Minera Alamos Provides Sabre Gold Acquisition and Operations Update
Minera Alamos Provides Sabre Gold Acquisition and Operations Update
Santana Phase 2 Pad Expansion Preparations Underway
桑塔納二期停機坪擴建準備工作正在進行中
Toronto, Ontario--(Newsfile Corp. - November 18, 2024) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide an interim corporate update to follow its recent announcement (see news release of October 28th, 2024) of the acquisition of Sabre Gold ("Sabre") and its flagship Copperstone gold project in Arizona.
安大略省多倫多--(Newsfile Corp.,2024年11月18日)——Minera Alamos Inc.(多倫多證券交易所股票代碼:MAI)(「公司」 或 「Minera Alamos」)很高興提供臨時公司最新情況,以繼其最近宣佈(見2024年10月28日新聞稿)收購亞利桑那州的Sabre Gold(「Sabre」)及其旗艦銅石黃金項目之後。
Copperstone Gold Project Developments
Copperstone 黃金項目開發
Following the recent Sabre Gold acquisition announcement, the Company and Sabre are moving quickly to finalize the transaction, with the Sabre shareholder meeting now set for January 14th, 2025, in parallel with the initiation of project development activities. To date, this includes:
繼最近宣佈收購Sabre Gold之後,該公司和Sabre正在迅速採取行動完成交易,Sabre股東大會現定於2025年1月14日舉行,同時啓動項目開發活動。迄今爲止,這包括:
- On November 11th, Sabre announced the repurchase of a 1.5% existing net smelter royalty ("NSR") on the Copperstone project in exchange for a non-core 0.5% NSR right held by the company on the 3 Aces project being explored by Seabridge Gold Inc. The completion of the transfer further reduces the historical royalty levels attached to the Copperstone project.
- The Company is preparing updated process models and flowsheets for the construction of the new Copperstone processing facility. This work is expected to be completed before year-end.
- Underground development plans are being reworked and are expected to reduce some of the reliance on higher operating cost mining methods while providing improved operational flexibility in order to more effectively maintain mining rates as envisioned in the 2023 Preliminary Economic Assessment ("PEA") for the project.
- Work is underway to finalize the preparation of the Company's existing grinding and flotation equipment for shipment to Copperstone, so it is available at site early in 2025 in advance of the start of the process plant construction.
- 11月11日,Sabre宣佈回購Copperstone項目1.5%的現有淨冶煉廠特許權使用費(「NSR」),以換取該公司在Seabridge Gold Inc正在勘探的3 Aces項目中持有的0.5%的非核心NSR權利。轉讓的完成進一步降低了與Copperstone項目相關的歷史特許權使用費水平。
- 該公司正在爲建造新的Copperstone加工設施準備更新的工藝模型和流程表。這項工作預計將在年底前完成。
- 地下開發計劃正在重新制定中,預計將減少對較高運營成本採礦方法的依賴,同時提高運營靈活性,從而更有效地維持該項目2023年初步經濟評估(「PEA」)中設想的採礦率。
- 目前正在完成公司現有研磨和浮選設備的準備工作,以便運往Copperstone,因此該設備將在加工廠建設開始之前於2025年初在現場投入使用。
In the coming months the Company will be able to more fully quantify the positive impact various current Minera initiatives will have on the overall Copperstone project economics as compared to those summarized in the 2023 PEA completed by Sabre.
在接下來的幾個月中,與Sabre完成的2023年PEA中總結的相比,公司將能夠更全面地量化當前各種Minera計劃對Copperstone項目整體經濟的積極影響。
Santana Operations
桑塔納運營
Mining and stacking operations during the first full quarter (Q3-2024) of production from the new Nicho Main Zone pit reached 3,800 ounces of gold which is in line with Company forecasts for the period, an amount that surpasses the total ounces mined and stacked for the entirety of 2023. As the new Nicho Main pit is expanded in surface area, access for mining operations continues to improve and two additional trucks were added to the mining fleet as anticipated.
在第一個完整季度(Q3-2024)中,新的Nicho Main Zone礦的採礦和堆放業務的黃金產量達到3,800盎司,這與公司對該期間的預測一致,這一數量超過了2023年全年開採和堆放的總盎司。隨着新的Nicho Main礦地表面積的擴大,採礦作業的通道不斷改善,並且如預期的那樣,採礦車隊中又增加了兩輛卡車。
- Gold grades of the mineralized material mined in the quarter averaged approximately 0.6 g/t with a strip ratio of 1.84:1 (waste to mineralized material). Average grades remain reasonably in line with those predicted from the current resource model.
- The Company is completing final preparations for the Phase 2 leach pad expansion at Santana which will increase the area available for site leaching operations by 40%. This leach pad expansion will allow for more efficient leaching activities as the ramp up of mining operations continues into 2025 with a better separation of the active leaching areas from newly mined material. The larger Phase 3 pad expansion is awaiting Permit Amendment approval that will allow the Company to execute on the larger future planned expansion of activities at Santana.
- A local contractor group has been selected to perform rehabilitation work on the Company's previously acquired crushing and transfer equipment. Final detailed engineering work is underway to install this equipment adjacent to the current leach pad facilities in order to improve the preparation and handling of mineralized material to be stacked on the expanded leach pad areas.
- Following a return to more active mine operations, the Company has embarked on a number of community projects including road maintenance and upgrade activities.
- 該季度開採的礦化材料的黃金品位平均約爲0.6 g/t,帶材比爲1. 84:1(廢物與礦化材料)。平均成績與當前資源模型預測的水平保持合理一致。
- 該公司正在完成桑塔納第二階段浸出場擴建的最後準備工作,這將使現場浸出作業的可用面積增加40%。隨着採礦業務的擴大將持續到2025年,活性浸出區與新開採的材料更好地分離,滲濾區的擴建將允許更高效的浸出活動。較大的第三階段停機坪擴建項目正在等待許可證修正案的批准,這將使公司能夠執行桑塔納未來計劃的大規模擴建活動。
- 已選定一個當地承包商集團對該公司先前收購的破碎和輸送設備進行修復工作。最後的詳細工程工作正在進行中,將該設備安裝在當前的滲濾墊設施附近,以改善堆疊在擴大的滲濾墊區域的礦化材料的製備和處理。
- 在恢復更加活躍的採礦業務之後,該公司已啓動了許多社區項目,包括道路維護和升級活動。
Cerro de Oro Project Developments
Cerro de Oro 項目開發
Engineering work continues for the Cerro de Oro project in advance of final permit receipt.
在收到最終許可證之前,Cerro de Oro項目的工程工作仍在繼續。
- Detailed engineering focused on the long-lead areas of the new site infrastructure facilities as required for the issuance of proposal requests related to these work/equipment items.
- Discussions are ongoing with potential contractors suitable for the rehabilitation of existing equipment (crushing/screening) to be utilized at Cerro de Oro
- Continued technical correspondence with the relevant authorities as the permit review continues to advance.
- 詳細工程側重於發佈與這些工作/設備項目相關的提案請求所需的新場地基礎設施的長距離區域。
- 目前正在與適合修復將在塞羅德奧羅使用的現有設備(壓碎/篩分)的潛在承包商進行討論
- 隨着許可證審查的繼續推進,繼續與有關當局進行技術通信。
Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the technical content of this press release under National Instrument 43-101.
Minera Alamos首席執行官達倫·科寧根先生是負責National Instrument 43-101下本新聞稿技術內容的合格人員。
Cautionary Statement
警示聲明
The Company made its production decision at the Santana gold mine without having completed a feasibility study demonstrating economic and technical viability. As such, there may be increased uncertainty of achieving planned production levels, estimated recovery of gold, the costs associated with such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.
該公司在沒有完成證明經濟和技術可行性的可行性研究的情況下做出了桑塔納金礦的生產決定。因此,實現計劃產量水平、預計的黃金回收率、與這種回收相關的成本,包括與開發商業可開採礦牀相關的風險增加的不確定性可能會增加。從歷史上看,此類項目發生經濟和技術故障的風險要高得多。
For Further Information Please Contact:
欲了解更多信息,請聯繫:
Minera Alamos
阿拉莫斯礦工
Doug Ramshaw, President
Tel: 604-600-4423
Email: dramshaw@mineraalamos.com
道格·拉姆肖,總裁
電話:604-600-4423
電子郵件:dramshaw@mineraalamos.com
Victoria Vargas de Szarzynski, VP Investor Relations
Tel: 289-242-3599
Email: vvargas@mineraalamos.com
維多利亞·瓦爾加斯·德·薩欽斯基,投資者關係副總裁
電話:289-242-3599
電子郵件:vvargas@mineraalamos.com
Website:
網站:
About Minera Alamos Inc.
關於 Minera Alamos Inc.
Minera Alamos is a gold production and development Company. The Company has a portfolio of high-quality Mexican assets, including the 100%-owned Santana open-pit, heap-leach mine in Sonora that is currently going through the start-up of operations at the new Nicho Main deposit. The 100%-owned Cerro de Oro oxide gold project in northern Zacatecas has considerable past drilling and metallurgical work completed and the proposed mining project is currently being guided through the permitting process by the Company's permitting consultants. The La Fortuna open pit gold project in Durango (100%-owned) has a positive, robust preliminary economic assessment (PEA) completed, and the main Federal permits are in place. Minera Alamos is built around its operating team that together brought three open pit heap leach gold mines into successful production in Mexico over the last 13 years.
阿拉莫斯礦業公司是一家黃金生產和開發公司。該公司擁有大量高質量的墨西哥資產,包括位於索諾拉州的桑塔納露天堆浸礦,該礦目前正在新的Nicho Main礦牀啓動運營。位於薩卡特卡斯州北部的Cerro de Oro氧化金項目過去已經完成了大量的鑽探和冶金工作,擬議的採礦項目目前正在公司的許可顧問的指導下完成許可程序。杜蘭戈的La Fortuna露天黃金項目(100% 持股)已經完成了積極、穩健的初步經濟評估(PEA),主要的聯邦許可證已經到位。Minera Alamos是圍繞其運營團隊建立的,在過去的13年中,該團隊共同使墨西哥的三個露天堆浸金礦成功生產。
The Company's strategy is to develop very low capex assets while expanding the projects' resources and continuing to pursue complementary strategic acquisitions.
該公司的戰略是開發非常低的資本支出資產,同時擴大項目資源並繼續進行補充性戰略收購。
Caution Regarding Forward-Looking Statements
關於前瞻性陳述的注意事項
This news release may contain forward-looking information and Minera Alamos cautions readers that forward-looking information is based on certain assumptions and risk factors that could cause actual results to differ materially from the expectations of Minera Alamos included in this news release. This news release includes certain "forward-looking statements", which often, but not always, can be identified by the use of words such as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". These statements are based on information currently available to Minera Alamos and Minera Alamos provides no assurance that actual results will meet management's expectations. Forward-looking statements include timing, cost estimates and statements with respect to Minera Alamos' future plans, objectives and goals with respect to the Cerro de Oro gold mine including the receipt of permits and construction timeline, and the satisfaction by the Company of the closing conditions to draw the Remaining Amount. Since forward-looking statements are based on assumptions and address future events and conditions that, by their very nature involve inherent risks and uncertainties. Actual results relating to, among other things, results of exploration, the economics of processing methods, project development, reclamation and capital costs of Minera Alamos' mineral properties, the ability to complete a preliminary economic assessment which supports the technical and economic viability of mineral production could differ materially from those currently anticipated in such statements for many reasons. Minera Alamos' financial condition and prospects could differ materially from those currently anticipated in such statements for many reasons such as: an inability to finance and/or complete an updated resource and reserve estimate and a preliminary economic assessment which supports the technical and economic viability of mineral production; changes in general economic conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation, legislative, environmental and other judicial, regulatory, political and competitive developments; technological and operational difficulties encountered in connection with Minera Alamos' activities; and other matters discussed in this news release and in filings made with securities regulators. This list is not exhaustive of the factors that may affect any of Minera Alamos' forward-looking statements. These and other factors should be considered carefully, and readers should not place undue reliance on Minera Alamos' forward-looking statements. Minera Alamos does not undertake to update any forward-looking statement that may be made from time to time by Minera Alamos or on its behalf, except in accordance with applicable securities laws.
本新聞稿可能包含前瞻性信息,Minera Alamos提醒讀者,前瞻性信息基於某些假設和風險因素,這些假設和風險因素可能導致實際業績與本新聞稿中對Minera Alamos的預期存在重大差異。本新聞稿包括某些 「前瞻性陳述」,這些陳述通常但並非總是可以通過使用 「相信」、「預期」、「期望」、「估計」、「可能」、「可能」、「將」、「將」 或 「計劃」 等詞語來識別。這些聲明基於Minera Alamos目前獲得的信息,Minera Alamos並不能保證實際業績將符合管理層的預期。前瞻性陳述包括時機、成本估算和與Minera Alamos有關Cerro de Oro金礦的未來計劃、目的和目標的陳述,包括許可證的獲得和施工時間表,以及公司對提取剩餘金額的成交條件的滿意程度。由於前瞻性陳述基於假設,涉及未來的事件和狀況,這些事件和條件本質上涉及固有的風險和不確定性。與勘探結果、加工方法的經濟學、阿拉莫斯礦產地產的項目開發、開墾和資本成本以及完成支持礦物生產技術和經濟可行性的初步經濟評估的能力等相關的實際結果可能與此類聲明中目前的預期存在重大差異,原因有很多。Minera Alamos的財務狀況和前景可能與此類報表中目前的預期存在重大差異,原因有很多,例如:無法融資和/或完成最新的資源和儲量估算以及支持礦產生產技術和經濟可行性的初步經濟評估;總體經濟狀況和金融市場狀況的變化;礦產需求和價格的變化;訴訟、立法、環境和其他司法、監管、政治和競爭情況事態發展;與Minera Alamos的活動相關的技術和運營困難;以及本新聞稿和向證券監管機構提交的文件中討論的其他事項。該清單並未詳盡列出可能影響Minera Alamos任何前瞻性陳述的因素。應仔細考慮這些因素和其他因素,讀者不應過分依賴Minera Alamos的前瞻性陳述。除非根據適用的證券法,否則Minera Alamos不承諾更新Minera Alamos或代表其不時發表的任何前瞻性陳述。
The Company does not have a feasibility study of mineral reserves, demonstrating economic and technical viability for the Santana project, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.
該公司沒有礦產儲量可行性研究,這表明桑塔納項目的經濟和技術可行性,因此,實現任何特定礦產回收水平或回收成本的不確定性可能會增加,包括與開發商業可開採礦牀相關的風險增加。從歷史上看,此類項目發生經濟和技術故障的風險要高得多。
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
多倫多證券交易所及其監管服務提供商(該術語在多倫多證券交易所風險投資交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。