start-up in Q1 2024, Ascot is stockpiling mineralized material from Big Missouri in the Diego pit, ready for processing. Underground development rates at Big Missouri have been gradually improving, with linear advances as high as 16 metres per day achieved, and on average crews are achieving approximately 10 to 12 metres per day currently. Including development in 2022, total underground development at Big Missouri totaled 1,300 metres as of Q4 2023, and approximately 1,650 metres by February 15, 2024.

2023 年第四季度,大密蘇里門戶基礎設施和礦山服務重新建立後,地下開發便重新開始。Procon推進了地下廢物和礦石的開發,包括衰退,最終將與銀幣礦牀相連。在工廠於2024年第一季度啓動之前,Ascot正在迭戈礦坑中儲存來自密蘇里大公司的礦化材料,準備加工。大密蘇里州的地下開發速度一直在逐步提高,每天的線性進度高達16米,目前工作人員平均每天的開發速度約爲10至12米。包括2022年的開發項目在內,截至2023年第四季度,大密蘇里州的地下開發總量爲1300米,到2024年2月15日約爲1,650米。

Recently in ore drive 6 at Big Missouri, the geology team noted an occurrence of coarse, visible gold in a quartz vein (see Figure 1 below). This material was within a geological wireframe approximately on dip with an existing stope shape about 20 metres away. In conjunction with exploration drilling intercepting high-grade gold mineralization outside of existing stope shapes in 2023, this occurrence provides further evidence of the potential for expansion beyond the current mine plan.

最近,在大密蘇里州的6號礦石大道中,地質小組注意到石英礦脈中存在粗糙可見的黃金(見下圖1)。這種材料大約在傾斜時位於地質線框內,現有的採場形狀在大約 20 米外。再加上勘探鑽探將在2023年截獲現有采場形狀之外的高品位金礦化,這進一步證明了在當前採礦計劃之外擴張的潛力。

In August 2023, surface work commenced on the new Premier Portal close to the mill. In Q4 2023, Procon continued the portal face preparations including holes for cable bolts and other ground support and began clearing a pad area for service infrastructure including gensets and compressors. The underground decline development started in early December with initial rounds and placement of shotcrete arches similar to what was done at Big Missouri in 2022. Poor ground near surface and extreme cold temperatures slowed advance in January 2024, but conditions have improved in February. Mining development will be advanced down into the Premier deposit for initial mining in the Prew Zone, with ore development anticipated to begin in Q2 2024, and stope production following in Q3 2024. The ramp has been strategically laid out to allow for underground drilling on the Sebakwe Zone in 2024 and will eventually connect a footwall ramp over to the 602 area at the southern end of the Premier deposit.

2023 年 8 月,工廠附近的新的 Premier Portal 開始了地面施工。2023 年第四季度,Procon 繼續進行門面準備工作,包括爲電纜螺栓和其他地面支撐開孔,並開始爲包括髮電機組和壓縮機在內的服務基礎設施清理停機坪區域。地下斜坡開發始於12月初,最初的幾輪施工和噴射混凝土拱門的佈置與2022年密蘇里巨頭的施工情況類似。2024年1月,地表附近地面條件不佳,極端寒冷的氣溫減緩了前進速度,但2月份情況有所改善。採礦開發將向下推進到Premier礦牀,用於在Prew區進行初始採礦,礦石開發預計將於2024年第二季度開始,採場生產將在2024年第三季度開始。該坡道的佈局經過了戰略規劃,允許在2024年在Sebakwe區進行地下鑽探,並將最終將人行坡道與Premier礦牀南端的602區域連接起來。

Recruitment
Recruitment efforts and activity materially increased in the past quarter, as Ascot continues to have many qualified candidates applying for open positions. In January 2024, Ascot representatives attended a recruitment fair in Campbell River, BC, after it was announced that the nearby Myra Falls underground mine and mill was being placed on care & maintenance. During the job fair Ascot conducted two hundred in person and virtual interviews, and the Company has since been able to fill many open positions for skilled trades and operators.

招聘
由於Ascot繼續有許多合格的候選人申請空缺職位,招聘工作和活動在過去一個季度中大幅增加。2024年1月,阿斯科特代表參加了在不列顛哥倫比亞省坎貝爾裏弗舉行的招聘會,此前宣佈附近的邁拉瀑布地下礦山和磨坊正在接受保養和維護。在招聘會期間,阿斯科特進行了兩百次面對面和虛擬面試,此後,該公司得以爲熟練工人和操作員填補了許多空缺職位。

Key senior level roles filled during Q4 2023 and recently include Operations Manager, a second Mine Superintendent, a Senior Mining Engineer, Maintenance Superintendent, Maintenance General Foreman, Mill Operations General Foreman and a number of Supervisors.

2023年第四季度擔任的主要高級職位包括運營經理、第二礦山主管、高級採礦工程師、維護總監、維護總監、維護總管、工廠運營總領班和多名主管。

PROJECT PHOTOS

項目照片

Figure 1 – Visible gold in quartz vein found in ore drive 6 at Big Missouri

圖 1 — 在密蘇里州大道 6 號礦石中發現的石英礦脈中可見的金

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 2 – TSF overview looking south

圖 2 — 向南看的 TSF 概述

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 3 – TSF South and Southeast dams complete

圖 3 — TSF 南大壩和東南大壩完工

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 4 – WTP commissioning

圖 4 — WTP 調試

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 5 – WTP MBBR system

圖 5 — WTP MBBR 系統

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 6 – Mill piping over 90% complete

圖 6 — 磨機管道已完成 90% 以上

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 7 – Premier underground portal overhead

圖 7 — 頭頂的頂級地下門戶

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 8 – Premier underground portal front view

圖 8 — 頂級地下入口正面視圖

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Figure 9 – Mill area overview

圖 9 — 磨機區域概述

A photo accompanying this announcement is available at

本公告附帶的照片可在以下網址獲得

Qualified Person

合格人員

John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company's Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.

根據National Instrument 43-101的定義,公司首席運營官約翰·基爾南是公司的合格人員(QP),並已審查並批准了本新聞稿的技術內容。

On behalf of the Board of Directors of Ascot Resources Ltd.
"Derek C. White"
President & CEO

代表阿斯科特資源有限公司董事會
“德里克·C·懷特”
總裁兼首席執行官

For further information contact:

欲了解更多信息,請聯繫:

David Stewart, P.Eng.
VP, Corporate Development & Shareholder Communications
dstewart@ascotgold.com
778-725-1060 ext. 1024

大衛·斯圖爾特,P.Eng
企業發展與股東傳播副總裁
dstewart@ascotgold.com
778-725-1060 分機 1024

About Ascot Resources Ltd.

關於阿斯科特資源有限公司

Ascot is a Canadian junior exploration and development company focused on re-starting the past producing Premier Gold Mine, located on Nisga'a Nation Treaty Lands, in British Columbia's prolific Golden Triangle. Ascot shares trade on the TSX under the ticker AOT. Concurrent with progressing the development of Premier, the Company continues to explore its properties for additional high-grade underground resources. Ascot is committed to the safe and responsible development of Premier in collaboration with Nisga'a Nation as outlined in the Benefits Agreement.

Ascot是一家加拿大初級勘探和開發公司,專注於重啓過去生產位於尼斯的Premier金礦的歷史ga'a Nation Treaty Lands 位於不列顛哥倫比亞省多產的金三角。阿斯科特股票在多倫多證券交易所上市,股票代碼爲AOT。在推進Premier開發的同時,該公司繼續勘探其地產,尋找更多的高品位地下資源。如福利協議所述,阿斯科特致力於與尼斯加民族合作,以安全和負責任的方式發展Premier。

For more information about the Company, please refer to the Company's profile on SEDAR+ at or visit the Company's web site at , or for a virtual tour visit under Ascot Resources.

有關公司的更多信息,請參閱公司在SEDAR+上的簡介,或訪問公司的網站,或訪問Ascot Resources下的虛擬參觀。

The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

多倫多證券交易所尚未審查本新聞稿的充分性或準確性,也不承擔任何責任。

Cautionary Statement Regarding Forward-Looking Information

關於前瞻性信息的警示聲明

All statements and other information contained in this press release about anticipated future events may constitute forward-looking information under Canadian securities laws ("forward-looking statements"). Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeted", "outlook", "on track" and "intend" and statements that an event or result "may", "will", "should", "could", "would" or "might" occur or be achieved and other similar expressions. All statements, other than statements of historical fact, included herein are forward-looking statements, including statements in respect of advancement and development of the PGP and the timing related thereto, the completion of the PGP mine, the production of gold and management's outlook for the remainder of 2024 and beyond. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements, including risks associated with entering into definitive agreements for the transactions described herein; fulfilling the conditions to closing of the transactions described herein, including the receipt of TSX approvals; the business of Ascot; risks related to exploration and potential development of Ascot's projects; business and economic conditions in the mining industry generally; fluctuations in commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; the need for cooperation of government agencies and indigenous groups in the exploration and development of Ascot's properties and the issuance of required permits; the need to obtain additional financing to develop properties and uncertainty as to the availability and terms of future financing; the possibility of delay in exploration or development programs and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; and other risk factors as detailed from time to time in Ascot's filings with Canadian securities regulators, available on Ascot's profile on SEDAR+ at including the Annual Information Form of the Company dated March 23, 2023 in the section entitled "Risk Factors". Forward-looking statements are based on assumptions made with regard to: the estimated costs associated with construction of the Project; the timing of the anticipated start of production at the Project; the ability to maintain throughput and production levels at the PGP mill; the tax rate applicable to the Company; future commodity prices; the grade of mineral resources and mineral reserves; the ability of the Company to convert inferred mineral resources to other categories; the ability of the Company to reduce mining dilution; the ability to reduce capital costs; and exploration plans. Forward-looking statements are based on estimates and opinions of management at the date the statements are made. Although Ascot believes that the expectations reflected in such forward-looking statements and/or information are reasonable, undue reliance should not be placed on forward-looking statements since Ascot can give no assurance that such expectations will prove to be correct. Ascot does not undertake any obligation to update forward-looking statements, other than as required by applicable laws. The forward-looking information contained in this news release is expressly qualified by this cautionary statement.

根據加拿大證券法,本新聞稿中包含的有關未來預期事件的所有陳述和其他信息可能構成前瞻性信息(“前瞻性陳述”)。前瞻性陳述通常使用 “尋求”、“預測”、“相信”、“計劃”、“估計”、“期望”、“目標”、“展望”、“走上正軌” 和 “打算” 等詞語來識別,以及關於某一事件或結果 “可能”、“將”、“可能”、“將” 或 “可能” 發生或實現的陳述以及其他類似的表述。除歷史事實陳述外,此處包含的所有陳述均爲前瞻性陳述,包括有關PGP進展和發展及其相關時機、PGP礦竣工、黃金產量以及管理層對2024年剩餘時間及以後的展望的陳述。這些陳述涉及已知和未知的風險、不確定性和其他因素,可能導致實際結果或事件與此類前瞻性陳述中的預期存在重大差異,包括與就本文所述交易簽訂最終協議相關的風險;滿足本文所述交易的完成條件,包括獲得多倫多證券交易所的批准;阿斯科特的業務;與阿斯科特項目的勘探和潛在開發相關的風險;採礦業的業務和經濟狀況整個工業;大宗商品價格和貨幣匯率的波動;與鑽探結果解釋以及礦牀地質、連續性和品位有關的不確定性;政府機構和土著群體在勘探和開發阿斯科特的房產和發放所需許可證方面進行合作的必要性;開發房產需要獲得額外融資以及未來融資的可得性和條款的不確定性;勘探或開發計劃延遲的可能性以及實現預期計劃里程碑的不確定性;及時獲得許可證和其他政府批准的不確定性;以及阿斯科特向加拿大證券監管機構提交的文件中不時詳述的其他風險因素,可在SEDAR+的Ascot簡介中查閱,包括2023年3月23日的公司年度信息表中的標題爲 “風險因素” 的部分。前瞻性陳述基於以下方面的假設:與項目建設相關的估計成本;項目預計開始生產的時間安排;維持PGP工廠吞吐量和產量水平的能力;適用於公司的稅率;未來大宗商品價格;礦產資源和礦產儲量等級;公司將推斷的礦產資源轉換爲其他類別的能力;公司減少採礦稀釋的能力;減少資本的能力成本;和勘探計劃。前瞻性陳述基於陳述發表之日管理層的估計和意見。儘管阿斯科特認爲此類前瞻性陳述和/或信息中反映的預期是合理的,但不應過分依賴前瞻性陳述,因爲阿斯科特無法保證此類預期會被證明是正確的。除非適用法律要求,否則Ascot不承擔任何更新前瞻性陳述的義務。本警示聲明明確限制了本新聞稿中包含的前瞻性信息。