VANCOUVER, British Columbia, Dec. 04, 2024 (GLOBE NEWSWIRE) -- West Red Lake Gold Mines Ltd. ("West Red Lake Gold" or the "Company") (TSXV: WRLG) (OTCQB: WRLGF) is pleased to provide an operations update on restart readiness activities at its 100% owned Madsen Mine project in the Red Lake Gold District of Northwestern Ontario, Canada.

不列顛哥倫比亞省溫哥華,2024年12月4日(GLOBE NEWSWIRE)——西紅湖金礦有限公司(「西紅湖金礦」 或 「公司」)(多倫多證券交易所股票代碼:WRLG)(OTCQB:WRLGF)很高興提供其位於加拿大安大略省西北部紅湖金區的全資持股的Madsen Mine項目的重啓準備活動的最新運營情況。

"As we push towards our goal of restarting the Madsen Mine next year, the team continues to make great progress on achieving key operational readiness milestones," said Shane Williams, President and CEO. "Access development for test mining has been underway since late summer, putting us on the edge of mining. The bulk samples generated through the test mining program will be stockpiled on surface and then batch processed. Meanwhile the Connection Drift, primary crusher, and camp projects are being completed on schedule while definition drilling and mine planning and optimization continue.

總裁兼首席執行官謝恩·威廉姆斯表示:「在我們努力實現明年重啓Madsen礦山的目標的過程中,該團隊在實現關鍵的運營準備里程碑方面繼續取得長足的進展。」“自夏末以來,試採的准入開發一直在進行中,這使我們處於採礦的邊緣。通過試採計劃生成的批量樣品將儲存在地面上,然後進行批量處理。同時,Connection Drift、初級破碎機和營地項目正在按計劃完成,同時定義鑽探、礦山規劃和優化仍在繼續。

"The entire WRLG team has been collectively working towards a successful restart of the Madsen mine. We are now approaching the finish line on many of the fundamental pieces that support this goal, including final optimization on the pre-feasibility study, completing key capital projects, mining our first underground stopes, and starting up the mill. It is a very exciting time for WRLG as we make the transition from developer to producer."

「整個WRLG團隊一直在共同努力,以成功重啓Madsen礦山。現在,支持這一目標的許多基本要素已接近終點,包括預可行性研究的最終優化、關鍵資本項目的完成、我們的第一個地下采礦點以及啓動工廠。對於WRLG來說,這是一個非常激動人心的時刻,因爲我們正在從開發者過渡到製作人。」

Connection Drift 50% Complete

連接漂移已完成 50%

The Connection Drift, the largest of the capital projects supporting restart of the Madsen Mine, is 50% complete and is on track for completion by the end of March 2025.

Connection Drift是支持麥德森礦重啓的最大資本項目,已完成50%,有望在2025年3月底之前完成。

The Connection Drift is a 1.2-km haulage way connecting the historic West Portal, which through extensive underground workings provides access to most parts of the Madsen mine including the Austin, South Austin, and McVeigh zones, and the East Portal, a modern portal from which development only extends a modest distance into the North Austin area.

Connection Drift 是一條 1.2 公里長的運輸方式,連接歷史悠久的西部入口,通過廣泛的地下施工,可以進入麥德森礦山的大部分地區,包括奧斯汀、南奧斯汀和麥克維區域,以及東方門戶,這是一個現代化的門戶,開發區僅向北奧斯汀地區延伸一小段距離。

The prior operator developed the East Portal and workings early in its construction effort but soon shifted to the less capital-intensive approach of using the historic West Portal.

之前的運營商在施工初期就開發了東方門戶並進行了運作,但很快轉向了使用歷史悠久的西部門戶的資本密集程度較低的方法。

West Red Lake Gold found notable inefficiencies in using the West Portal for moving mined material, including:

West Red Lake Gold發現,使用西部傳送開採物資的效率明顯不足,包括:

  • The portal is relatively small, limiting hauling to 30-tonne trucks.
  • The haulage ways descending from the West Portal were developed over many years of historic operations; an array of steep sections and sharp corners make the route relatively inefficient for trucking.
  • The route from the portal to the mill crosses two public roads and goes past the town of Madsen. Material must be dumped out of underground haul truck and reloaded into surface-insured trucks and only hauled during daylight hours (because of noise restrictions) to use this route.
  • Much of the resource at Madsen sits spatially under the mill. Moving it west to bring it up through the West Portal and then driving it back east to the mill adds kilometres of trucking distance.
  • 該入口相對較小,僅限於運輸30噸的卡車。
  • 從西部入口向下的運輸方式是在多年的歷史運營中開發出來的;一系列陡峭的路段和尖角使這條路線的卡車運輸效率相對較低。
  • 從入口到磨坊的路線穿過兩條公共道路,穿過麥德森鎮。物資必須從地下運輸卡車中傾倒出來,然後裝上地面保險的卡車,並且只能在白天(由於噪音限制)拖運才能使用這條路線。
  • Madsen的大部分資源在空間上都位於工廠下方。向西移動使其穿過西部入口,然後將其向東行駛回磨坊,會增加數公里的卡車運輸距離。

The East Portal, by contrast, is a large portal with modern workings. It can accommodate 60-tonne trucks, the haulage route within the mine was designed with efficiency in mind, and the East Portal is beside the primary crusher, which is close to the mill.

相比之下,東方門戶是一個具有現代化運作方式的大型門戶。它可以容納 60 噸的卡車,礦山內的運輸路線在設計時考慮到了效率,East Portal 位於主破碎機旁邊,離磨機很近。

The Connection Drift will allow West Red Lake Gold to move all mined material out through the East Portal, eliminating the inefficiencies of the West Portal (which will remain open for ventilation and emergency access).

連接漂移將允許西紅湖黃金將所有開採的材料通過東部傳送門運出,從而消除西部入口(西部門戶將繼續開放,便於通風和緊急進入)的效率低下。

West Red Lake Gold raised $10 million in Canadian Development Expense flow through funds to finance this major project. Work started in August 2024.

West Red Lake Gold通過資金籌集了1000萬美元的加拿大開發費用,爲這個重大項目提供資金。工作於 2024 年 8 月開始。

"The Connection Drift is a key project as we prepare to mine, for several reasons," said Maurice Mostert, Vice President Technical Services. "It is creating an efficient way to move material, the effort to develop it is giving our mining teams valuable experience working accurately and effectively underground at Madsen, and it is unlocking the potential to drill test some prospective targets.

技術服務副總裁莫里斯·莫斯特說:「Connection Drift是我們準備挖礦時的一個關鍵項目,原因有很多。」“它創造了一種高效的物料運輸方式,開發它的努力爲我們的採礦團隊提供了在Madsen準確、高效地進行地下工作的寶貴經驗,並且它釋放了鑽探測試一些潛在目標的潛力。

"Investing in capital projects to create an efficient operation before we restart this mine is one of the key pillars of our Madsen thesis, which is that an efficient mine tapping a well-drilled and understood resource in appropriate ways will be very much worth the effort."

「在我們重啓該礦山之前,投資資本項目以實現高效運營,這是我們Madsen理念的關鍵支柱之一,即一個高效的礦山以適當的方式利用經過良好鑽探和了解的資源將非常值得付出努力。」

The Connection Drift is on track for its targeted completion date in late March. To date 604.8 metres have been completed, of the 1.2 km total length.

Connection Drift的目標完成日期定在3月下旬。迄今爲止,在總長度1.2公里中,已經完成了604.8米。

Figure 1. A view of the Connection Drift, which is progressing west to east. This 1.2-km haulage way is now 50% complete.

圖 1。連接漂移的視圖,它正在從西向東移動。這條 1.2 公里的運輸方式現已完成 50%。

Primary Crusher Commissioned

初級破碎機投入使用

The primary crusher was delivered to the Madsen Mine site on November 5, 2024. It was unloaded, assembled, and has now been commissioned.

初級破碎機於 2024 年 11 月 5 日交付到 Madsen 礦場。它已卸載、組裝,現已投入使用。

"A fully functioning and reliable primary crusher is a good example of the kind of capital investments we are making to support efficient operations when we restart the Madsen Mine," said Williams. "It is exciting to see the crusher processing material as we commission this key piece of infrastructure."

威廉姆斯說:「功能齊全且可靠的初級破碎機就是一個很好的例子,說明我們在重啓Madsen礦山時爲支持高效運營而進行的資本投資。」「在我們調試這一關鍵基礎設施時,看到破碎機加工材料真是令人興奮。」

Figure 2. The CRJ3042 Electric Primary Jaw Crushing Plant being commissioned at the Madsen Mine site in late November.

圖 2。CRJ3042 電動初級顎式破碎設備於 11 月下旬在 Madsen 礦場投入使用。

Camp Installation

夏令營裝置

The camp was delivered on November 11, 2024 and is now being installed at the Madsen Mine site.

該營地於2024年11月11日交付,目前正在馬德森礦場安裝。

The camp is a 114-person facility. It offers individual rooms with ensuite bathrooms for each worker, a kitchen and dining hall, and recreation space.

該營地是一個可容納114人的設施。它爲每位員工提供帶獨立浴室的獨立房間、廚房和餐廳以及娛樂空間。

Horizon North, an industry leader in providing accommodations and services to meet workforce requirements within the mining industry in Canada, supplied and will staff the camp facility.

Horizon North是提供住宿和服務以滿足加拿大采礦業勞動力需求的行業領導者,該公司提供了營地設施並將爲其配備人員。

Figure 3. The 114-person workforce accommodations facility for the Madsen Mine project during the unloading and installation process.

圖 3.在卸貨和安裝過程中,Madsen 礦山項目可容納 114 人的員工住宿設施。

QUALIFIED PERSON

合格的人

The technical information presented in this news release has been reviewed and approved by Maurice Mostert, P.Eng., Vice President of Technical Services for West Red Lake Gold and the Qualified Person for technical services at the West Red Lake Project, as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects.

根據國家儀器43-101礦業項目披露標準,本新聞稿中提供的技術信息已由工程師莫里斯·莫斯特進行了審查和批准,他是西紅湖黃金技術服務副總裁兼西紅湖項目技術服務合格人士。

ABOUT WEST RED LAKE GOLD MINES

關於西紅湖金礦

West Red Lake Gold Mines Ltd. is a mineral exploration company that is publicly traded and focused on advancing and developing its flagship Madsen Gold Mine and the associated 47 km2 highly prospective land package in the Red Lake district of Ontario. The highly productive Red Lake Gold District of Northwest Ontario, Canada has yielded over 30 million ounces of gold from high-grade zones and hosts some of the world's richest gold deposits. WRLG also holds the wholly owned Rowan Property in Red Lake, with an expansive property position covering 31 km2 including three past producing gold mines – Rowan, Mount Jamie, and Red Summit.

West Red Lake Gold Mines Ltd. 是一家上市的礦產勘探公司,專注於推進和開發其旗艦麥德森金礦以及相關的位於安大略省紅湖區的47平方公里極具前景的土地一攬子計劃。加拿大安大略省西北部的高產紅湖金礦區已從高品位區開採了超過3000萬盎司的黃金,並擁有一些世界上最豐富的金礦。WRLG還持有位於紅湖的全資羅文地產,其廣闊的土地佔地31平方公里,包括過去生產的三個金礦——羅文、傑米山和雷德薩米特。

ON BEHALF OF WEST RED LAKE GOLD MINES LTD.
"Shane Williams"
Shane Williams
President & Chief Executive Officer

代表西紅湖金礦有限公司
「Shane Williams」
肖恩·威廉姆斯
總裁兼首席執行官

FOR FURTHER INFORMATION, PLEASE CONTACT:

欲了解更多信息,請聯繫:

Gwen Preston
Vice President Communications
Tel: (604) 609-6132
Email: investors@wrlgold.com or visit the Company's website at

格溫·普雷斯頓
傳播副總裁
電話:(604) 609-6132
電子郵件:investors@wrlgold.com 或訪問公司的網站

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多倫多證券交易所風險投資交易所及其監管服務提供商(該術語在多倫多證券交易所風險投資交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

CAUTIONARY STATEMENT AND FORWARD-LOOKING INFORMATION

警示聲明和前瞻性信息

The decision to continue with the advancement of the Madsen Mine restart and the Company's operations and plans with respect thereto, as described herein (the "Madsen Mine Restart"), are based on economic models prepared by the Company in conjunction with management's knowledge of the property and the existing estimate of indicated and inferred mineral resources on the property set out in the report entitled, "Independent NI 43-101 Technical Report and Updated Mineral Resource Estimate for the PureGold Mine, Canada", with an effective date of July 31, 2022, as amended on April 24, 2024, a copy of which is available on SEDAR+ at . The Madsen Mine Restart is not based on a preliminary economic assessment, a pre-feasibility study or a feasibility study of mineral reserves demonstrating economic and technical viability. Accordingly, there is increased uncertainty and economic and technical risks of failure associated with the Madsen Mine Restart, in particular: the risk that mineral grades will be lower than expected; the risk that additional ongoing mining operations are more difficult or more expensive than expected; and the risk that production and economic variables may vary considerably, due to the absence of a detailed economic and technical analysis undertaken in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects.

如本文所述,繼續推進Madsen礦山重啓以及公司的運營和相關計劃(「Madsen礦山重啓」)的決定是基於公司制定的經濟模型,以及管理層對該物業的了解以及標題爲 「北愛爾蘭獨立43-101技術報告和PureGold最新礦產資源估算」 的報告中對該物業指示和推斷礦產資源的現有估計。我的,加拿大”,生效日期爲2022年7月31日,即於 2024 年 4 月 24 日修訂,其副本可在 SEDAR+ 上查閱,網址爲。重啓麥德森礦山並非基於初步經濟評估、預可行性研究或對錶明經濟和技術可行性的礦產儲量可行性研究。因此,與Madsen礦山重啓相關的不確定性以及失敗的經濟和技術風險增加,特別是:礦物等級低於預期的風險;正在進行的額外採礦作業比預期更困難或更昂貴的風險;由於缺乏根據國家儀器43-101——礦產項目披露標準進行詳細的經濟和技術分析,生產和經濟變量可能存在很大差異的風險。

Certain statements contained in this news release may constitute "forward-looking information" within the meaning of applicable securities laws. Forward-looking information generally can be identified by words such as "anticipate", "expect", "estimate", "forecast", "planned", and similar expressions suggesting future outcomes or events. Forward-looking information is based on current expectations of management; however, it is subject to known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from the forward-looking information in this news release and include without limitation, statements relating to plans for the potential restart of mining operations at the Madsen Mine, the potential of the Madsen Mine; any untapped growth potential in the Madsen deposit or Rowan deposit; and the Company's future objectives and plans. Readers are cautioned not to place undue reliance on forward-looking information.

本新聞稿中包含的某些陳述可能構成適用證券法所指的 「前瞻性信息」。前瞻性信息通常可以通過 「預期」、「預期」、「估計」、「預測」、「計劃」 等詞語以及暗示未來結果或事件的類似表述來識別。前瞻性信息基於管理層當前的預期;但是,它受已知和未知的風險、不確定性和其他因素的影響,這些因素可能導致實際業績與本新聞稿中的前瞻性信息存在重大差異,包括但不限於與麥德森礦可能重啓採礦業務的計劃、麥德森礦的潛力、麥德森礦牀或羅文礦牀中任何未開發的增長潛力以及公司未來目標有關的聲明計劃。提醒讀者不要過分依賴前瞻性信息。

Forward-looking information involve numerous risks and uncertainties and actual results might differ materially from results suggested in any forward-looking information. These risks and uncertainties include, among other things, market volatility; the state of the financial markets for the Company's securities; fluctuations in commodity prices; timing and results of the cleanup and recovery at the Madsen Mine; and changes in the Company's business plans. Forward-looking information is based on a number of key expectations and assumptions, including without limitation, that the Company will continue with its stated business objectives and its ability to raise additional capital to proceed. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such forward-looking information. Accordingly, readers should not place undue reliance on forward-looking information. Readers are cautioned that reliance on such information may not be appropriate for other purposes. Additional information about risks and uncertainties is contained in the Company's management's discussion and analysis for the year ended November 30, 2023, and the Company's annual information form for the year ended November 30, 2023, copies of which are available on SEDAR+ at .

前瞻性信息涉及許多風險和不確定性,實際結果可能與任何前瞻性信息中建議的結果存在重大差異。除其他外,這些風險和不確定性包括市場波動;公司證券的金融市場狀況;大宗商品價格的波動;清理和恢復麥德森礦的時間和結果;以及公司業務計劃的變化。前瞻性信息基於許多關鍵預期和假設,包括但不限於公司將繼續實現其既定業務目標及其籌集額外資金以繼續前進的能力。儘管公司管理層試圖確定可能導致實際業績與前瞻性信息中包含的業績存在重大差異的重要因素,但可能還有其他因素導致業績與預期、估計或預期不符。無法保證此類前瞻性信息會被證明是準確的,因爲實際結果和未來事件可能與此類前瞻性信息中的預期存在重大差異。因此,讀者不應過分依賴前瞻性信息。請讀者注意,依賴此類信息可能不適合用於其他目的。有關風險和不確定性的其他信息包含在公司管理層對截至2023年11月30日的年度的討論和分析以及公司截至2023年11月30日的年度信息表中,其副本可在SEDAR+上查閱,網址爲。

The forward-looking information contained herein is expressly qualified in its entirety by this cautionary statement. Forward-looking information reflects management's current beliefs and is based on information currently available to the Company. The forward-looking information is made as of the date of this news release and the Company assumes no obligation to update or revise such information to reflect new events or circumstances, except as may be required by applicable law.

本警示聲明明確規定了此處包含的前瞻性信息的全部限定。前瞻性信息反映了管理層當前的信念,並基於公司目前獲得的信息。前瞻性信息是自本新聞稿發佈之日起發佈的,除非適用法律要求,否則公司沒有義務更新或修改此類信息以反映新的事件或情況。

For more information on the Company, investors should review the Company's continuous disclosure filings that are available on SEDAR+ at .

有關公司的更多信息,投資者應查看公司的持續披露文件,該文件可在SEDAR+上查閱,網址爲。

Images accompanying this announcement are available at:

本公告附帶的圖片可在以下網址獲取:


声明:本內容僅用作提供資訊及教育之目的,不構成對任何特定投資或投資策略的推薦或認可。 更多信息
    搶先評論