NexGen Energy Provides Rook I Update, Costs $645 Million More Than Expected

NexGen Energy Provides Rook I Update, Costs $645 Million More Than Expected

nexgen energy提供rook I的更新,成本比預期高64500萬美元。
Benzinga ·  08/02 09:59

NexGen Energy (NYSE:NXE) has announced that construction costs for its Rook I uranium project in Saskatchewan have soared nearly 70% above the previous estimate from 2021.

NexGen Energy(紐約證券交易所代碼:NXE)宣佈,自2021年以來,其位於薩斯喀徹溫省的Rook I鈾項目的建設成本已比先前的估計高出近70%。

The updated capital cost now stands at $1.6 billion, up from around $950 million, showcasing the challenge of domestic uranium production.

更新後的資本成本目前爲16億美元,高於約9.5億美元,這表明了國內鈾生產面臨的挑戰。

"The updated capital cost presents an all-encompassing spend to bring the Rook I project into production based on robust, proven mining and construction methodologies, with a payback period of 12 months," said CEO Leigh Curyer.

首席執行官利·庫里爾表示:“最新的資本成本爲Rook I項目提供了無所不包的支出,旨在基於穩健、成熟的採礦和施工方法將Rook I項目投入生產,投資回收期爲12個月。”

Operating costs are projected to nearly double to $10 per pound of uranium oxide (U3O8), compared to $5.4 per pound in the earlier study. Consequently, the project's after-tax net present value has fallen from $5.55 billion to $4.54 billion, and the internal rate of return has dropped from 79% to 45%.

預計運營成本將增加近一倍,達到每磅氧化鈾(U3O8)10美元,而先前研究的運營成本爲每磅5.4美元。因此,該項目的稅後淨現值已從55.5億美元下降至45.4億美元,內部回報率從79%下降到45%。

Now Read: EXCLUSIVE – Seabed Mining Company Execs See Industry Developing Regardless Of UN Authority Vote

立即閱讀:獨家——無論聯合國機構如何投票,海底採礦公司的高管都認爲行業正在發展

Regardless of the cost hike, Alexander Pearce, a mining analyst at BMO Capital Markets, remains optimistic.

無論成本如何上漲,BMO Capital Markets的礦業分析師亞歷山大·皮爾斯都保持樂觀。

"Despite an increase in cash cost to about $10 per lb., the asset would remain one of the largest and lowest cost uranium mines globally," he said, per a Bloomberg report.

彭博社報道說:“儘管現金成本增加到每磅約10美元,但該資產仍將是全球最大和成本最低的鈾礦之一。”

The Rook I project is in Saskatchewan's Athabasca Basin, known for its rich uranium deposits. It aims to produce 21.7 million pounds of U3O8 annually and has a potential production capacity of up to 30 million pounds. The site holds 3.7 million measured and indicated tons with an average grade of 3.1% U3O8.

Rook I項目位於薩斯喀徹溫省的阿薩巴斯卡盆地,該盆地以其豐富的鈾礦牀而聞名。它的目標是每年生產2170萬磅的八氧化三鈾,潛在的生產能力高達3000萬磅。該場地擁有370萬噸測定和標示的噸位,八氧化三鈾的平均品位爲3.1%。

The new cost estimates reflect $220 million attributed to price inflation and $425 million from enhanced engineering and procurement activities since March 2021. NexGen is advancing its project engineering, now 45% complete, up from 18% during the feasibility study.

新的成本估算反映了自2021年3月以來因價格上漲而產生的2.2億美元和來自加強工程和採購活動的4.25億美元。NexGen正在推進其項目工程,現已完成45%,高於可行性研究期間的18%。

The company's strategy includes incorporating underground tailings management to reduce environmental impact and lower closure costs to an estimated $50 million, significantly less than other uranium mines in Canada. Rook I's unique design integrates progressive reclamation, reducing future liabilities and ensuring a safer, more efficient operation.

該公司的戰略包括整合地下尾礦管理以減少對環境的影響,並將關閉成本降低至約5000萬美元,大大低於加拿大其他鈾礦。Rook I 的獨特設計融合了漸進式回收、減少了未來的負債並確保了更安全、更高效的運營。

The project has already received provincial environmental approval and is awaiting the completion of the federal review process. NexGen is looking to begin construction soon after receiving the green light from federal authorities.

該項目已獲得省級環境批准,正在等待聯邦審查程序的完成。NexGen希望在獲得聯邦當局的批准後不久開始施工。

Now Read:

現在閱讀:

  • Uranium Prices Surge To 16-Year Highs Due To Supply Uncertainties, Rising Demand For AI Data Centers
  • 由於供應的不確定性,對人工智能數據中心的需求增加,鈾價格飆升至16年高點

Benzinga Mining is the bridge between mining companies and retail investors. Reach out to licensing@benzinga.com to get started!

本辛加礦業是礦業公司和散戶投資者之間的橋樑。聯繫 licensing@benzinga.com 開始吧!

Image: Shutterstock

圖片:Shutterstock

声明:本內容僅用作提供資訊及教育之目的,不構成對任何特定投資或投資策略的推薦或認可。 更多信息
    搶先評論