Ivanhoe Electric On-Track to Deliver Santa Cruz Copper Project Preliminary Feasibility Study in Q2 2025

Ivanhoe Electric On-Track to Deliver Santa Cruz Copper Project Preliminary Feasibility Study in Q2 2025

易方達電氣計劃在2025年第二季度發佈聖克魯斯銅項目初步可行性研究報告
newsfile ·  09/16 07:00

Ivanhoe Electric Will Use the Preliminary Feasibility Study to Pursue Long-term Project Financing

艾凡豪電氣將使用初步可行性研究來尋求長期項目融資。

Metallurgical Results from Ongoing Testwork Show High Copper Recoveries and Recoverable Precious Metals

正在進行的冶金試驗結果顯示出高銅回收率和可回收的貴金屬。

Santa Cruz Copper Project Received General Plan Amendment Approval from the City of Casa Grande and is Preparing Key Permit Applications for Submittal in H1 2025

聖克魯斯銅礦項目已獲得Casa Grande市的總體規劃修改批准,並正在準備在2025年上半年提交的重要許可申請。

Recent Infill Drilling Intersects High-Grade Copper Mineralization at the Santa Cruz Deposit, Including 99 Meters Grading 2.39% Copper

最近的補充鑽探在聖克魯斯礦牀處遇到了高品位的銅礦化,包括99米2.39%的銅。

Phoenix, Arizona--(Newsfile Corp. - September 16, 2024) - Ivanhoe Electric Inc. (NYSE American: IE) (TSX: IE) ("Ivanhoe Electric") Executive Chairman Robert Friedland and President and Chief Executive Officer Taylor Melvin are pleased to provide an update on the ongoing progress at the Company's Santa Cruz Copper Project in Arizona.

亞利桑那州鳳凰城-(新聞資料公司-2024年9月16日)-艾凡豪電氣公司(紐交所美國:IE)(tsx:IE)("艾凡豪電氣")執行主席羅伯特·弗裏德蘭和總裁兼首席執行官泰勒·梅爾文高興地宣佈了該公司位於亞利桑那州聖克魯斯銅礦項目的持續進展最新情況。

Mr. Melvin commented: "We are encouraged by the ongoing progress at our Santa Cruz Copper Project. Our Preliminary Feasibility Study remains on track and on budget for completion in the second quarter of 2025. We are pleased to have received approval by the City of Casa Grande for our General Plan Amendment, and we look forward to submitting key permit applications in early 2025."

梅爾文先生評論說:「我們對聖克魯斯銅礦項目的持續進展感到鼓舞。我們的初步可行性研究仍然按計劃進行,預計將於2025年第二季度完成,我們很高興獲得Casa Grande市對我們的總體規劃修改的批准,並期待在2025年初提交關鍵許可申請。」

The Santa Cruz Copper Project Preliminary Feasibility Study will define an underground mining operation supported by a mine plan and an updated mineral resource and reserve estimate

聖克魯斯銅礦項目的初步可行性研究將定義一個受地下采礦運營支持的礦山計劃和更新的礦產資源和儲量估計。

Our Preliminary Feasibility Study ("PFS" or the "Study") is being conducted under the standards of U.S. Regulation S-K 1300. The Study will include a detailed mine plan that will be supported by an updated mineral resource and reserve estimate resulting from our infill drilling and testwork activities. The Study will be used by Ivanhoe Electric to make an investment decision and pursue long-term project financing.

我們的初步可行性研究("PFS"或"研究")是根據美國S-k 1300條款進行的。該研究將包括一個詳細的礦山計劃,該計劃將由我們的補充鑽探和試驗工作活動得出的更新的礦產資源和儲量估計來支持。該研究將被艾凡豪電氣用來做出投資決策,並尋求長期項目融資。

The Santa Cruz Copper Project Preliminary Feasibility Study is now 50% complete, with several significant milestones achieved, and on track for completion in Q2 2025

聖克魯斯銅項目初步可行性研究已完成50%,達到了幾個重要里程碑,並計劃在2025年第二季度完成。

  • 120,000 meters of new drilling completed since December 2022 Mineral Resource Estimate ("MRE") to support Preliminary Feasibility Study
  • 自2022年12月礦產資源評估(「MRE」)以來,已完成了12萬米的新鑽探,以支持初步可行性研究。
  • Significant advancements in metallurgy, mine engineering, processing, tailings trade-off studies, and mine access planning
  • 冶金學、礦山工程、處理、尾礦權衡研究和礦山進入規劃方面取得了重大進展。
  • Studies focused on process design and optimization, power, water management, and environmental/permitting are ongoing
  • 正在進行的研究集中在工藝設計和優化、電力、水管理和環境/許可方面。

Metallurgical studies, conducted by Blue Coast Research Ltd. of British Columbia, Canada, showing high copper recoveries and presence of recoverable precious metal by-products

由加拿大不列顛哥倫比亞省的Blue Coast Research Ltd.進行的冶金研究顯示出高銅回收率和可回收貴金屬副產品的存在。

  • Up to 98% recoveries of acid-soluble copper for production of copper cathode

  • Up to 92% recoveries of floatable copper to produce high-grade copper concentrate

  • 可生產酸溶銅的回收率高達98%,用於生產銅陽極。

  • 可浮選銅的回收率高達92%,用於生產高品位的銅精礦。

  • Expected to produce a high-grade copper concentrate grading up to 51% copper by weight and high-purity copper cathode meeting London Metal Exchange Grade A standards
  • 預計將生產高品位的銅精礦,銅含量高達51%(以重量計),並符合倫敦金屬交易所A級標準的高純銅陽極。
  • Identified recoverable precious metal by-products expected to average 2.0 g/t gold and 145.9 g/t silver in the high-grade copper concentrate
  • 預計高品位銅精礦中可回收貴金屬副產物平均含金量爲2.0g/t,銀含量爲145.9g/t。

Permitting milestone achieved and major permits in preparation for submittal

達到許可里程碑,併爲提交準備了重要許可證。

In June 2024, Ivanhoe Electric received approval from the City of Casa Grande for the Major General Plan Amendment for the Santa Cruz Copper Project, a major milestone for the Project. The City of Casa Grande Council unanimously approved amending nearly 3,000 acres of land use designation from "Neighborhoods" to "Manufacturing/Industry." Key permitting applications are being prepared for submittal in the first half of 2025 in connection with the PFS.

2024年6月,Ivanhoe Electric獲得Casa Grande市對聖克魯斯銅礦項目的大型總體規劃修正的批准,這是該項目的重要里程碑。Casa Grande市議會一致同意將近3000英畝的土地用途規劃從「居住區」修改爲「製造/行業」。關鍵的許可申請正在爲2025年上半年的提交而準備,以配合前期評估報告。

Infill drilling at Santa Cruz Deposit demonstrates presence of high-grade domains within the Mineral Resource Estimate

聖克魯斯礦牀的補充鑽探顯示出高品位區域存在於礦產資源估算中。

The development drill program at the Santa Cruz Copper Project included drill holes completed to support metallurgical studies, resource definition and infill, hydrogeology, and geotechnical studies, all of which support the PFS. Infill drill holes were completed to support the conversion of resources from the Inferred category to the higher-confidence Indicated category.

聖克魯斯銅礦項目的開發鑽探計劃包括完成以支持冶金研究、資源定義和補充鑽探、水文地質學和岩土工程學研究爲目的的鑽孔,這些鑽孔都是爲了支持前期評估報告。補充鑽孔完成以支持將資源從推測範疇轉化爲更可靠的指控範疇。

Infill drill hole SCC-234, completed in the Santa Cruz Deposit, intersected higher than expected copper grades, with mineralization present as strong chalcocite, atacamite, and chrysocolla in bedrock Oracle Granite and porphyry as disseminations, veins, and fracture fillings.

在聖克魯斯礦牀中完成的補充鑽孔SCC-234,在岩石群Oracle Granite和透晶巖中發現了高於預期的銅品位,礦化物存在於岩石中作爲強硫化銅礦、阿塔卡礦和赤銅礦以礦脈和裂隙填充形式存在。

Assays from the recently completed development drill program continue to be received and will be added to an updated MRE to support the PFS delivery in Q2 2025. Recent intercepts include:

最近完成的開發鑽探計劃中的化驗結果仍在陸續接收,並將被添加到更新的礦產資源評估中,以支持2025年第二季度的前期評估報告交付。最近的截獲包括:

  • 99.4 meters @ 2.39% total copper from 738.0 meters, including 46.1 meters @ 3.99% total copper from 755.9 meters (Hole SCC-234)
  • 738.0米處開始,總銅含量爲2.39%,其中755.9米處的總銅含量爲3.99%(鑽孔SCC-234),全長99.4米。
  • 140.1 meters @ 1.56% total copper from 753.4 meters, including 29.0 meters @ 2.92% total copper from 799.0 meters (Hole SCC-228)
  • 從753.4米處深度爲140.1米,總銅含量爲1.56%,其中從799.0米處深度爲29.0米,總銅含量爲2.92%(SCC-228孔)
  • 101.9 meters @ 1.65% total copper from 678.1 meters, including 17.6 meters @ 2.37% total copper from 702.7 meters (Hole SCC-232)
  • 從678.1米處深度爲101.9米,總銅含量爲1.65%,其中從702.7米處深度爲17.6米,總銅含量爲2.37%(SCC-232孔)
  • 70.2 meters @ 1.44% total copper from 551.0 meters, and 115.8 meters @ 1.12% total copper from 630.2 meters (Hole SCC-219A)
  • 從551.0米處深度爲70.2米,總銅含量爲1.44%,從630.2米處深度爲115.8米,總銅含量爲1.12%(SCC-219A孔)

See Figure 1 below for drill hole locations.

請參見下面的圖1,了解鑽孔位置。

Highlighted drill intercepts not previously disclosed from the Santa Cruz Copper Project (refer to the Santa Cruz Drill Results page on Ivanhoe Electric's website for further details of all reported drill holes).

來自聖克魯茲銅項目的未公開穿透力突出部分(有關所有報告的鑽孔的詳細信息,請參閱Ivanhoe Electric公司網站上的聖克魯茲鑽孔結果頁面)。

DRILL HOLE LOCATION

FROM
(M)

TO
(M)

INTERVAL LENGTH
(M)

TOTAL COPPER
(%)

TOTAL SOLUBLE COPPER
(%)

SCC-210 Santa Cruz 594.97 650.00 55.03 1.05 1.01
AND 656.00 705.00 49.00 1.36 1.12
SCC-211 Santa Cruz 552.00 584.00 32.00 1.34 1.24
INCLUDING 552.00 568.00 16.00 1.68 1.63
SCC-212 Santa Cruz 615.00 640.00 25.00 1.19 1.02
AND 667.96 698.46 30.50 1.42 1.35
INCLUDING 675.56 698.46 22.90 1.54 1.46
INCLUDING 675.56 692.00 16.44 1.73 1.65
AND 707.21 748.15 40.94 1.10 1.06
INCLUDING 707.21 726.95 19.74 1.41 1.34
AND 753.49 808.00 54.51 1.17 1.15
SCC-215 Santa Cruz 598.46 630.89 32.43 1.38 1.32
AND 745.00 794.20 49.20 1.18 0.69
INCLUDING 750.93 772.00 21.07 1.57 1.17
AND 802.00 857.00 55.00 0.86 0.07
SCC-219A Santa Cruz 551.00 621.22 70.22 1.44 1.34
AND 630.17 746.00 115.83 1.12 0.82
SCC-221 Santa Cruz 844.91 965.00 120.09 1.34 1.25
INCLUDING 870.00 922.31 52.31 1.81 1.88
SCC-223 Santa Cruz 421.00 450.00 29.00 1.59 1.36
SCC-225A Santa Cruz 479.00 519.00 40.00 2.00 1.91
INCLUDING 479.00 509.00 30.00 2.42 2.33
INCLUDING 482.00 488.87 6.87 4.23 4.17
SCC-228 Santa Cruz 616.62 702.00 85.38 1.21 1.17
INCLUDING 638.85 657.40 18.55 1.97 1.86
AND 753.39 893.52 140.13 1.56 0.18
INCLUDING 799.00 828.00 29.00 2.92 0.37
SCC-229 Santa Cruz 623.00 701.00 78.00 1.47 1.15
INCLUDING 623.00 655.00 32.00 2.37 2.30
INCLUDING 629.00 645.00 16.00 2.86 2.78
SCC-232 Santa Cruz 678.09 780.00 101.91 1.65 1.68
INCLUDING 678.09 758.00 79.91 1.79 1.83
INCLUDING 702.69 720.25 17.56 2.37 2.41
AND 788.00 838.30 50.30 1.51 1.49
INCLUDING 788.00 825.09 37.09 1.74 1.72
SCC-234 Santa Cruz 691.08 731.98 40.90 1.59 1.58
INCLUDING 691.08 730.04 38.96 1.63 1.62
AND 738.00 837.36 99.36 2.39 2.36
INCLUDING 738.00 814.00 76.00 2.92 2.86
INCLUDING 755.91 802.00 46.09 3.99 3.93
鑽探孔 地點


(M)

致:
(M)

間隔長度
(M)

總銅
(%)

總可溶銅
(%)

SCC-210 Santa Cruz 594.97 650.00 55.03 1.05 1.01
656.00 705.00 49.00 1.36 1.12
SCC-211 Santa Cruz 552.00 584.00 32.00 1.34 1.24
包括 552.00 568.00 16.00 1.68 1.63
SCC-212 Santa Cruz 615.00 640.00 25.00 1.19 1.02
667.96 698.46 30.50 1.42 每股稀釋1.35美元
包括 675.56 698.46 22.90 1.54 1.46
包括 675.56 692.00 16.44 1.73 1.65
707.21 748.15 40.94 1.10 1.06
包括 707.21 726.95 19.74 1.41 1.34
753.49 808.00 54.51 1.17 1.15
SCC-215 Santa Cruz 598.46 630.89 32.43 1.38 1.32
745.00 794.20 49.2 1.18 0.69
包括 750.93 772.00 21.07 1.57 1.17
802.00 857.00 55.00 0.86 0.07
SCC-219A Santa Cruz 551.00 621.22 70.22 1.44 1.34
630.17 746.00 115.83 1.12 0.82
SCC-221 Santa Cruz 844.91 965.00 120.09 1.34 根據公司的固定費用覆蓋率,利率爲1.25% 至 1.75%每年,或者(b)有一個「備選主板利率」,並可減少至0.75%每年,取決於公司的固定費用覆蓋率。截至2021年7月3日,公司的基於LIBOR的利率爲% (對於$),公司的主板基準利率爲% (對於$)。根據未取出的貸款利率,每月應支付承諾費,利率爲%每年。根據與摩根大通銀行(「貸款協議」)的信貸協議的條款,現金收據將被存入鎖匣中,並由公司自行決定,除非處於「現金控制期」,在此期間,現金收據將用於減少貸款協議下的應付金額。現金控制期在事件違約或可用餘額連續三個工作日低於$時觸發,並將繼續到先前的連續天數中存在任何違約事件且多餘的可用餘額始終大於$(這樣的觸發器根據公司的循環承諾進行調整)。此外,如果依據信貸協議所定義的「額外可用餘額」小於$,則公司應維持最低固定費用覆蓋率爲1.0至1.0 (觸發器根據公司的循環承諾進行調整)。截至2021年7月3日,公司的可用餘額爲$25,764。信貸協議要求我們在判斷任何應支付股息或進行任何普通股分配時獲得摩根大通銀行的事先書面同意。信貸設施於2022年12月16日到期。
包括 870.00 922.31 52.31 1.81 1.88
SCC-223 Santa Cruz 421.00 450.00 29.00 1.59 1.36
SCC-225A Santa Cruz 479.00 519.00 40.00 2.00 1.91
包括 479.00 509.00 30.00 2.42 2.33
包括 A23-008 488.87 6.87 4.23 4.17
SCC-228 Santa Cruz 616.62 702.00 85.38 1.21 1.17
包括 638.85 657.40 18.55 1.97 1.86
753.39 893.52 140.13 1.56 0.18
包括 817.00 Elevation 29.00 2.92 0.37
SCC-229 Santa Cruz 623.00 701.00 78.00 1.47 1.15
包括 623.00 655.00 32.00 2.30
包括 629.00 645.00 16.00 2.86 2.78
SCC-232 Santa Cruz 678.09 780.00 101.91 1.65 1.68
包括 678.09 758.00 79.91 1.79 1.83
包括 702.69 720.25 17.56 2.41
788.00 838.30 50.3 1.51 1.49
包括 788.00 825.09 37.09 1.74 1.72
SCC-234 Santa Cruz 691.08 731.98 40.90 1.59 1.58
包括 691.08 730.04 38.96 1.63 1.62
738.00 837.36 99.36 2.39 2.36
包括 738.00 814.00 76.00 2.92 2.86
包括 755.91 802.00 46.09 3.99 3.93

*Total Soluble Copper is the calculated summation of all soluble copper analyses derived from the sequential copper analysis suite.
*Reported intervals at the Santa Cruz Deposit are calculated at a cut-off grade of 0.70% total copper.
*Reported intervals at the East Ridge Deposit are calculated at a cut-off grade of 0.90% total copper.
*Results are derived from diamond core intervals and may not be true widths but are believed to be representative of actual drill thicknesses.
†Some intercepts include assay gaps due to removed core used for various technical studies, these assay gaps have been treated as null values during intercept calculation, average core removed from these intervals is less than 1.5%
*Some rounding errors may occur.

*可溶性銅總數是從連續銅分析套件中得出的所有可溶性銅分析的累加計算結果。
*聖克魯斯礦牀報告的間隔是以總銅含量0.70%的切割品位計算的。
*東嶺礦牀報告的間隔是以總銅含量0.90%的切割品位計算的。
*結果來自金剛石芯樣間隙,並非真實寬度,但被視爲實際鑽頭厚度的代表。
†部分攔截涵蓋了由於用於各種技術研究而移除的岩心的化驗間隙,這些化驗間隙在攔截計算過程中被視爲空值,這些間隙中移除的岩心平均小於1.5%。
*可能會出現一些四捨五入誤差。

Qualified Persons

合格人員

Disclosures of a scientific or technical nature included in this news release, including the sampling, analytical and technical data underlying the information, have been reviewed, verified, and approved by Glen Kuntz, P.Geo., who is a Qualified Person as defined by Regulation S-K, Subpart 1300 promulgated by the U.S. Securities and Exchange Commission and by Canadian National Instrument 43-101. Mr. Kuntz is an employee of Ivanhoe Electric Inc.

本新聞稿中包含的科學或技術性披露,包括基礎信息所採集的採樣、分析和技術數據,已由Glen Kuntz P.Geo審核、核實並批准。Glen Kuntz P.Geo按照美國證券交易委員會制定的Regulation S-k,Subpart 1300和加拿大43-101號國家儀器定義的「合格人士」的標準進行,是Ivanhoe Electric Inc.的僱員。

Ivanhoe Electric had prepared an independent technical report summary for the Santa Cruz Project prepared under SEC Regulation S-K, Subpart 1300 and an independent technical report prepared under Canadian National Instrument 43-101. The reports are available on the company's website, on EDGAR and on the company's SEDAR profile:

Ivanhoe Electric已經根據SEC 1300法規下的子條例和根據加拿大43-101國家儀器準備了聖克魯斯項目的獨立技術報告摘要。這些報告可以在公司網站、EDGAR和公司的SEDAR資料中找到:

  • "Mineral Resource Estimate Update and S-K 1300 Technical Report Summary for the Santa Cruz, Texaco, and East Ridge Deposits, Arizona, USA," authored by Nordmin Engineering Ltd. ("Nordmin") and Met Engineering LLC ("Met Engineering"). Current to December 31, 2022, and dated February 14, 2023.
  • 「亞利桑那州聖克魯斯、特克薩科和東嶺礦牀的礦產資源估算更新和S-k 1300法規技術報告摘要」,由Nordmin工程有限公司(「Nordmin」)和Met Engineering LLC(「Met Engineering」)編寫。截止日期爲2022年12月31日,日期爲2023年2月14日。
  • "Mineral Resource Estimate Update and NI 43-101 Technical Report for The Santa Cruz, Texaco, and East Ridge Deposits, Arizona, USA," prepared by Nordmin and Met Engineering with an effective date of December 31, 2022, and an issue date of March 14, 2023.
  • 「亞利桑那州聖克魯斯、特克薩科和東嶺礦牀的礦產資源估算更新和NI 43-101技術報告」,由Nordmin和Met Engineering準備,截止日期爲2022年12月31日,發佈日期爲2023年3月14日。

The technical report summary and technical report include relevant information regarding the assumptions, parameters and methods of the mineral resource estimates on the Santa Cruz Project, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release.

技術報告摘要和技術報告包括關於Santa Cruz項目的礦產資源估算的假設、參數和方法的相關信息,以及有關數據驗證、勘探程序和其他與本新聞發佈包含的科學和技術披露相關的事項。

About Ivanhoe Electric

關於Ivanhoe Electric

We are a U.S. company that combines advanced mineral exploration technologies with electric metals exploration projects predominantly located in the United States. We use our accurate and powerful Typhoon geophysical surveying system, together with advanced data analytics provided by our subsidiary, Computational Geosciences Inc., to accelerate and de-risk the mineral exploration process as we seek to discover new deposits of critical metals that may otherwise be undetectable by traditional exploration technologies. We believe the United States is significantly underexplored and has the potential to yield major new discoveries of critical metals. Our mineral exploration efforts focus on copper as well as other metals including nickel, vanadium, cobalt, platinum group elements, gold and silver. Through the advancement of our portfolio of electric metals exploration projects, headlined by the Santa Cruz Copper Project in Arizona and the Tintic Copper-Gold Project in Utah, as well as other exploration projects in the United States, we intend to support United States supply chain independence by finding and delivering the critical metals necessary for the electrification of the economy. We also operate a 50/50 joint venture with Saudi Arabian Mining Company Ma'aden to explore for minerals on ~48,500 km2 of underexplored Arabian Shield in the Kingdom of Saudi Arabia. Website: .

我們是一家美國公司,結合先進的礦產勘探技術和主要位於美國的電化學金屬勘探項目。我們使用準確而強大的颱風地球物理勘測系統,以及我們子公司Computational Geosciences Inc.提供的先進數據分析,加速並降低了礦產勘探過程中的風險,力圖發現新的地下資源,這些地下資源可能通過傳統勘探技術無法探測到。我們認爲美國的勘探程度嚴重不足,有潛力發現重要的地下資源。我們的礦產勘探工作重點關注銅以及其他金屬,包括鎳、釩、鈷、鉑族元素、黃金和白銀。通過推動我們的電化學金屬勘探項目組合,重點是亞利桑那州的Santa Cruz銅項目和猶他州的Tintic銅金項目,以及美國其他的勘探項目,我們打算通過尋找並提供經濟電化學金屬來支持美國的供應鏈獨立性。我們還與沙特阿拉伯礦業公司Ma'aden合資50/50,在沙特阿拉伯王國的約48,500平方公里的未充分勘探的阿拉伯盾進行礦產勘探。網站:

Contact Information

聯繫信息

Mike Patterson
Vice President, Investor Relations and Business Development
Email: mike@ivnelectric.com
Phone: 1-480-601-7878

邁克·帕特森
副總裁,投資者關係和業務拓展
郵箱: mike@ivnelectric.com
電話: 1-480-601-7878

Follow us on X

在X上關注我們

Ivanhoe Electric's Executive Chairman Robert Friedland: @robert_ivanhoe

Ivanhoe Electric的執行主席羅伯特·弗裏德蘭德(Robert Friedland):@robert_ivanhoe

Ivanhoe Electric: @ivanhoeelectric

Ivanhoe Electric:@ivanhoeelectric

Ivanhoe Electric's investor relations website located at should be considered Ivanhoe Electric's recognized distribution channel for purposes of the Securities and Exchange Commission's Regulation FD.

Ivanhoe Electric的投資者關係網站位於,應視爲Ivanhoe Electric的公認的分銷渠道,用於美國證券交易委員會的FD法規的目的。

Forward-Looking Statements

前瞻性聲明

Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable US and Canadian securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of Ivanhoe Electric, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect Ivanhoe Electric's current expectations regarding future events, performance and results and speak only as of the date of this news release.

本新聞稿中的某些聲明構成適用的美國和加拿大證券法律下的「前瞻性聲明」或「前瞻性信息」。這些聲明和信息涉及已知和未知的風險、不確定性和其他因素,可能導致Ivanhoe Electric、其項目或行業的實際結果、績效或成就與任何未來結果、績效或成就在本前瞻性聲明或信息中明示或暗示的結果、績效或成就差異顯著。這些聲明可以通過使用諸如「可能」、「將」、「可能」、「將」、「打算」、「預計」、「相信」、「計劃」、「預判」和其他類似的術語來識別,或者表明某些行動、事件或結果「可能」、「可能」、「將」、「可能」或「將」被採取、發生或實現。這些聲明反映了Ivanhoe Electric關於未來事件、表現和結果的當前期望,並且僅於本新聞稿的日期,僅僅是指控日期的前瞻性描述。

Such statements in this news release include, without limitation timing and results of drilling operations, the timing and results of ongoing studies and test work in support of a Preliminary Feasibility Study for the Santa Cruz Project, the completion of the Preliminary Feasibility Study in Q2 2025, the ability to convert of resources from the Inferred category to the higher-confidence Indicated category, the submission of major state permit applications by H1 2025, and other planned or potential developments in the businesses of Ivanhoe Electric.

此新聞稿中的陳述包括但不限於鑽井作業的時間和結果、支持聖克魯茲項目初步可行性研究的持續研究和試驗結果的時間和結果、在2025年第二季度完成初步可行性研究、將資源從推論類別轉化爲更高置信度的指示類別的能力、在2025年上半年提交主要州級許可申請以及伊萬霍電氣業務中的其他計劃或潛在發展。

Forward-looking statements are based on management's beliefs and assumptions and on information currently available to management. Such statements are subject to significant risks and uncertainties, and actual results may differ materially from those expressed or implied in the forward-looking statements due to various factors, including changes in the prices of copper or other metals Ivanhoe Electric is exploring for; the results of exploration and drilling activities and/or the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations; the final assessment of exploration results and information that is preliminary; the significant risk and hazards associated with any future mining operations, extensive regulation by the US government as well as local governments; changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with Ivanhoe Electric to perform as agreed; and the impact of political, economic and other uncertainties associated with operating in foreign countries, and the impact of the COVID-19 pandemic and the global economy. These factors should not be construed as exhaustive and should be read in conjunction with the other cautionary statements and risk factors described in Ivanhoe Electric's Annual Report on Form 10-K filed with the U.S. Securities and Exchange Commission.

前瞻性聲明基於管理層的信念和假設,以及管理層目前可用的信息。這些聲明存在重大風險和不確定性,實際結果可能與前瞻性聲明中表達或暗示的結果有很大不同,原因包括Ivanhoe Electric正在開發的銅或其他金屬的價格變化;勘探和鑽探活動的結果和/或勘探計劃或研究未能提供預期的結果或結果未能支持進一步的勘探,研究、開發或運營;勘探結果和所謂基礎信息尚屬初步評估;未來採礦業務存在重大風險和危害,受美國政府及當地政府的廣泛監管;法律、規則或法規的變化,或者它們被適當當局實施的方式;與Ivanhoe Electric簽訂的合同方未能履行協議;在國外經營所涉及的政治、經濟和其他不確定性以及COVID-19疫情和全球經濟的影響。這些因素不應被視爲詳盡,應與Ivanhoe Electric的年度報告上Form 10-K中描述的其他警示性聲明和風險因素一併閱讀。

No assurance can be given that such future results will be achieved. Forward-looking statements speak only as of the date of this news release. Ivanhoe Electric cautions you not to place undue reliance on these forward-looking statements. Subject to applicable securities laws, Ivanhoe Electric does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release, and Ivanhoe Electric expressly disclaims any requirement to do so.

本新聞稿中包含的科學或技術性披露,包括基礎信息所採集的採樣、分析和技術數據,已由Glen Kuntz P.Geo審核、核實並批准。Glen Kuntz P.Geo按照美國證券交易委員會制定的Regulation S-k,Subpart 1300和加拿大43-101號國家儀器定義的「合格人士」的標準進行,是Ivanhoe Electric Inc.的僱員。

声明:本內容僅用作提供資訊及教育之目的,不構成對任何特定投資或投資策略的推薦或認可。 更多信息
    搶先評論