Endeavour Achieves First Gold Pour at Lafigué Mine in Côte D'Ivoire

Endeavour Achieves First Gold Pour at Lafigué Mine in Côte D'Ivoire

恩德能在科特迪瓦的拉菲格礦實現首次黃金傾注
GlobeNewswire ·  07/02 02:00

ENDEAVOUR ACHIEVES FIRST GOLD POUR AT LAFIGUÉ MINE IN CÔTE D'IVOIRE

奮進號在科特迪瓦的拉菲格礦實現了首次淘金

Constructed in only 21 months · Delivered on budget and ahead of schedule · Investment phase completed

僅在 21 個月內建成·按預算提前交付·投資階段完成

HIGHLIGHTS:
  • First gold pour at the Lafigué mine achieved on budget and ahead of schedule, only 21 months after construction launch
  • Commercial production and subsequent ramp-up to nameplate plant capacity of 4.0Mtpa expected to be achieved in Q3-2024
  • Over 17.8Mt of total material moved since Q4-2023 with over 1.8Mt of ore at 1.37g/t totalling over 80koz mined and stockpiled ahead of the processing plant ramp-up
  • Lafigué is expected to produce between 90-110koz of gold at a sector leading AISC of between $900-975/oz in FY-2024, with production increasing to approximately 200koz in FY-2025
  • The Lafigué mine is the fifth project Endeavour has built in West Africa in the last ten years, all of which have been delivered on budget and on or ahead of schedule, in two years or less
亮點:
  • 在施工啓動僅21個月後,拉菲格礦就按預算提前完成了首次淘金
  • 預計在 Q3-2024 中將實現商業化生產,並隨後將銘牌工廠產能提高到每年 400 萬噸
  • 自 Q4-2023 以來,運送的總材料超過1780萬噸,在加工廠擴建之前,總共開採和儲存了超過180萬噸的礦石,總重量超過80koz
  • 預計拉菲格將在該行業領先的 AISC 生產 90-110 千盎司的 FY-2024 黃金,產量在 900-975 美元之間,FY-2025 的產量將增加到大約 200 koz
  • 拉菲格礦是奮進號在過去十年中在西非建造的第五個項目,所有項目均在兩年或更短的時間內按預算按計劃交付

Abidjan, 2 July 2024 – Endeavour Mining plc (LSE:EDV, TSX:EDV, OTCQX:EDVMF) ("Endeavour", the "Group" or the "Company") is pleased to announce that the first gold pour from the Lafigué mine in Côte d'Ivoire was achieved on 28 June 2024, marking the successful delivery of the project construction on budget and a quarter ahead of schedule.

阿比讓,2024年7月2日——奮進礦業公司(倫敦證券交易所:EDV,多倫多證券交易所股票代碼:EDV,OTCQX: EDVMF)(“奮進號”,“集團” 或 “公司”)欣然宣佈,科特迪瓦拉菲格礦的首次淘金已於2024年6月28日實現,這標誌着項目建設按預算成功交付,比計劃提前了一個季度。

Ian Cockerill, CEO, commented "We are proud to have achieved our first gold pour at Lafigué, which, alongside the first gold pour at the Sabodala-Massawa BIOX expansion that we achieved in April, marks the successful completion of the recent phase of investment and growth that we started in Q2-2022. We now begin a new phase of increased free cash flow generation, de-levering and enhanced shareholder returns.

首席執行官伊恩·科克里爾評論道 “我們很自豪能夠在拉菲格實現首次淘金,此外還有薩博達拉-馬薩瓦BIOX的首次淘金 我們在四月份實現的擴張標誌着我們在 Q2-2022 中啓動的最新投資和增長階段的成功完成。現在,我們開始了增加自由現金流、降低槓桿化和提高股東回報率的新階段。

The Lafigué project is the fifth project that we have successfully built in West Africa in the last decade, which is a testament to the strength of our in-house project construction team and is a demonstration of our competitive advantage in West Africa, the world's most prospective and largest gold producing region.

拉菲格項目是我們在過去十年中在西非成功建造的第五個項目,這證明了我們內部項目建設團隊的實力,也表明了我們在西非這個世界上最具前景和最大的黃金生產區的競爭優勢。

Lafigué is an excellent example of our ability to leverage this advantage by self-generating a project pipeline. We discovered Lafigué for a cost of $31 million, equivalent to an industry-low discovery cost of just $12 per ounce of M&I resources. The project was quickly advanced through technical studies and permitting, before construction was launched in Q4-2022, and first gold was delivered only 21 months later for a low capital intensity of approximately $150/oz of M&I resources. In less than eight years we have transformed Lafigué from a discovery to production, creating a cornerstone asset that has the potential to produce over 200koz per year, at an industry leading all-in sustaining cost of approximately $900/oz for at least 13 years, improving the quality of our existing portfolio.

Lafigue'是一個很好的例子,說明我們有能力通過自行生成項目管道來利用這一優勢。我們以3,100萬美元的成本發現了Lafigue,相當於業界較低的發現成本,即每盎司併購資源僅爲12美元。在 Q4-2022 啓動施工之前,該項目通過技術研究和許可迅速取得了進展,僅在 21 個月後才交付了第一批黃金,資本密集度低,約爲 150 美元/盎司的併購資源。在不到八年的時間裏,我們已經將Lafigue從發現轉變爲生產,創造了一種基石資產,該資產有可能每年產量超過200koz,其總維持成本約爲900美元/盎司,爲期至少13年,從而提高了我們現有投資組合的質量。

We believe this level of value creation is repeatable in West Africa, and we have already identified the Assafou deposit on the Tanda-Iguela property in Côte d'Ivoire, where we have delineated a top tier resource and another potential cornerstone asset, which will underpin our next phase of organic growth in a few years time.

我們認爲,這種價值創造水平在西非是可以重複的,而且我們已經在科特迪瓦的Tanda-Iguela地產上確定了Assafou礦牀,我們在那裏劃定了一種頂級資源和另一種潛在的基石資產,這將支撐我們在幾年後實現下一階段的有機增長。

With the current phase of organic growth completed, we are now focused on quickly ramping up our recent development projects to maximise their returns and support our near-term capital allocation priorities of de-levering our balance sheet and enhancing our shareholder returns."

隨着當前階段的有機增長完成,我們現在專注於快速擴大我們最近的開發項目,以最大限度地提高其回報,並支持我們的短期資本配置優先事項,即分期資產負債表和提高股東回報。”

Since the start of wet commissioning on 30 May 2024, approximately 77kt of ore has been processed through the Lafigué processing plant, with all circuits operating in line with expectations. The first gold pour included gold from both the gravity and CIL circuits, and yielded approximately 380 ounces of gold. The Lafigué mine is expected to achieve commercial production and ramp up to its nameplate capacity of 4.0Mtpa in Q3-2024.

自2024年5月30日開始溼式調試以來,拉菲格加工廠已經加工了約77萬噸礦石,所有迴路的運行均符合預期。第一次淘金包括來自重力迴路和 CIL 迴路的黃金,產生了大約 380 盎司的黃金。預計拉菲格礦將實現商業化生產,並在 Q3-2024 中將其銘牌產能提高到每年400萬噸。

Figure 1: First gold pour at the Lafigué mine
Please refer to figure in attached press release

圖 1:拉菲格礦的首次淘金
請參考所附新聞稿中的圖

Figure 2: Paul Day, General Manager at Lafigué with the first gold bar poured at the mine
Please refer to figure in attached press release

圖 2:拉菲格總經理 Paul Day 向礦山澆注了第一根金條
請參考所附新聞稿中的圖

ABOUT THE LAFIGUÉ MINE

關於拉菲格礦山

The Lafigué mine is located towards the northern end of the Birimian aged Oumé-Fetekro greenstone belt, in north-central Côte d'Ivoire, approximately 500km from Abidjan by road. The Lafigué deposit is located in the northeast part of the Fetekro exploration permit, adjacent to existing infrastructure, including sealed paved roads and high voltage grid power. Endeavour has an 80% ownership stake in the Lafigué mine (with 10% owned by the Ivorian Government and 10% owned by SODEMI, a state-owned mining company) and a 100% ownership stake in the remainder of the Fetekro exploration licence.

拉菲格礦位於科特迪瓦中北部的比裏米亞古老的歐美-費特克羅綠巖帶的北端,公路距離阿比讓約500公里。拉菲格礦牀位於 Fetekro 勘探許可證的東北部,毗鄰現有基礎設施,包括封閉的鋪裝道路和高壓電網電力。奮進號擁有拉菲格礦80%的所有權(其中10%由科特迪瓦政府持有,10%由國有礦業公司SODEMI擁有),並擁有Fetekro勘探許可證剩餘部分的100%所有權。

Endeavour began exploration on the Fetekro property in March 2017, following a strategic assessment of its exploration tenements which identified the project as a top priority target. To date, only a limited portion of the Fetekro property has been explored, as the priority has been the delineation of the Lafigué deposit. A maiden Mineral Resource Estimate for the Lafigué deposit was published on 29 October 2018 and subsequently updated on 3 September 2019, 18 August 2020 and 15 May 2022. A Preliminary Economic Assessment ("PEA") was published on 18 August 2020 and a Preliminary Feasibility Study ("PFS") was completed with the effective date of 31 December 2020.

Endeavor於2017年3月開始對Fetekro地產進行勘探,此前對其勘探礦權進行了戰略評估,該評估將該項目確定爲重中之重。迄今爲止,僅對Fetekro地產的有限部分進行了勘探,因爲當務之急是劃定拉菲格礦牀。拉菲格礦牀的首次礦產資源估算於2018年10月29日發佈,隨後於2019年9月3日、2020年8月18日和2022年5月15日進行了更新。初步經濟評估(“PEA”)於2020年8月18日發佈,初步可行性研究(“PFS”)已完成,生效日期爲2020年12月31日。

Construction of the Lafigué project in Côte d'Ivoire was launched in Q4-2022, following the completion of a Definitive Feasibility Study ("DFS") which confirmed Lafigué's potential to be a cornerstone asset for Endeavour. The 2022 DFS contemplates a 12.8 year LOM with average annual production of 203koz at a low AISC of $871/oz, with an initial capital cost of $448 million. The project DFS displayed robust economics at an $1,800/oz gold price assumption including an after-tax NPV5% of $870m and an after-tax IRR of 33%. For FY-2024, Lafigué is expected to produce between 90-110koz at an AISC of between $900-975/oz.

在完成最終可行性研究(“DFS”)之後,科特迪瓦拉菲格項目的建設於 Q4-2022 啓動,該研究證實了拉菲格有可能成爲奮進號的基石資產。2022年DFS計劃使用12.8年的LOM,平均年產量爲203koz,AISC爲8.71美元/盎司,初始資本成本爲4.48億美元。DFS項目以每盎司1,800美元的金價假設顯示出強勁的經濟效益,包括稅後淨現值5% 8.7億美元,稅後內部收益率爲33%。對於 FY-2024,Lafigue的產量預計在90-110koz之間,AISC在900-975美元/盎司之間。

As at 31 December 2023, Proven and Probable reserves totalled 49.8Mt at 1.69 g/t containing 2.7Moz of gold and Measured and Indicated resources (inclusive of reserves) totalled 46.2Mt at 2.04 g/t containing 3.0Moz of gold.

截至2023年12月31日,探明和可能的儲量總計爲49.8萬噸,重量爲1.69克/噸,含有2.7Moz的黃金,測定和指示的資源(包括儲量)總計爲46.2萬噸,重量爲2.04克/噸,含有3.0Moz的黃金。

Given the strong exploration potential, Endeavour is targeting the discovery of 1.2 – 1.8Moz of Indicated resources across the Lafigué mining permit and the wider Fetekro exploration permit area over the 2021 to 2025 period at a discovery cost of $14/oz. To date 0.6Moz, or 50% of the lower end of the target, has been discovered.

鑑於強大的勘探潛力,奮進號的目標是在2021年至2025年期間,在拉菲格採礦許可證和更廣泛的Fetekro勘探許可區域內發現1.2 — 1.8Moz的指示資源,發現成本爲14美元/盎司。迄今爲止,已經發現了0.6Moz,佔目標下限的50%。

QUALIFIED PERSONS

合格人員

Mark Morcombe, COO of Endeavour Mining plc., a Fellow of the Australasian Institute of Mining and Metallurgy, is a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and has reviewed and approved the technical information in this news release.

澳大利亞礦業和冶金學會會員、奮進礦業公司首席運營官馬克·莫爾科姆是《國家儀器43-101——礦業項目披露標準》(“NI 43-101”)定義的 “合格人士”,他已經審查並批准了本新聞稿中的技術信息。

CONTACT INFORMATION

聯繫信息

Jack Garman
Vice President, Investor Relations
+44 203 011 2723
jack.garman@endeavourmining.com
Brunswick Group LLP in London
Carole Cable, Partner
+44 207 404 5959
ccable@brunswickgroup.com
傑克·加曼
投資者關係副總裁
+44 203 011 2723
jack.garman@endeavourmining.com
倫敦不倫瑞克集團律師事務所
Carole Cable,合夥人
+44 207 404 5959
ccable@brunswickgroup.com

ABOUT ENDEAVOUR MINING PLC

關於奮進礦業 PLC

Endeavour Mining is one of the world's senior gold producers and the largest in West Africa, with operating assets across Senegal, Cote d'Ivoire and Burkina Faso and a strong portfolio of advanced development projects and exploration assets in the highly prospective Birimian Greenstone Belt across West Africa.

Endeavor Mining是全球資深的黃金生產商之一,也是西非最大的黃金生產商,其運營資產遍佈塞內加爾、科特迪瓦和布基納法索,在西非極具前景的比裏米亞綠石帶擁有強大的先進開發項目和勘探資產組合。

A member of the World Gold Council, Endeavour is committed to the principles of responsible mining and delivering sustainable value to its employees, stakeholders and the communities where it operates. Endeavour is listed on the London and Toronto Stock Exchanges, under the symbol EDV.

作爲世界黃金協會的成員,Endeavor致力於奉行負責任採礦的原則,爲員工、利益相關者和運營所在社區提供可持續的價值。奮進號在倫敦和多倫多證券交易所上市,股票代碼爲EDV。

For more information, please visit .

欲了解更多信息,請訪問

CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION

關於前瞻性信息的警示性說明

This news release contains "forward-looking statements" within the meaning of applicable securities laws. All statements, other than statements of historical fact, are "forward-looking statements". Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "expected", "budgeted", "forecasts", and "anticipates".

本新聞稿包含適用證券法所指的 “前瞻性陳述”。除歷史事實陳述外,所有陳述均爲 “前瞻性陳述”。通常,這些前瞻性陳述可以通過使用前瞻性術語來識別,例如 “預期”、“預期”、“預算”、“預測” 和 “預期”。

Forward-looking statements, while based on management's best estimates and assumptions, are subject to risks and uncertainties that may cause actual results to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to the successful integration of acquisitions; risks related to international operations; risks related to general economic conditions and credit availability, actual results of current exploration activities, unanticipated reclamation expenses; changes in project parameters as plans continue to be refined; fluctuations in prices of metals including gold; fluctuations in foreign currency exchange rates, increases in market prices of mining consumables, possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes, title disputes, claims and limitations on insurance coverage and other risks of the mining industry; delays in the completion of development or construction activities, changes in national and local government regulation of mining operations, tax rules and regulations, and political and economic developments in countries in which Endeavour operates. Although Endeavour has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Please refer to Endeavour's most recent Annual Information Form filed under its profile at for further information respecting the risks affecting Endeavour and its business.

前瞻性陳述雖然基於管理層的最佳估計和假設,但存在風險和不確定性,可能導致實際結果與此類前瞻性陳述所表達或暗示的結果存在重大差異,包括但不限於:與成功整合收購相關的風險;與國際業務相關的風險;與總體經濟狀況和信貸可用性相關的風險、當前勘探活動的實際結果、意想不到的開採費用;項目變更計劃中的參數不斷完善;包括黃金在內的金屬價格的波動;外幣匯率的波動,採礦消耗品市場價格的上漲,礦石儲量、品位或回收率的可能變化;工廠、設備或工藝未能按預期運行;事故、勞資糾紛、所有權糾紛、索賠和保險範圍限制以及採礦業的其他風險;開發或建築活動延遲完成,國家和地方政府監管的變化Endeavor運營所在國家的採礦業務、稅收規則和法規以及政治和經濟發展。儘管Endeavor試圖確定可能導致實際業績與前瞻性陳述中包含的結果存在重大差異的重要因素,但可能還有其他因素導致結果與預期、估計或預期不符。無法保證此類陳述會被證明是準確的,因爲實際結果和未來事件可能與此類陳述中的預期存在重大差異。因此,讀者不應過分依賴前瞻性陳述。有關影響奮進號及其業務的風險的更多信息,請參閱Endeavor在其簡介下提交的最新年度信息表。

Attachment

附件

  • 240702 - NR - Lafigue First Gold
  • 240702-NR-Lafigue First Gold

声明:本內容僅用作提供資訊及教育之目的,不構成對任何特定投資或投資策略的推薦或認可。 更多信息
    搶先評論