share_log

Lithium Americas | 6-K: Report of foreign private issuer (related to financial reporting)

リチウム アメリカズ | 6-K:海外発行者報告書(決算情報)

SEC ·  2024/08/15 05:25

Moomoo AIのまとめ

Lithium Americas reported Q2 2024 financial results with a cash position of $375.8 million as of June 30, 2024. The company completed a $275 million public offering in April 2024 and received a conditional commitment from the U.S. DOE for a $2.26 billion loan to fund Thacker Pass Phase 1 construction. Net loss for Q2 was $6.3 million compared to net income of $10.9 million in Q2 2023.Construction progress at Thacker Pass continues with site preparation completed and detailed engineering over 30% complete. The company expects to issue full notice to proceed in H2 2024 following DOE loan closing. The project's revised CAPEX estimate is $2.93 billion, with mechanical completion targeted for 2027. In August 2024, the company received an $11.8 million grant from the U.S. Department of Defense for infrastructure development.The company continues advancing its...Show More
Lithium Americas reported Q2 2024 financial results with a cash position of $375.8 million as of June 30, 2024. The company completed a $275 million public offering in April 2024 and received a conditional commitment from the U.S. DOE for a $2.26 billion loan to fund Thacker Pass Phase 1 construction. Net loss for Q2 was $6.3 million compared to net income of $10.9 million in Q2 2023.Construction progress at Thacker Pass continues with site preparation completed and detailed engineering over 30% complete. The company expects to issue full notice to proceed in H2 2024 following DOE loan closing. The project's revised CAPEX estimate is $2.93 billion, with mechanical completion targeted for 2027. In August 2024, the company received an $11.8 million grant from the U.S. Department of Defense for infrastructure development.The company continues advancing its partnership with General Motors, with the GM Tranche 2 Investment of up to $329.9 million expected to close in H2 2024. The Workforce Hub development is progressing, with earthworks completed and infrastructure planning underway. The project has achieved 203,383 work hours without a lost time incident and is expected to create approximately 1,800 construction jobs and 360 permanent operational positions.
リチウムアメリカズは2024年第2四半期の財務結果を発表し、2024年6月30日時点での現金残高は$37580万でした。同社は2024年4月に$27500万の公募を完了し、テッカーパス第1段階の建設資金を調達するために米国エネルギー省から$22.6億の融資に対する条件付きのコミットメントを受けました。第2四半期の当期純利益は$630万で、2023年第2四半期の当期純利益$1090万と比較されました。テッカーパスでの建設進捗は続いており、サイトの準備が完了し、詳細なエンジニアリングが30%以上完了しています。同社は、DOEの融資クローズ後に2024年下半期に全ての進行通知を発行する予定です。プロ...すべて展開
リチウムアメリカズは2024年第2四半期の財務結果を発表し、2024年6月30日時点での現金残高は$37580万でした。同社は2024年4月に$27500万の公募を完了し、テッカーパス第1段階の建設資金を調達するために米国エネルギー省から$22.6億の融資に対する条件付きのコミットメントを受けました。第2四半期の当期純利益は$630万で、2023年第2四半期の当期純利益$1090万と比較されました。テッカーパスでの建設進捗は続いており、サイトの準備が完了し、詳細なエンジニアリングが30%以上完了しています。同社は、DOEの融資クローズ後に2024年下半期に全ての進行通知を発行する予定です。プロジェクトの修正後のCAPEX見積もりは$29.3億で、機械的な完成は2027年を目指しています。2024年8月に、同社は米国国防省からインフラ関連開発のために$1180万の助成金を受け取りました。同社はゼネラルモーターズとのパートナーシップを進展させており、Gmトランシェ2の投資$32990万が2024年下半期にクロージングされる見込みです。労働力ハブの開発が進行中で、土工事が完了し、インフラ計画が進行中です。このプロジェクトは、失われた時間の事故なしで203,383作業時間を達成しており、約1,800の建設職と360の恒久的な運用ポジションを創出する見込みです。
これらの内容は、情報提供及び投資家教育のためのものであり、いかなる個別株や投資方法を推奨するものではありません。 更に詳しい情報