Growing Indicated Resource by 70% to 1,058,200 Gold Ounces

將指示資源增加70%至1,058,200盎司黃金

Toronto, Ontario--(Newsfile Corp. - October 16, 2024) - Xtra-Gold Resources Corp. (TSX: XTG) (OTCQB: XTGRF) ("Xtra-Gold" or the "Company") is very pleased to announce the results of an updated Mineral Resource estimate on its wholly-owned Kibi Gold Project, located in the Kibi-Winneba greenstone belt ("Kibi Gold Belt"), in Ghana, West Africa. The independent resource estimate, with an effective date of September 30, 2024, incorporates an additional 174 diamond core drillholes (34,737.1 m), completed by Xtra-Gold's in-house drilling crews since the previous September 2021 Mineral Resource Estimate.

多倫多,安大略--(Newsfile 股份有限公司 - 2024年10月16日) - Xtra-Gold資源公司(TSX:XTG)(OTCQB:XTGRF)("Xtra-Gold" 或 "公司")非常高興宣佈其全資Kibi黃金項目的更新礦產資源估計結果,該項目位於加納西非的Kibi-Winneba綠巖帶("Kibi黃金帶")中。獨立資源估計,截至2024年9月30日,包括額外的174個金剛石岩心鑽孔(34,737.1米),由Xtra-Gold公司自設的鑽探隊完成,自2021年9月之前的礦產資源估算以來

The new Mineral Resource encompasses initial resource estimates for the Boomerang and Twin Zone deposits in Zone 3, as well as previously-declared Mineral Resource estimates for the following eight (8) deposits: Big Bend, East Dyke, Mushroom, South Ridge, Road Cut, Double 19, Gatehouse and Gold Mountain. In aggregate, these ten (10) auriferous bodies, lying within approximately 2.7 km of each other, are estimated to contain an Indicated Mineral Resource of 1,058,200 ounces of gold and an additional Inferred Mineral Resource of 180,700 ounces of gold as summarized in Table 1, with details presented in Table 2 in the Mineral Resource Estimate summary section.

新的礦產資源包括第3區的迴旋鏢和雙區沉積物的初始資源估算,以及之前在以下八個(8)沉積物中宣佈的礦產資源估算: 大彎曲、東礦、蘑菇、南山脊、挖路口、雙19、門樓和金山。總計,這十個(10)含金體,位於相互距離約2.7公里的範圍內,據估計包含1,058,200盎司黃金的指示礦產資源和額外的180,700盎司黃金的推斷礦產資源,如表1所總結,詳細信息請參見礦產資源估計摘要部分的表2。

Table 1: Summary of Mineral Resource Declaration for Kibi Gold Project
Effective Date: September 30, 2024
(Cut-Off Grade: 0.5 g/t Au)
License and Buffer Zone
Tonnage (t) Density (t/m3) Grade - Au (g/t) Au (oz)
Indicated 27,532,000 2.79 1.20 1,058,200 (1)
Inferred 5,694,000 2.80 0.99 180,700
Buffer Zone between License and Forest Reserve
Tonnage (t) Density (t/m3) Grade - Au (g/t) Au (oz)
Indicated 3,769,000 2.83 1.20 145,400
Inferred
License Area
Tonnage (t) Density (t/m3) Grade - Au (g/t) Au (oz)
Indicated 22,179,000 2.79 1.18 842,400
Inferred 5,694,000 2.80 0.99 180,700
(1) See Cautionary Note below regarding status of mineral resources lying within the Buffer Zone, corresponding to the "open ground" between the existing Apapam mining lease and Forest Reserve boundaries.
表1: Kibi黃金項目礦產資源聲明摘要
有效日期:2024年9月30日
(截止品位:0.5克/噸Au)
許可證和緩衝區
噸數 (t) 密度(t/m3) 品位 - Au(g/t) 金(盎司)
指示資源 27,532,000 2.79 1.20 1,058,200 (1)
詳見2024年4月3日新聞稿 5,694,000 2.80 0.99 180,700
許可證與森林保護區之間的緩衝區
噸數 (t) 密度(t/m3) 品位 - Au(g/t) 金(盎司)
指示資源 3,769,000 2.83 1.20 145,400
詳見2024年4月3日新聞稿
許可區域
噸數 (t) 密度(t/m3) 品位 - Au(g/t) 金(盎司)
指示資源 22,179,000 2.79 1.18 842,400
詳見2024年4月3日新聞稿 5,694,000 2.80 0.99 180,700
(1)請參閱下方關於涉礦資源位於緩衝區內的注意事項,對應於現有Apapam礦權和森林保護區邊界之間的「空地」。

Cautionary Note: The Mineral Resource estimate includes mineral resources lying within the area termed the "Buffer Zone", which encompasses the "open ground" between the existing Apapam mining lease boundary up to the Forest Reserve boundary (see Table 2 for breakdown of mineral resources lying within the Buffer Zone). Xtra-Gold applied for this Buffer Zone in the original application of extension/renewal of the Apapam mining lease on June 17th, 2015, and in the updated extension/renewal dated June 28th, 2019. These applications were approved by the Technical Committee of the Minerals Commission and certified to be in conformity with the official cadastral system introduced under Ghana Mineral Law. Xtra-Gold is currently awaiting formal approval of the extension/renewal. Although the Company has taken all legal steps to extend the lease with the addition of the Buffer Zone, there is no assurance that such approval will be granted. In the interim, under Ghanaian mining law, the existing lease continues to remain in full force and effect.

注意:涉礦概念評估包括位於「緩衝區」內的礦產資源,該區域包括現有Apapam採礦租賃邊界和森林保護區邊界之間的「開放地面」(詳見表2,了解位於緩衝區內的礦產資源細分)。 Xtra-Gold於2015年6月17日在原始申請的Apapam採礦租賃延期/更新中申請了該緩衝區,並於2019年6月28日提出了更新的延期/更新申請。這些申請已獲得礦產委員會技術委員會批准,並獲得了符合引入加納礦產法下官方地籍系統的認證。 Xtra-Gold目前正在等待延期/更新的正式批准。儘管公司已採取了所有法律步驟擴展租賃以增加緩衝區,但不能保證將獲得批准。與此同時,在加納采礦法下,現有租賃繼續完全有效。

James Longshore, President and CEO remarked: "Today's updated Mineral Resource estimate symbolizes a major milestone for the Kibi Gold Project, surpassing 1 million gold ounces in the Indicated category. With approximately 83% of the Indicated Mineral Resource (880,500 oz.) contained within three deposits lying approximately 1.5 km of each other, including the essentially contiguous Big Bend and East Dyke deposits in Zone 2, and the Boomerang deposit in Zone 3. We are diligently building on this exciting Kibi Gold Project milestone, with an aggressive exploration drilling campaign currently ongoing and utilizing our in-house diamond core drill rigs, testing both near-deposit and favorable litho-structural targets within the mineral resource footprint, as well as prospective grassroot targets across the concession. This updated Mineral Resource, in addition to further validating the multi-million-ounce potential of the Kibi Gold Project, represents a pivotal step in our strategic plan to unlock the full potential of our extensive ground position across the underexplored Kibi Gold Belt."

James Longshore,總裁兼首席執行官表示:“今天更新的涉礦概念評估象徵着Kibi黃金項目的重要里程碑,超過100萬盎司黃金位於指示類別。約83%的指示類別涉礦資源(880,500盎司)位於相距約1.5公里的三個礦牀之內,包括位於第2區的基本連續的Big Bend和East Dyke礦牀以及第3區的Boomerang礦牀。我們正在努力建立在這一令人振奮的Kibi黃金項目里程碑上,目前正在積極進行勘探鑽探活動,並利用我們內部的金剛石中心鑽機,在礦產資源印記內測試近礦牀和有利構造巖靶區,以及在整個特許區內的有前途的基礎靶區。這次更新的涉礦概念評估,除了進一步驗證Kibi黃金項目的數百萬盎司潛力外,也代表了我們解鎖Kibi黃金帶未利用全部潛力的戰略計劃的關鍵一步。

Mineral Resource Estimate Summary

涉礦概念估算摘要

The updated Mineral Resource estimate for the Kibi Gold Project disclosed herein was jointly prepared by Pivot Mining Consultants (Pty) Ltd and Tect Geological Consulting of Johannesburg and Somerset West, South Africa, respectively. The mineral resource estimate, with an effective date of September 30, 2024, was prepared in accordance with the guidelines of the Definition Standards for Mineral Resources and Mineral Reserves set out by the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM").

本文披露的Kibi金礦項目更新的礦產資源估算由南非約翰內斯堡和薩默塞特威斯特的Pivot礦業顧問(有限公司)和Tect地質諮詢公司共同編制。礦產資源估算的有效日期爲2024年9月30日,按照加拿大礦業、冶金和石油協會("CIM")的《礦產資源與礦藏定義標準》指南進行了準備。

The present Mineral Resource encompasses initial resource estimates for the Boomerang and Twin Zone deposits, which were at an early exploration stage at the time of the 2021 Mineral Resource declaration, as well as previously-declared resource estimates for the following eight (8) deposits: Big Bend, East Dyke, Mushroom, South Ridge, Road Cut, Double 19, Gatehouse and Gold Mountain. With these ten (10) deposits, lying approximately within 2.7 km of each other, collectively estimated to contain an Indicated Mineral Resource of 1,058,200 ounces of gold based on 27,532,000 tonnes at an average grade of 1.20 grams per tonne ("g/t") gold and an additional Inferred Mineral Resource of 180,700 ounces of gold based on 5,694,000 tonnes at an average grade of 0.99 g/t gold. Details for the Mineral Resource estimate are presented in Table 2 and the location of the respective auriferous bodies depicted in plan and orthographic (3D) views in Figure 1, available at:

當前礦產資源包括Boomerang和Twin Zone礦牀的初始資源估算,這兩個礦牀在2021年礦產資源聲明時處於早期勘探階段,以及先前宣佈的以下八個礦牀的資源估算:Big Bend,East Dyke,Mushroom,South Ridge,Road Cut,Double 19,Gatehouse和Gold Mountain。這十個礦牀相互之間相距約2.7公里,據估計總共包含1,058,200盎司黃金的指示礦產資源,基於27,532,000噸,平均品位爲1.20克/噸黃金,並額外包含基於5,694,000噸,平均品位爲0.99克/噸黃金的推斷礦產資源180,700盎司黃金。礦產資源估算細節見表2,各金礦體位置見平面圖和正交圖(3D)俯視圖於圖1,詳見:

Figure 1_Kibi Gold Project_MRE Body Locations

圖1_Kibi金礦項目_MRE礦體位置

An independent NI 43-101 technical report prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") supporting the updated Mineral Resource estimate, entitled "Xtra-Gold Resources Corporation Kibi Gold Project", with an Effective Date of September 30, 2024, and dated September 30, 2024, jointly prepared by Pivot Mining Consultants (Pty) Ltd and Tect Geological Consulting, under the supervision of Ken Lomberg, Director, Geology and Resources, of Pivot Mining Consultants (Pty) Ltd., has been filed on SEDAR.

根據《43-101號國家儀器-礦產項目披露標準》("NI 43-101")編制的獨立NI 43-101技術報告,支持更新的礦產資源估算,題爲"Xtra-Gold Resources Corporation Kibi金礦項目",有效日期爲2024年9月30日,日期爲2024年9月30日,由Pivot礦業顧問(有限公司)和Tect地質諮詢公司共同編制,由Pivot礦業顧問(有限公司)的地質資源總監Ken Lomberg監督,已在SEDAR上提交。

This new Mineral Resource estimate updates and replaces the Company's prior Mineral Resource for the Kibi Gold Project, with an effective date of September 30, 2021, enclosed in the NI 43-101 technical report entitled "Xtra-Gold Resources Corporation Kibi Gold Project", jointly prepared by Pivot Mining Consultants (Pty) and Tect Geological Consulting, and dated November 16, 2021.

這份新的涉礦概念評估更新並取代了公司之前的基比黃金項目涉礦概念,截至2021年9月30日,包含在由Pivot Mining Consultants(Pty)和Tect Geological Consulting共同準備的《Xtra-Gold Resources Corporation基比黃金項目》NI 43-101技術報告中,報告日期爲2021年11月16日。

The database for the Kibi Gold Project encompasses 642 drillholes totalling 108,942.5 m, including 592 diamond drillcore holes (104,227.5 m) and 50 reverse circulation (RC) drillholes (4,715 m), drilled by Xtra-Gold since 2008. This includes an additional 174 diamond core drillholes, totalling 34,737.1 m, completed since the 2021 Mineral Resource. The Kibi Gold Project database also incorporates 417 trenches, totalling 17,863 m, excavated by Xtra-Gold since 2007. This new mineral resource estimate encompasses drillhole and trench data available as of January 29, 2024.

基比黃金項目的數據庫包括642口鑽孔,總計10894250萬,包括592口金剛石鑽孔(104,227.5米)和50口倒環(RC)鑽孔(4,715米),自2008年以來由Xtra-Gold鑽探。這包括自2021年涉礦概念以來完成的額外174口金剛石岩心鑽孔,總計3473710萬。基比黃金項目數據庫還包括自2007年以來由Xtra-Gold挖掘的417個探槽,總計1786300萬。這份新的涉礦概念評估涵蓋了截至2024年1月29日的鑽孔和探槽數據。

Three-dimensional (3D) geological models (i.e., mineralization envelopes) were generated for each auriferous body, based on their known geology and identified structural trends. The approach was based on the premise that gold-bearing fluids would have preferentially flowed through the defined structures, as depicted by the geological models. A lower cut-off of 0.4 g/t gold was utilized to constrain the outer limits of mineralization envelopes. The detailed geological models, in addition to providing well-constrained mineralization envelopes for mineral resource estimation, also serve as guides for structurally-controlled mineralization zones that will be subject to further exploration targeting.

爲每個含金體生成了三維(3D)地質模型(即礦化圍巖),基於它們已知的地質情況和確定的構造趨勢。該方法基於一個前提,即含金流體將優先流經地質模型所描繪的定義結構。黃金下限設定爲0.4克/噸,以限制礦化圍巖的外限。詳細的地質模型不僅爲涉礦概念評估提供了良好約束的礦化圍巖,還可作爲對進一步勘探目標構造控制礦化帶的指導。

The mineral resource estimation was undertaken separately for each auriferous body, utilizing the Ordinary Kriging method. Directional variograms and search parameters were developed for each body using the veining direction within the respective geological models. A block model cell size of 5 m x 5 m x 5 m was set after considering various parameters, as well as the geometry of the gold bodies. Assay capping values were independently established for each deposit, with capping values ranging from 15 g/t - 25 g/t gold. A cut-off grade of 0.5 g/t gold was applied after consideration of the reasonable expectation of eventual economic extraction.

對每個含金體單獨進行了涉礦概念評估,採用普通克里金法。利用各自地質模型內脈的方向開發了每個體的方向變異圖和搜索參數。在考慮各種參數及黃金脈體的幾何形態後,設定了500萬 x 500萬 x 500萬的塊模型單元大小。爲每個礦牀獨立制定了檢測值上限,檢測值範圍從15克/噸至25克/噸。在考慮到最終經濟開採的合理預期後,應用了0.5克/噸的下限品位。

The updated Mineral Resource encompasses ten (10) auriferous bodies lying within approximately 2.7 km of each other, including: the Big Bend, East Dyke, Mushroom, Road Cut and South Ridge deposits within Zone 2, with separations varying from almost contiguous to 200 m; the Double 19, Twin Zone and Boomerang deposits in Zone 3, approximately 400 m to 950 m southwest of Zone 2; and the Gatehouse and Gold Mountain bodies situated in Zone 1, approximately 650 m southeast of Zone 2. Mineralization remains open down-plunge for all auriferous bodies, with several bodies remaining open in multiple directions. Approximately 83% of the Indicated Mineral Resource (880,500 oz.) is contained within three (3) deposits, including the essentially contiguous Big Bend and East Dyke deposits in Zone 2, and the Boomerang deposit in Zone 3, approximately 1.5 km to the southwest of Zone 2.

更新後的涉礦概念涵蓋了彼此之間約2.7公里距離的十個富金礦體,包括:Zone 2內的Big Bend、East Dyke、Mushroom、Road Cut和South Ridge礦牀,彼此之間的分隔從幾乎相鄰到200米不等;Zone 3內的Double 19、Twin Zone和Boomerang礦牀,位於Zone 2西南約40000萬至95000萬處;以及Zone 1內的Gatehouse和Gold Mountain礦體,位於Zone 2東南約65000萬處。所有富金礦體向深處的礦化仍然開放,幾個礦體在多個方向上仍然開放。指示性涉礦概念(880,500盎司)約83%包含在三個礦牀中,包括Zone 2內基本相鄰的Big Bend和East Dyke礦牀,以及Zone 3內的Boomerang礦牀,位於Zone 2西南約1.5公里處。

Gold mineralization within the Mineral Resource footprint area consists predominantly of tensional arrays of auriferous quartz-carbonate veins typically, hosted within or spatially associated with F1-or F2-folded / strained diorite units, and/or metasedimentary rock - diorite contacts, with diorite bodies having an interpreted Belt-type granitoid affinity. Over 20 significant gold occurrences hosted by Belt (Dixcove)- and Basin (Cape Coast)-type granitoids are known in Ghana, with a number constituting significant deposits. These deposits represent a relatively new style of gold mineralization for orogenic gold deposits within the West African Birimian terrain. Belt-type intrusion-hosted gold deposits include Newmont Mining's Subika deposit at their Ahafo mine and Asante Gold's Chirano deposit (formerly Kinross Mining) within the Sefwi gold belt, as well as Chifeng Gold's Hwini-Butre deposit (formerly Gold Star Resources) at the southern extremity of the Ashanti gold belt.

涉礦概念範圍內的金礦化主要由拉張數組的富金石英-碳酸鹽石英脈組成,通常寄主於或與F1或F2褶皺/應變閃長質巖體及/或變質沉積岩 - 閃長質接觸帶空間相關,並且閃長質巖體具有解釋爲帶型花崗岩親緣性。在加納已知有20多個主要的金礦出現於Belt(Dixcove)和Basin(Cape Coast)型花崗岩中,其中一些構成重要礦牀。這些礦牀代表了西非比裏米地塊內造山成因金礦牀相對較新的類型。帶型侵入式金礦牀包括紐曼礦業Subika礦牀和安香金礦Chirano礦牀(前金石礦業,位於Sefwi金帶)以及赤峯金礦的Hwini-Butre礦牀(前金星資源公司),位於阿散蒂金帶的南端極端。

Table 2: Mineral Resource Declaration - Kibi Gold Project (1-14)
Declared in terms of the CIM Standards
Effective Date: September 30, 2024
(Cut-off: Au 0.5 g/t)
Apapam License and Buffer Area Buffer Zone between License and Forest Reserve Apapam License Area
Indicated Indicated Indicated
Tonnage (t) Density (t/m3) Grade Au (g/t) Ozs Tonnage (t) Density (t/m3) Grade Au (g/t) Ozs Tonnage (t) Density (t/m3) Grade Au (g/t) Ozs
Big Bend 6,472,000 2.78 1.48 307,400 - - - - 6,472,000 2.78 1.48 307,400
East Dyke 3,102,000 2.72 1.49 148,800 - - - - 3,102,000 2.72 1.49 148,800
Mushroom 505,000 2.63 1.37 22,200* 16,000 2.82 1.18 600 489,000 2.64 1.37 21,600
South Ridge 2,005,000 2.70 1.07 68,700 - - - - 2,005,000 2.70 1.07 68,700
Double 19 1,584,000 3 1 70,400 - - - - - - - -
Gatehouse & Gold Mountain - - - - - - - - - - - -
Road Cut 225,000 3 1 6,100 - - - - 225,000 2.80 0.85 6,100
Boomerang 13,281,000 2.84 0.99 424,300* 3,722,000 2.83 1.20 144,100 9,559,000 2.85 0.91 280,200
Twin Zone 358,000 2.81 0.89 10,300* 31,000 2.65 0.68 700 327,000 2.83 0.91 9,600
27,532,000 2.79 1.20 1,058,200* 3,769,000 2.83 1.20 145,400 22,179,000 2.79 1.18 842,400
Inferred Inferred Inferred
Tonnage (t) Density (t/m3) Grade Au (g/t) Ozs Tonnage (t) Density (t/m3) Grade Au (g/t) Ozs Tonnage (t) Density (t/m3) Grade Au (g/t) Ozs
Big Bend 1,257,000 2.82 1.03 41,400 - - - - 1,257,000 2.82 1.03 41,400
East Dyke 1,128,000 2.84 1.19 43,300 - - - - 1,128,000 2.84 1.19 43,300
Mushroom - - - - - - - - - - - -
South Ridge 943,000 2.82 1.02 30,800 - - - - 943,000 2.82 1.02 30,800
Double 19 - - - - - - - - - - - -
Gatehouse & Gold Mountain 2,366,000 2.76 0.79 65,200 - - - - 2,366,000 2.76 0.79 65,200
Road Cut - - - - - - - - - - - -
Boomerang - - - - - - - - - - - -
Twin Zone - - - - - - - - - - - -
5,694,000 2.80 0.99 180,700 - - 5,694,000 2.80 0.99 180,700
* See Cautionary Note below regarding status of mineral resources lying within the Buffer Zone, corresponding to the "open ground" between the existing Apapam mining lease and Forest Reserve boundaries.
表2:涉礦概念聲明 - 基比黃金項目(1-14)
按照CIm標準聲明
生效日期:2024年9月30日
(截止線:Au 0.5 g/t)
Apapam許可證及緩衝區 許可證與森林保護區之間的緩衝區 Apapam許可證區域
指示資源 指示資源 指示資源
噸數 (t) 密度(t/m3) 黃金品位(g/t) 盎司 噸數 (t) 密度(t/m3) 黃金品位(g/t) 盎司 噸數 (t) 密度(t/m3) 黃金品位(g/t) 盎司
Big Bend 6,472,000 2.78 1.48 307,400 - - - - 6,472,000 2.78 1.48 307,400
the eastern 鄧克 3,102,000 2.72 1.49 148,800 - - - - 3,102,000 2.72 1.49 148,800
Mushroom 505,000 2.63 1.37 22,200* 16,000 2.82 1.18 600 489,000 2.64 1.37 21,600
南嶺 2,005,000 2.70 1.07 68,700 - - - - 2,005,000 2.70 1.07 68,700
Double 19 1,584,000 3 1 70,400 - - - - - - - -
Gatehouse & 黃金山 - - - - - - - - - - - -
路口切割 225,000 3 1 6,100 - - - - 225,000 2.80 0.85 6,100
Boomerang 13,281,000 2.84 0.99 424,300* 3,722,000 2.83 1.20 144,100 9,559,000 2.85 0.91 280,200
雙區 358000 2.81 0.89 10,300* 31,000 2.65 0.68 700 327,000 2.83 0.91 分別爲2023年和2022年12月31日結束的六個月,並分別爲 $ 9,600 和 $ 。
27,532,000 2.79 1.20 1,058,200* 3,769,000 2.83 1.20 145,400 22,179,000 2.79 1.18 842,400
詳見2024年4月3日新聞稿 詳見2024年4月3日新聞稿 詳見2024年4月3日新聞稿
噸數 (t) 密度(t/m3) 黃金品位(g/t) 盎司 噸數 (t) 密度(t/m3) 黃金品位(g/t) 盎司 噸數 (t) 密度(t/m3) 黃金品位(g/t) 盎司
Big Bend 1,257,000 2.82 1.03 41,400 - - - - 1,257,000 2.82 1.03 41,400
the eastern 鄧克 1,128,000 2.84 1.19 43,300 - - - - 1,128,000 2.84 1.19 43,300
Mushroom - - - - - - - - - - - -
南嶺 943,000壓力位服務,以及$ 2.82 1.02 30,800 - - - - 943,000壓力位服務,以及$ 2.82 1.02 30,800
Double 19 - - - - - - - - - - - -
Gatehouse & 黃金山 2,366,000 2.76 0.79 65,200 - - - - 2,366,000 2.76 0.79 65,200
路口切割 - - - - - - - - - - - -
Boomerang - - - - - - - - - - - -
雙區 - - - - - - - - - - - -
5,694,000 2.80 0.99 180,700 - - 5,694,000 2.80 0.99 180,700
* 請參閱以下有關涉及緩衝區內礦產資源狀況的警示說明,對應於現有Apapam採礦租約和森林保護區邊界之間的"露天地"。

Notes

票據

1) CIM Definition Standards were followed for the Mineral Resource estimate.

1) 對於礦產資源估計,遵循了CIM定義標準。

2) The Mineral Resource estimate encompasses drillhole and trench data available as of January 29, 2024.

2) 礦產資源估計包括截至2024年1月29日可獲得的鑽孔和溝槽數據。

3) A cut-off grade of 0.5 g/t gold was applied to all mineral resource estimates, after consideration of the reasonable expectation of eventual economic extraction, assuming initially open pit extraction with some deposits transitioning to an underground mining operation.

3) 所有涉礦概念估算均應用了0.5克/噸的黃金基準品位,經過合理考慮預計最終經濟開採,並假定最初爲露天開採,一些礦牀過渡爲地下黃金股操作。

4) The capping value was established for each deposit independently, with assay capping values ranging from 15 g/t - 25 g/t gold.

4) 每個礦牀獨立建立了一個上限值,化驗值上限範圍爲15克/噸 - 25克/噸的黃金。

5) The estimation utilised Ordinary Kriging, with each target being evaluated independently.

5) 估算採用了普通克里金法,每個目標均獨立評估。

6) The understanding of the geology - and specifically the structure -f of each body underpinned the estimation.

6) 對每個礦體地質學 - 特別是結構 - 的了解支撐了此估算。

7) Average density values for oxide, transition, and fresh (sulphide) materials were established for each deposit independently; with the indicated density values reflecting weighted averages for oxide, transition, and fresh materials for the respective deposits.

7) 氧化、過渡和新鮮(硫化物)材料的平均密度值均獨立建立,表明所指密度值反映了相應礦牀氧化、過渡和新鮮材料的加權平均值。

8) Mineral Resource tonnage and contained metal have been rounded to reflect the accuracy of the estimate, and numbers may not add due to rounding.

8) 涉礦概念噸位和含金屬量已四捨五入以反映估計準確性,數字可能因四捨五入而無法相加。

9) Mineral Resource tonnage and grade are reported as undiluted.

9) 涉礦概念噸位和品位報告爲未稀釋。

10) The figures for contained gold are in-situ Mineral Resources.

10) 含金量數字爲原位涉礦概念。

11) 1 troy ounce equals 31.10348 grams.

11) 1金衡盎司等於31.10348克。

12) Mineral Resources are not Mineral Reserves and by definition do not demonstrate economic viability.

12) 涉礦概念不等同於礦產資源,根據定義,不表明其經濟可行性。

13) Inferred Mineral Resources have a great amount of uncertainty as to their existence and as to whether they can be mined economically. It cannot be assumed that all or part of the Inferred Mineral Resources will ever be upgraded to a higher category.

13) 推測的涉礦概念存在着很大的不確定性,以及是否可以在經濟上進行開採也存在着不確定性。不能假設所有或部分推測的礦產資源最終會被提升到更高的分類。

14) The estimate of Mineral Resources may be materially affected by geological, environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

14) 涉礦概念的估算可能會受到地質、環境、許可、法律、所有權、稅收、社會政治、市場或其他相關問題的重大影響。

Cautionary Note: The Mineral Resource estimate includes portions of the mineral resources for the Mushroom, Boomerang and Twin Zone deposits lying within the area termed the "Buffer Zone", which encompasses the "open ground" between the existing Apapam mining lease boundary up to the Forest Reserve boundary. Xtra-Gold applied for this Buffer Zone in the original application of extension/renewal of the Apapam mining lease on June 17th, 2015, and in the updated extension/renewal dated June 28th, 2019. These applications were approved by the Technical Committee of the Minerals Commission and certified to be in conformity with the official cadastral system introduced under Ghana Mineral Law. Xtra-Gold is currently awaiting formal approval of the extension/renewal. Although the Company has taken all legal steps to extend the lease with the addition of the Buffer Zone, there is no assurance that such approval will be granted. In the interim, under Ghanaian mining law, the existing lease continues to remain in full force and effect.

注意事項: The Mineral Resource estimate includes portions of the mineral resources for the Mushroom, Boomerang and Twin Zone deposits lying within the area termed the "Buffer Zone", which encompasses the "open ground" between the existing Apapam mining lease boundary up to the Forest Reserve boundary. Xtra-Gold applied for this Buffer Zone in the original application of extension/renewal of the Apapam mining lease on June 17th, 2015, and in the updated extension/renewal dated June 28th, 2019. These applications were approved by the Technical Committee of the Minerals Commission and certified to be in conformity with the official cadastral system introduced under Ghana Mineral Law. Xtra-Gold is currently awaiting formal approval of the extension/renewal. Although the Company has taken all legal steps to extend the lease with the addition of the Buffer Zone, there is no assurance that such approval will be granted. In the interim, under Ghanaian mining law, the existing lease continues to remain in full force and effect.

Technical Disclosure and Qualified Persons

技術披露和有資格人士

The Mineral Resource estimate for the Kibi Gold Project has been prepared by Mr. Ken Lomberg, Pr.Sci.Nat., of Pivot Mining Consultants (Pty) Ltd ("Pivot") of Johannesburg, South Africa, and Dr Corné Koegelenberg, Pr.Sci.Nat., and Dr Ian Basson, Pr.Sci.Nat., of Tect Geological Consulting ("Tect") of Somerset West, South Africa, all of whom are independent Qualified Persons ("QP's") for the purposes of NI 43-101. Pivot has conducted an audit of the sampling procedures and QA/QC data and is of the opinion that the data is suitable for use in the mineral resource estimate. The mineral resource estimate was prepared in accordance with guidelines of the Definition Standards for Mineral Resources and Mineral Reserves set out by the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM"). All the abovementioned QP's have reviewed and approved the contents of this news release with respect to the Mineral Resource estimate.

Kibi黃金項目的涉礦概念估算由南非約翰內斯堡Pivot Mining Consultants (Pty) Ltd ("Pivot")的Ken Lomberg和Somerset West, 南非Tect Geological Consulting ("Tect")的Dr Corné Koegelenberg, 和Dr Ian Basson準確地準備,他們全部爲獨立的資格人士 ("QP's"),符合NI 43-101的要求。Pivot對取樣程序和質保/質控數據進行了審核,並認爲數據適用於礦產資源估算。礦產資源估算是根據加拿大礦業、冶金和石油學會("CIM")制定的礦產資源和礦產儲量定義標準的指導方針準備的。所有上述QP已經審查並批准了關於礦產資源估算的新聞發佈的內容。

An independent NI 43-101 technical report prepared in accordance with NI 43-101 - Standards of Disclosure for Mineral Projects supporting the updated Mineral Resource estimate, entitled "Xtra-Gold Resources Corporation Kibi Gold Project", with an Effective Date of September 30, 2024, and dated September 30, 2024, jointly prepared by Pivot Mining Consultants (Pty) Ltd and Tect Geological Consulting, under the supervision of Ken Lomberg, Director, Geology and Resources, of Pivot Mining Consultants (Pty) Ltd., has been filed on SEDAR.

在SEDAR上已提交了由Pivot Mining Consultants(Pty)Ltd和Tect Geological Consulting聯合編制的、由Ken Lomberg(Pivot Mining Consultants(Pty)Ltd的地質和資源主管)監督的,於2024年9月30日生效的、日期爲2024年9月30日的《Xtra-Gold Resources Corporation Kibi Gold Project》支持更新的礦產資源估計的符合NI 43-101標準的獨立NI 43-101技術報告。

Yves P. Clement, P.Geo., Vice President, Exploration of Xtra-Gold Resources Corp, who is a "Qualified Person" for the purposes of NI 43-101, has prepared and/or supervised the preparation of this news release and has reviewed and approved the scientific and technical information in this announcement.

作爲符合NI 43-101標準挖礦項目披露要求的"有資質人士",Xtra-Gold Resources Corp的勘探副總裁,P.Geo. Yves P. Clement,已準備和/或監督了此新聞發佈內容的準備,並已審查和批准了本公告中的科學技術信息。

About Xtra-Gold Resources Corp.

關於Xtra-Gold Resources Corp。

Xtra-Gold is a gold exploration company with a substantial land position in the Kibi Gold Belt. The Kibi Gold Belt, which exhibits many similar geological features to Ghana's main gold belt, the Ashanti Belt, has been the subject of very limited modern exploration activity targeting hard rock gold deposits, as virtually all past gold mining activity and exploration efforts have been focused on the extensive alluvial gold occurrences in many river valleys throughout the Kibi area.

Xtra-Gold是一家黃金勘探公司,在Kibi Gold Belt擁有大規模土地。Kibi Gold Belt展示了許多類似於加納主要黃金帶Ashanti Belt的地質特徵,現代對硬巖金礦礦牀的勘探活動非常有限,幾乎所有過去的黃金開採活動和勘探工作都集中在Kibi地區許多河谷中的廣泛沖積黃金產區。

Xtra-Gold holds five (5) Mining Leases totaling approximately 226 sq km (22,600 ha) at the northern extremity of the Kibi Gold Belt. The Company's exploration efforts to date have focused on the Kibi Gold Project located on the Apapam Concession (33.65 sq km), along the eastern flank of the Kibi Gold Belt. The updated Kibi Gold Project (Zones 1-3) Mineral Resource estimate, produced by Xtra-Gold on September 30, 2024, represents the only Mineral Resource ever generated on a lode gold project within the Kibi Gold Belt. The NI 43-101 technical report entitled "Xtra-Gold Resources Corporation Kibi Gold Project", jointly prepared by Pivot Mining Consultants (Pty) and Tect Geological Consulting, and dated September 30, 2024, is filed under the Company's profile on SEDAR+ at .

在Kibi Gold Belt北端擁有總面積約226平方公里(22,600公頃)的五(5)個礦業許可證。至今,公司的勘探工作重點放在Kibi Gold Belt東翼的Apapam特許區(33.65平方公里)上的Kibi Gold Project。由Xtra-Gold於2024年9月30日發佈的更新的Kibi Gold Project(區域1-3)礦產資源估計代表了Kibi Gold Belt內金礦項目的唯一礦產資源。由Pivot Mining Consultants(Pty)和Tect Geological Consulting聯合編制的日期爲2024年9月30日的《Xtra-Gold Resources Corporation Kibi Gold Project》符合NI 43-101標準的技術報告已在公司的SEDAR+檔案中提交。

Forward-Looking Statements

前瞻性聲明

Neither TSX nor its Regulation Services Provider (as that term is defined in the policies of the TSX) accepts responsibility for the adequacy or accuracy of this release. No other stock Exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein. This News Release includes certain "forward-looking statements" which are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". Since forward-looking statements are based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties. Although these statements are based on information currently available to the Company, the Company provides no assurance that actual results will meet management's expectations. Risks, uncertainties, and other factors involved with forward-looking information could cause actual events, results, performance, prospects, and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward looking information in this news release includes, but is not limited to, the Company's objectives, goals or future plans, statements, exploration results, potential mineralization, the estimation of mineral resources, exploration and mine development plans, timing of the commencement of operations and estimates of market conditions. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to failure to identify mineral resources, failure to convert estimated mineral resources to reserves, the inability to complete a feasibility study which recommends a production decision, the preliminary nature of metallurgical test results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects, capital and operating costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry, and those risks set out in the Company's public documents filed on SEDAR+. Although the Company believes that the assumptions and factors used in preparing the forward-looking information in this news release are reasonable, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law.

TSX及其監管服務提供商(如TSX政策中所定義的那樣)均不對本公告的充分性或準確性負責。沒有其他證券交易所、證券監管機構或其他監管機構批准或未批准本文中包含的信息。本新聞稿包含一些「前瞻性聲明」,這些聲明不包含歷史事實。前瞻性聲明包括描述公司未來計劃、目標或目標的估計和說明,包括公司或管理層預期某種狀態或結果會發生的措辭。前瞻性聲明可能被識別爲「相信」、「預期」、「期望」、「估計」、「可能」、「可能」、「將」或「計劃」。由於前瞻性聲明基於假設並涉及未來事件和狀況,因其本質而言,它們涉及固有的風險和不確定性。儘管這些聲明基於目前對公司可獲得的信息,但公司並不保證實際結果將符合管理層的期望。風險、不確定性和其他與前瞻信息相關的因素可能導致實際事件、結果、表現、前景和機會與這種前瞻信息所表達的有實質不同。本新聞發佈中的前瞻性信息包括但不限於公司的目標、計劃或未來計劃、聲明、勘探結果、潛在礦化、礦產資源估計、勘探和礦山開發計劃、開工時間以及市場狀況的估計。可能導致實際結果與此類前瞻性信息存在實質差異因素包括但不限於未能鑑定礦產資源、未能將估計礦產資源轉換爲儲量、無法完成建議生產決策的可行性研究、冶金試驗結果初步性、延遲獲得或未能獲得必要的政府、環境或其他項目批准、政治風險、與未來融資可用性和成本相關的不確定性、股票市場的變化、通貨膨脹、匯率的變動、商品價格的波動、項目開發延遲、資本和營運成本與估計有顯著差異以及對礦產勘探和開發行業涉及的其他風險以及公司在SEDAR+上公開文件中列出的那些風險。儘管公司相信本新聞發佈中的前瞻性信息準備所使用的假設和因素是合理的,但不應對這類信息置於過度依賴,這類信息只適用於本新聞發佈的日期,並且不能保證此類事件將在披露的時間範圍內或根本發生。公司否認有意或義務更新或修改任何前瞻性信息,除非依法要求。

Cautionary Note to United States Investors

美國投資者的警告提示

This news release has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of U.S. securities laws. Unless otherwise indicated, all resource and reserve estimates included in this news release have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") and the Canadian Institute of Mining, Metallurgy, and Petroleum 2014 Definition Standards on Mineral Resources and Mineral Reserves. NI 43-101 is a rule developed by the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Canadian standards, including NI 43-101, differ significantly from the requirements of the SEC, and Mineral Resource and reserve information contained herein may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term "resource" does not equate to the term "reserves". Under U.S. standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. The SEC's disclosure standards normally do not permit the inclusion of information concerning "measured Mineral Resources", "indicated Mineral Resources" or "inferred Mineral Resources" or other descriptions of the amount of mineralization in mineral deposits that do not constitute "reserves" by U.S. standards in documents filed with the SEC. Investors are cautioned not to assume that any or all of the mineral deposits in these categories will ever be converted into reserves. U.S. investors should also understand that "inferred Mineral Resources" have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred Mineral Resource" will ever be upgraded to a higher category. Under Canadian rules, estimated "inferred Mineral Resources" may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an "inferred Mineral Resource" exists or is economically or legally mineable. Disclosure of "contained ounces" in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute "reserves" by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of "reserves" are also not the same as those of the SEC, and reserves reported by the Company in compliance with NI 43-101 may not qualify as "reserves" under SEC standards. Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.

該新聞資訊已根據加拿大現行證券法的要求進行了準備,這些要求與美國的證券法要求不同。除非另有說明,本新聞資訊中包含的所有資源和儲量評估均是根據《礦產項目披露標準第43-101號國家儀器》("NI 43-101")和2014年加拿大礦業、冶金和石油學院有關礦產資源和礦產儲量的定義標準進行準備的。NI 43-101是由加拿大證券管理者制定的規則,爲發行人就礦產項目的科學技術信息做出的所有公開披露制定了標準。加拿大標準,包括NI 43-101,與SEC的要求有很大不同,其中包含的礦產資源和儲量信息可能與美國公司披露的類似信息不可比。特別地,並不限於前述,"資源"一詞不等同於"儲量"一詞。根據美國標準,除非已作出確定礦化物能在作出儲量確定時經濟上和合法上被生產或提取的決定,否則礦化可能不被分類爲"儲量"。SEC的披露標準通常不允許在提交給SEC的文件中包含關於"測量礦產資源"、"指示礦產資源"或"推測礦產資源"或其他礦牀中礦化量的描述,這些描述不符合美國標準中"儲量"的說法。投資者應該警惕,不要假設這些類別中的任何礦牀將全部或部分轉化爲儲量。美國投資者還應理解,"推測礦產資源"存在很大的不確定性,無法確定其存在以及經濟和法律上的可行性。不能假設"推測礦產資源"的全部或任何部分將被升級至更高級別。根據加拿大規定,在極少數情況下,估計的"推測礦產資源"可能不構成可行性或可行性前期研究的依據。投資者應該警惕,不要假設"推測礦產資源"的全部或任何部分存在或具有經濟或法律上的可採性。在加拿大規定下,在資源中披露的"含量盎司"是允許的披露;然而,SEC通常只允許發行人報告不符合SEC標準的礦化爲原位噸位和品位,而不涉及單位措施。NI 43-101對"儲量"的識別要求也與SEC的要求不同,公司根據NI 43-101合規報告的儲量可能不符合SEC標準的"儲量"。因此,此處列出的礦牀相關信息可能與按照美國標準披露信息的公司公開的信息不可比。

Contact Information

聯繫信息

For further information please contact:

要了解更多信息,請聯繫:

James Longshore
Chief Executive Officer
242-363-3864
E-mail: info@xtragold.com
Website:

James Longshore
首席執行官
242-363-3864
郵箱:info@xtragold.com
網站:

NOT FOR DISSEMINATION IN THE UNITED STATES OF AMERICA OR THROUGH U.S. NEWSWIRE SERVICES

不得在美利堅合衆國或通過美國新聞線發佈。

声明:本內容僅用作提供資訊及教育之目的,不構成對任何特定投資或投資策略的推薦或認可。 更多信息
    搶先評論