share_log

Meeka Readying for Gold Development

Meeka Readying for Gold Development

Meeka 爲黃金開發做好準備
sharecafe ·  05/09 19:23

Meeka Metals (ASX:MEK) is aiming to be ready to push the button on it's the development of its Murchison gold project in Western Australia by mid-year.

Meeka Metals(澳大利亞證券交易所股票代碼:MEK)的目標是在年中之前做好在西澳大利亞州默奇森開發黃金項目的準備。

Murchison has a resource of 1.24 million ounces at 3 grams per tonne gold, with over half in the measured and indicated categories.

默奇森的黃金資源爲124萬盎司,按每噸3克計算,其中一半以上屬於計量和指示類別。

It comes after Meeka this week updated the resource for its Turnberry open pit deposit to 690,000oz at 2g/t gold.

在此之前,Meeka本週將其Turnberry露天礦牀的資源更新爲69萬盎司黃金,金價爲2克/噸。

A prefeasibility study released last year defined an initial 9.3-year operation to produce an average 66,000oz per annum of gold.

去年發佈的一項預可行性研究確定了最初的9.3年的運營期,即平均每年生產66,000盎司的黃金。

Using a gold price of A$2750 an ounce, the project would generate pre-tax free cashflow of A$363 million and has a net present value of A$249 million.

按每盎司2750澳元的黃金價格計算,該項目將產生3.63億澳元的稅前自由現金流,淨現值爲2.49億澳元。

At A$3000/oz, free cashflow increases to A$521 million and the NPV grows to A$371 million.

每盎司3000澳元,自由現金流增至5.21億澳元,淨現值增長至3.71億澳元。

"At [the current gold price of] A$3500/oz, you can go ahead and add another A$250 million-odd to that," Meeka managing director Tim Davidson told the RIU Sydney Resources

米卡董事總經理蒂姆·戴維森告訴RIU悉尼資源公司:“按目前的金價每盎司3500澳元,你可以繼續再增加超過2.5億澳元。”

Round-up.

綜述。

Capital costs were forecast at A$137 million in the PFS, based on the development of a 1 million tonne per annum mill at Turnberry.

根據坦貝利每年100萬噸工廠的開發,PFS的資本成本預計爲1.37億澳元。

However, the company is now looking at a refurbishment and restart of its existing 500,000tpa Andy Well project with the potential to expand the mill.

但是,該公司現在正在考慮翻新和重啓其現有的50萬噸/年安迪威爾項目,該項目有可能擴建該工廠。

"We're looking at options to increase the throughput through the plant," Davidson said.

戴維森說:“我們正在研究提高工廠產量的備選方案。”

A definitive feasibility study is due within a couple of weeks.

最終的可行性研究將在幾周內完成。

Davidson said start-up costs were estimated at A$40-45 million.

戴維森說,啓動成本估計爲4000萬至4,500萬澳元。

Meeka is aiming to have final approvals in June and funding in place by July.

Meeka的目標是在6月獲得最終批准,並在7月之前獲得資金。

"We're running a process now and we expect to have the funding in place for development in July," he said.

他說:“我們現在正在啓動一個程序,我們預計將在7月份爲開發提供資金。”

Meeka has a market capitalisation of around A$45 million, even after a 12% rise in its share price yesterday.

儘管昨天股價上漲了12%,但Meeka的市值仍約爲4,500萬澳元。

Davidson said the market was only valuing Meeka's gold inventory at about A$30/oz, compared to recent transactions, which saw ounces changing hands at more than A$200/oz.

戴維森說,市場對Meeka的黃金庫存的估值僅爲每盎司30澳元左右,而最近的交易中,盎司的易手價格超過每盎司200澳元。

"Which we feel gives us lots of room to move higher," he said.

他說:“我們認爲這爲我們提供了很大的向上移動的空間。”