Endeavour Silver Nears 77% Completion of Terronera Project, $258M Spent.
Endeavour Silver Nears 77% Completion of Terronera Project, $258M Spent.
Endeavour Silver已完成Terronera項目的77%,支出25800萬美元。
Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:EXK, TSX:EDR) is pleased to provide a Q3 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are in United States dollars.
Endeavour Silver Corp.("Endeavour" 或該公司)(紐交所:EXk, tsx:EDR)很高興爲其位於墨西哥哈利斯科州Terronera項目提供2024年第三季度施工進展更新。照片展示隨新聞發佈一併附上,可在此處或公司網站Terronera項目進展照片中找到。本新聞發佈中所有美元($)參考均以美元表示。
The Terronera project made substantial progress during the third quarter as the Upper Plant Platform nears completion. Surface mill and infrastructure construction reached 90%, further preparing for advancement into operations. Focus continues on the Lower Platform, where concrete work...
Terronera項目在第三季度取得了實質性進展,上部工廠平台即將完成。地面...