Secured high-performance computing (HPC) data center leases with Core42 for more than 70 MW of digital infrastructure, representing total revenue of more than $1 billion over initial 10-year term
Earned 158 self-mined bitcoin in December for a total of 2,728 bitcoin year-to-date and 423 in Q4 2024
Achieved 9.7 EH/s of installed self-mining capacity, a 94% year-over-year increase
EASTON, Md., Jan. 03, 2025 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) ("TeraWulf" or the "Company"), a leading owner and operator of vertically integrated, next-generation digital infrastructure powered by predominantly zero-carbon energy, today provided its unaudited monthly production and operations update for December 2024.
December 2024 Production and Operations Highlights
- Bitcoin Production: Self-mined 158 bitcoin, with an average daily production rate of approximately 5.1 bitcoin.
- Operating Capacity: Achieved 9.7 EH/s of installed self-mining capacity, a 94.0% year-over-year increase.
- Power Costs: Achieved an average power cost of $62,805 per bitcoin mined, equivalent to approximately $0.078/kWh, excluding proceeds from demand response and ancillary services.
Key Metrics1 | December 2024 | November 2024 |
Bitcoin Self-Mined | | 158 | | | 115 | |
Value per Bitcoin Self-Mined2 | $ | 98,326 | | $ | 83,947 | |
Power Cost per Bitcoin Self-Mined | $ | 62,805 | | $ | 41,190 | |
Avg. Operating Hash Rate (EH/s)3 | | 8.4 | | | 5.9 | |
Nameplate Miner Efficiency (J/TH)4 | | 19.2 | | | 19.2 | |
Management Commentary
"In December, we finalized data center lease agreements totaling over 70 MW of our infrastructure, representing a potential revenue opportunity exceeding $1 billion over the initial 10-year terms," said Paul Prager, TeraWulf's Chief Executive Officer. "These agreements are a significant milestone for TeraWulf, not only representing our entry into HPC hosting but also demonstrating the immense value of our sustainable and scalable digital infrastructure."
Prager added, "We are in active discussions with additional tenants to utilize the remaining 178 MW of near-term HPC hosting capacity at Lake Mariner, including our inaugural partner, Core42. Core42 retains a time-limited option for an additional 135 MW of capacity to be delivered in early 2026, further emphasizing the growing demand for our low-cost, predominantly zero-carbon infrastructure. In parallel, we are evaluating strategic site acquisition opportunities to extend our footprint beyond the 750 MW potential at Lake Mariner, solidifying our leadership in the next generation of digital infrastructure."
Production and Operations Update
TeraWulf's commitment to operational excellence and sustainability continues to drive its growth across the Company's bitcoin mining and HPC hosting businesses.
As of December 31, 2024, TeraWulf's operational bitcoin mining capacity was 195 MW with an installed self-mining hash rate of approximately 9.7 EH/s. December's average hash rate was 8.4 EH/s, reflecting performance tuning to optimize margins in a higher winter power price environment. Construction of miner building 5 (MB-5, 50 MW) is proceeding on schedule, with foundation pours completed and building framing underway, with target completion in mid Q1 2025.
On the WULF Compute front, under the recently announced data center lease agreements, TeraWulf will deliver more than 70 MW of turn-key data center infrastructure to host Core42's HPC operations at the Lake Mariner facility in Upstate New York. The infrastructure will include the WULF Den (2.5 MW), CB-1 (20 MW), and CB-2 (50 MW), which have all been fully funded.
About TeraWulf
TeraWulf develops, owns, and operates environmentally sustainable, next-generation data center infrastructure in the United States, specifically designed for Bitcoin mining and high-performance computing. Led by a team of seasoned energy entrepreneurs, the Company owns and operates the Lake Mariner facility situated on the expansive site of a now retired coal plant in Western New York. Currently, TeraWulf generates revenue primarily through Bitcoin mining, leveraging predominantly zero-carbon energy sources, including hydroelectric and nuclear power. Committed to environmental, social, and governance (ESG) principles that align with its business objectives, TeraWulf aims to deliver industry-leading economics in mining and data center operations at an industrial scale.
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as "plan," "believe," "goal," "target," "aim," "expect," "anticipate," "intend," "outlook," "estimate," "forecast," "project," "continue," "could," "may," "might," "possible," "potential," "predict," "should," "would" and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf's management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) conditions in the cryptocurrency mining industry, including fluctuation in the market pricing of bitcoin and other cryptocurrencies, and the economics of cryptocurrency mining, including as to variables or factors affecting the cost, efficiency and profitability of cryptocurrency mining; (2) competition among the various providers of cryptocurrency mining services; (3) changes in applicable laws, regulations and/or permits affecting TeraWulf's operations or the industries in which it operates, including regulation regarding power generation, cryptocurrency usage and/or cryptocurrency mining, and/or regulation regarding safety, health, environmental and other matters, which could require significant expenditures; (4) the ability to implement certain business objectives and to timely and cost-effectively execute integrated projects; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to growth strategies or operations; (6) loss of public confidence in bitcoin or other cryptocurrencies and the potential for cryptocurrency market manipulation; (7) adverse geopolitical or economic conditions, including a high inflationary environment; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability, delivery schedule and cost of equipment necessary to maintain and grow the business and operations of TeraWulf, including mining equipment and infrastructure equipment meeting the technical or other specifications required to achieve its growth strategy; (10) employment workforce factors, including the loss of key employees; (11) litigation relating to TeraWulf and/or its business; and (12) other risks and uncertainties detailed from time to time in the Company's filings with the Securities and Exchange Commission ("SEC"). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company's filings with the SEC, which are available at www.sec.gov.
Investors:
Investors@terawulf.com
Media:
media@terawulf.com
1 All figures except Bitcoin Self-Mined are estimates and remain subject to standard month-end adjustments.
2 Computed as the weighted-average opening price of bitcoin on each respective day the Bitcoin Self-Mined is earned.
3 While nameplate mining inventory as of December 31, 2024 for Lake Mariner is estimated at 9.7 EH/s, actual monthly hash rate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICs due to adverse weather and ASIC maintenance and repair. Performance in November was impacted by planned outage for electrical upgrades and miner fleet upgrade work.
4 Nameplate miner efficiency excludes auxiliary load.
Core42との間で、高性能コンピューティング(HPC)IDC関連のリースを確保し、70MWを超えるデジタルインフラ関連を構築し、初回の10年間で10億ドルを超える売上高を表しています
12月に158の自己採掘ビットコインを獲得し、年初来で合計2,728ビットコイン、2024年第4四半期で423ビットコインとなりました
自己採掘能力が9.7 EH/sに達し、前年同期比で94%の増加を記録しました
メリーランド州イーストン、2025年1月3日(グローブニュースワイヤー) -- テラウルフ社(ナスダック:WULF)("テラウルフ"または"会社")は、主にゼロカーボンエネルギーで動く垂直統合型次世代デジタルインフラストラクチャの主要な所有者およびオペレーターであり、2024年12月の監査なしの月次生産および業務更新を提供しました.
2024年12月の生産と運営のハイライト
- ビットコイン生産:自社で158ビットコインをマイニングし、平均日産5.1ビットコインの生産率を達成。
- 稼働能力:自己マイニングの設置能力は9.7 EH/sに達し、前年同期比94.0%の増加。
- 電力コスト:マイニングされたビットコインあたり平均電力コストは$62,805で、約$0.078/kWhに相当し、需要応答および付随サービスからの収益は含まれていない。
主要指標1 | 2024年12月 | 2024年11月 |
ビットコインの自己採掘 | | 158 | | | 115 | |
セルフマイニング1ビットコインあたりの価値2 | $ | 98,326 | | $ | 83,947 | |
Bitcoin自己採掘当量あたりの電力コスト | $ | 62,805 | | $ | 41,190 | |
平均稼働ハッシュレート (EH/s)3 | | 8.4 | | | 5.9 | |
ネームプレートマイナー効率 (J/TH)4 | | 19.2 | | | 19.2 | |
経営陣のコメント
「12月に、私たちは70MW以上のインフラ関連のデータセンターのリース契約を締結し、初期の10年間で10億ドルを超える売上高の機会を示しています」とテラウルフの最高経営責任者であるポール・プラガーは述べました。「これらの契約は、テラウルフにとって重要なマイルストーンであり、HPCホスティングへの参入だけでなく、私たちの持続可能でスケーラブルなデジタルインフラストラクチャの巨大な価値を示しています。」
プラガーは次のように追加しました。「私たちは、初のパートナーであるCore42を含む、Lake Marinerでの残りの178 MWの近接HPCホスティング容量を利用するための追加テナントとの積極的な議論を行っています。Core42は、2026年初頭に提供される追加の135 MWの容量に対して、時間限定のオプションを保持しており、私たちの低コストで主にゼロカーボンのインフラストラクチャに対する需要の高まりをさらに強調しています。同時に、私たちはLake Marinerでの750 MWの潜在能力を超えて足跡を広げるための戦略的なサイト買収の機会を評価しており、次世代のデジタルインフラストラクチャにおけるリーダーシップを固めています。」
生産および運営の更新
テラウルフの運営の卓越性と持続可能性へのコミットメントは、同社のビットコインマイニングおよびHPCホスティングビジネス全体での成長を促進し続けています。
2024年12月31日現在、テラウルフの運営ビットコインマイニング能力は195 MWで、約9.7 EH/sの自己マイニングハッシュレートが設置されています。12月の平均ハッシュレートは8.4 EH/sで、より高い冬の電力価格環境でのマージンを最適化するためのパフォーマンス調整を反映しています。マイナー建物5(Mb-5、50 MW)の建設は予定通り進んでおり、基礎のコンクリート打設が完了し、建物のフレーミングが進行中で、2025年第1四半期中の完了を目指しています。
WULFコンピュートに関して、最近発表されたIDC関連リース契約に基づき、テラウルフはニューヨーク州上北部のレイクマリナー施設でCore42のHPC運用をホストするために、70 MWを超えるターンキーのIDC関連インフラを提供します。インフラには、WULF Den(2.5 MW)、Cb-1(20 MW)、Cb-2(50 MW)が含まれ、すべて完全に資金提供されています。
テラウルフについて
テラウルフは、アメリカ合衆国において、ビットコインマイニングと高性能コンピューティングのために特別に設計された環境に優しい次世代IDC関連インフラを開発、所有、運営しています。経験豊富なエネルギー起業家チームによって運営されており、同社はニューヨーク州西部の退役した石炭プラントの広大な敷地にあるレイクマリナー施設を所有・運営しています。現在、テラウルフは主にビットコインマイニングを通じて売上高を生成しており、主に水力発電と原子力発電を含むゼロカーボンエネルギー源を活用しています。環境、社会、およびガバナンス(ESG)の原則に基づくコミットメントがビジネス目標と一致しており、テラウルフは業種の中で、マイニングとIDC関連運営において業界最先端の経済性を提供することを目指しています。
将来の見通しに関する声明
本プレスリリースには、1995年のプライベート・セキュリティ訴訟改革法の「セーフハーバー」条項の意味の範囲内での将来の展望に関する記述が含まれています。このような将来の展望に関する記述には、予想される将来の出来事や歴史的事実ではない期待に関する記述が含まれています。歴史的事実の記述以外のすべての記述は、将来の展望に関する記述と見なされる可能性のある記述です。さらに、将来の展望に関する記述は、通常、「計画」、「信じる」、「目標」、「ターゲット」、「目指す」、「期待する」、「予想する」、「意図する」、「見込み」、「見積もり」、「予測」、「プロジェクト」、「継続する」、「可能性」、「かもしれない」、「予測する」、「すべき」、「されるべき」、「可能性のある」、「潜在的な」およびその他の類似した語や表現によって識別されますが、これらの語や表現が欠如している場合でも、その記述が将来の見通しではないわけではありません。将来の展望に関する記述は、テラウルフの経営陣の現在の期待と信念に基づいており、さまざまな要因、リスク、不確実性および仮定に本質的に影響され、その潜在的な効果があります。将来の展開が予想されたものであるという保証はありません。実際の結果は、将来の見通しに関する記述によって表現されるまたは示唆されるものから大きく異なる場合があります。これには、次のようなさまざまな要因、リスク、不確実性および仮定が含まれます。(1) ビットコインやその他の暗号通貨の市場価格の変動を含む、暗号通貨マイニング業界の条件、暗号通貨マイニングのコスト、効率、収益性に影響を与える変数または要因を含む経済学。(2) 暗号通貨マイニングサービスの各プロバイダー間の競争。(3) テラウルフの事業またはその事業が展開される業界に影響を及ぼす適用法、規制及び/または許可の変更、発電、暗号通貨の使用及び/または暗号通貨マイニングに関する規制、安全、健康、環境及びその他の事項に関する規制が含まれ、これはかなりの支出を必要とする可能性があります。(4) 特定のビジネス目標を実施する能力及び統合プロジェクトをタイムリーかつコスト効率よく実行する能力。(5) 成長戦略または運営に関して、タイムリーにかつ妥当な条件で十分な資金を調達できないこと。(6) ビットコインまたはその他の暗号通貨に対する公共の信頼の喪失及び暗号通貨市場の操作の可能性。(7) 高いインフレ状況を含む逆風的な地政学的または経済的条件。(8) サイバー犯罪、マネーロンダリング、マルウェア感染及びフィッシング及び/または機器の故障または破損、自然災害、データセキュリティ侵害、コンピュータの故障またはサボタージュによる損失や干渉の可能性(及び前述のいずれかに関連する費用)。(9) テラウルフの事業を維持し成長させるために必要な機器の入手可能性、納期及びコスト、暗号通貨の成長戦略を達成するために必要な技術的またはその他の仕様を満たすマイニング機器及びインフラ関連機器を含む。(10) 重要な従業員の喪失を含む雇用労働力の要因。(11) テラウルフ及び/またはそのビジネスに関連する訴訟。(12) その他、時々証券取引委員会(「SEC」)への会社の提出書類で詳細に説明されるリスク及び不確実性。潜在的な投資家、株主及びその他の読者は、これらの将来の見通しに関する記述に過度に依存しないように警告されます。これらの記述は、作成された日付に限り有効です。テラウルフは、法律または規制で要求される場合を除き、作成された後に新しい情報、将来のイベントまたはその他の結果出発などに基づいて、いかなる将来の見通しの記述も公に更新する義務を負いません。投資家は、SECへの会社の提出書類に含まれる将来の展望に関する記述及びリスク要因の完全な議論を参照することができ、これらはwww.sec.govで入手可能です。
投資家:
Investors@terawulf.com
メディア:
media@terawulf.com
1 ビットコイン自主管理を除く全ての数値は推定値であり、標準の月末調整の影響を受けることがあります。
ビットコインの自己採掘が得られるそれぞれの日の加重平均始値として計算されます。
2024年12月31日時点でのレイクマリナーの名目採掘在庫は9.7 EH/sと推定されていますが、実際の月間ハッシュレートのパフォーマンスは、効率を向上させてマージンを最大化するためのパフォーマンス調整、信頼性または性能向上のための予定された停電、突発的な停電、さまざまな現金生成需要応答プログラムへの参加による抑制、悪天候によるASICの能力低下およびASICのメンテナンスと修理など、さまざまな要因に依存します。11月のパフォーマンスは、電気のアップグレードとマイナーフリートのアップグレード作業のための予定された停電の影響を受けました。
名目マイナー効率は補助負荷を除外します。