Bear Creek Mining Announces Q4 2023 Mercedes Gold Production of 13,478 Ounces; a 47% Increase Over Previous Quarter
Bear Creek Mining Announces Q4 2023 Mercedes Gold Production of 13,478 Ounces; a 47% Increase Over Previous Quarter
2023 Mercedes Production at High End of Guidance with 43,860 Ounces of Gold Produced
2023 年梅赛德斯产量达到预期的最高水平,黄金产量为 43,860 盎司
Vancouver, British Columbia--(Newsfile Corp. - January 16, 2024) - Bear Creek Mining Corporation (TSXV: BCM) (OTCQX: BCEKF) (BVL: BCM) ("Bear Creek" or the "Company") announces it produced 13,478 ounces of gold and 52,144 ounces of silver from the Mercedes Mine ("Mercedes") during the three months ended December 31, 2023 ("Q4 2023"). Consequently, Mercedes production for 2023 totaled 43,860 ounces of gold and 167,019 ounces of silver, placing it near the high end of the Company's most recent production guidance of 39,000 - 45,000 gold ounces (see Bear Creek news release dated November 24, 2023).
不列颠哥伦比亚省温哥华--(Newsfile Corp.,2024年1月16日)——熊溪矿业公司(TSXV:BCM)(OTCQX:BCEKF)(BVL:BCM)(“Bear Creek” 或 “公司”)宣布,在截至2023年12月31日的三个月(“第四季度”)中,它从梅赛德斯矿(“梅赛德斯”)生产了13,478盎司黄金和52,144盎司白银 3")。因此,梅赛德斯2023年的黄金总产量为43,860盎司黄金和167,019盎司白银,接近该公司最新的39,000至45,000盎司的产量预期的最高水平(见2023年11月24日的熊溪新闻稿)。
Eric Caba, President and CEO of Bear Creek, states, "We are extremely pleased that the efforts we have made at Mercedes to improve production are finally bearing out, with a 47% increase in gold production in Q4 compared to Q3 2023. Q4 2023 saw month-over-month improvements culminating in an output of 5,198 gold ounces in December 2023 - the highest monthly level of gold production at Mercedes since April 2019. We have had to go back to fundamental basics in the mine and focus on increasing development, managing costs, and placing key talent in the right positions. There is still a lot to be done on all fronts, but we believe the corner is being turned. With the gold and silver stream burdens having been reduced as of January 1, 2024, we look forward to continuing to optimize Mercedes' profitability through 2024 and to testing the many promising exploration targets within the Mercedes property. Our confidence in the potential for the discovery of additional mineralization remains strong as does our commitment to maximize Mercedes' generation of free cash flow."
Bear Creek总裁兼首席执行官埃里克·卡巴表示:“我们非常高兴梅赛德斯为提高产量所做的努力终于取得了成效,与2023年第三季度相比,第四季度的黄金产量增长了47%。2023年第四季度出现了环比改善,最终使2023年12月的黄金产量达到5,198盎司,这是梅赛德斯自2019年4月以来的最高月度黄金产量水平。我们必须回到矿山的基本原理,专注于加强开发、管理成本和将关键人才安置在正确的位置。各方面仍有许多工作要做,但我们相信局面正在转向。自2024年1月1日起,黄金和白银流负担有所减轻,我们期待在2024年之前继续优化梅赛德斯的盈利能力,并在梅赛德斯物业内测试许多有前途的勘探目标。我们对发现更多矿化的潜力仍然充满信心,我们对最大限度地提高梅赛德斯创造自由现金流的承诺也是如此。”
Production and development results for the quarter and year ended December 31, 2023 are as follows:
截至2023年12月31日的季度和年度的生产和开发业绩如下:
Q1 2023 (1) | Q2 2023 (1) | Q3 2023 (1) | Q4 2023 | Full Year 2023 (2) | |
Ore Processed (tonnes) | 134,487 | 125,135 | 126,208 | 135,918 | 521,749 |
Gold recovery (%) | 95.5 | 94.5 | 94.0 | 93.6 | 94.9 |
Gold grade processed (gpt) | 2.91 | 2.42 | 2.40 | 3.30 | 2.77 |
Gold ounces produced | 12,025 | 9,199 | 9,159 | 13,478 | 43,860 |
Silver ounces produced | 40,105 | 39,841 | 34,928 | 52,144 | 167,019 |
Development (meters) | 1,044 | 1,353 | 1,791 | 2,833 | 7,071 |
2023 年第一季 (1) | 2023 年第二季度 (1) | 2023 年第三季度 (1) | 2023 年第四季度 | 2023 年全年 (2) | |
已处理矿石(吨) | 134,487 | 125,135 | 126,208 | 135,918 | 521,749 |
黄金回收率 (%) | 95.5 | 94.5 | 94.0 | 93.6 | 94.9 |
金级加工 (gpt) | 2.91 | 2.42 | 2.40 | 3.30 | 2.77 |
生产的黄金盎司 | 12,025 | 9,199 | 9,159 | 13,478 | 43,860 |
白银盎司产量 | 40,105 | 39,841 | 34,928 | 52,144 | 167,019 |
发展(米) | 1,044 | 1,353 | 1,791 | 2833 | 7,071 |
(1) See Bear Creek news releases dated April 14, July 18 and October 20, 2023
(2) Full year 2023 numbers may not add due to rounding
(1) 查看 Bear Creek 于 2023 年 4 月 14 日、7 月 18 日和 10 月 20 日发布的新闻稿
(2) 由于四舍五入,2023 年全年数字可能不相加
Directly underlying the improvements in production during Q4 2023 were higher gold grades and increased working faces. The gold grade of ore processed increased to 3.30 grams per tonne ("gpt") in Q4 2023 from 2.40 g/t the previous quarter. Development meters steadily increased over the course of the year, reaching a total of 2,833 meters in Q4 202, an increase of 1,042 meters over the previous quarter. Improving development meters, which results in increased working faces, has been a key component of the Company's multi-faceted strategy to improve Mercedes' production.
2023年第四季度产量改善的直接基础是金品位提高和工作面增加。加工的矿石的黄金品位从上一季度的2.40克提高到2023年第四季度的每吨3.30克(“gpt”)。在过去的一年中,开发仪表稳步增长,2022年第四季度总计达到2833米,比上一季度增加了1,042米。改进开发规模,从而增加工作面积,一直是该公司提高梅赛德斯产量的多方面战略的关键组成部分。
Mercedes' 2023 production was comprised of contributions from four main deposit areas: Marianas, San Martin, Diluvio and Lupita. During 2023 Bear Creek changed mining methodologies at the San Martin and Marianas deposits in order to better align the mining method with the geological and structural conditions of each deposit.
梅赛德斯2023年的产量来自四个主要矿区:马里亚纳群岛、圣马丁、迪卢维奥和卢皮塔。2023 年,Bear Creek 改变了圣马丁和马里亚纳矿床的采矿方法,以更好地使采矿方法与每个矿床的地质和结构条件保持一致。
The San Martin deposit became a key contributor to consolidated gold production during Q4 2023 as mining faces progressed into the higher grade heart of the San Martin deposit. During the last quarter, Bear Creek focused on further refining the mining and blasting methods utilized at San Martin to reduce dilution and optimize production while reducing processing costs. San Martin is expected to continue to be a significant contributor to Mercedes' gold production in 2024.
随着采矿业进入圣马丁矿床更高品位的中心地带,圣马丁矿床成为2023年第四季度合并黄金产量的关键贡献者。在上个季度,Bear Creek专注于进一步完善圣马丁岛使用的采矿和爆破方法,以减少稀释和优化生产,同时降低加工成本。预计圣马丁将在2024年继续成为梅赛德斯黄金产量的重要贡献者。
Delineation drilling at the Marianas deposit has returned numerous intersections and zones of high-grade gold mineralization - in some cases with grades up to 20x the average gold grade of the current Marianas reserves (see Bear Creek news releases dated February 22 and August 30, 2023). The deposit, however, is also structurally complex with challenging ground conditions and it has proven difficult to control dilution. As a result, the gold grade per tonne of ore mined from Marianas was lower than planned during the second half of 2023. During the last quarter, Bear Creek commenced a transition from sublevel caving mining methods to a mixture of sublevel stoping and cut and fill, to more effectively reduce dilution and optimize grade. Monitoring of the impact of these changes is ongoing.
马里亚纳矿床的划界钻探已经返回了许多高品位金矿化的交叉点和区域——在某些情况下,其品位高达当前马里亚纳储量平均黄金品位的20倍(见2023年2月22日和8月30日的Bear Creek新闻稿)。但是,该沉积物结构也很复杂,地面条件艰苦,事实证明很难控制稀释。结果,在2023年下半年,从马里亚纳群岛开采的每吨矿石的黄金品位低于计划。在上个季度,Bear Creek开始从次级洞穴采矿方法过渡到混合采矿和采掘和填充,以更有效地减少稀释和优化品位。正在监测这些变化的影响。
On January 1, 2024 reductions to the Mercedes gold and silver stream obligations took effect pursuant to the restructuring agreement (the "Restructuring Agreement") with Sandstorm Gold Ltd. and its subsidiaries (collectively "Sandstorm") announced by the Company on September 28, 2023. The Sandstorm Gold Stream has now been reduced from 600 oz to 275 oz per month and silver deliveries under the Nomad Silver Stream have been fully suspended until April 2028. In combination with the completion of the Nomad Gold Stream on September 27, 2023, the stream burden on Mercedes has been reduced by approximately 78%. The Company expects these stream reductions to positively impact the Company's free cash flow.
根据公司于2023年9月28日宣布的与Sandstorm Gold Ltd.及其子公司(统称 “Sandstorm”)达成的重组协议(“重组协议”),对梅赛德斯黄金和白银流债务的削减于2024年1月1日生效。沙尘暴金流现已从每月600盎司减少到275盎司,Nomad银流下的白银交付已完全暂停至2028年4月。再加上Nomad Gold Stream于2023年9月27日完工,梅赛德斯的直播负担减少了约78%。该公司预计,这些资金流的减少将对公司的自由现金流产生积极影响。
Closing of the Restructuring Agreement, including issuance of a 1% net smelter returns royalty on Corani and payment of up to $10 million in the form of common shares of Bear Creek, is expected in the coming weeks, subject to TSX-V approval. Readers are referred to the Company's news releases September 28 and November 24, 2023 for additional information regarding the Sandstorm Restructuring.
重组协议预计将在未来几周内完成,包括发行净熔炼厂回报Corani的特许权使用费以及以Bear Creek普通股的形式支付高达1000万美元的款项,但须经多伦多证券交易所批准。有关沙尘暴重组的更多信息,请读者参阅公司于2023年9月28日和11月24日发布的新闻稿。
On behalf of the Board of Directors,
Eric Caba
President and Chief Executive Officer
我代表董事会,
埃里克·卡巴
总裁兼首席执行官
For further information contact:
Barbara Henderson - VP Corporate Communications
Direct: 604-628-1111
E-mail: barb@bearcreekmining.com
欲了解更多信息,请联系:
芭芭拉·亨德森-企业传播副总裁
直接:604-628-1111
电子邮件:barb@bearcreekmining.com
Subscribe to Bear Creek Mining news
订阅熊溪矿业新闻
NI 43-101 Disclosure
NI 43-101 披露
Unless otherwise indicated, scientific and technical information in this news release is based on work programs and initiatives conducted under the supervision of, and/or has been reviewed and approved by, Andrew Swarthout, AIPG Certified Professional Geologist, a director of the Company who is a Qualified Person ("QP") as defined in NI 43-101. Additional information related to the Mercedes Mine and the Corani Project, including the Quality Assurance and Quality Control measures applied to the Company's sampling and assaying practices, is available in its Annual Information Form for the year ended December 31, 2022, available on its website and on SEDAR+.
除非另有说明,否则本新闻稿中的科学和技术信息基于在AIPG认证专业地质学家的监督下开展的工作计划和举措,并/或已由其审查和批准。安德鲁·斯沃索特是公司董事,是NI 43-101中定义的合格人士(“QP”)。有关梅赛德斯矿和科拉尼项目的更多信息,包括适用于公司抽样和化验行为的质量保证和质量控制措施,可在截至2022年12月31日的年度信息表中查阅,可在其网站和SEDAR+上查阅。
Cautionary Statement Regarding Forward-Looking Information
关于前瞻性信息的警示声明
This news release contains forward-looking statements regarding: actions being taken to improve development progress and processing grades, reduce dilution, reduce operating costs, discover additional mineralization and attract personnel at the Mercedes mine; the Company's goals and expectations for Mercedes' operations in 2024; the technical and geological appropriateness of various mining methodologies; the intended use of cash resources on exploration drilling and the intended targets of these exploration programs; the Company's financial condition and future cash flow potential; anticipated impacts stemming from the Restructuring Agreement; TSXV approval of the Restructuring Agreement; terms and conditions of the Restructuring Agreement and the Company's ability its obligations thereunder; and the anticipated effect of the Restructuring Agreement on the Company's financial condition. These forward-looking statements are provided as of the date of this news release and reflect predictions, expectations or beliefs regarding future events based on the Company's expectations at the time the statements were made, as well as various assumptions made by and information currently available to them. In making the forward-looking statements included in this news release, the Company has applied several material assumptions, including, but not limited to assumptions related to the Company's planned development and operating activities, business objectives, goals and capabilities, financial resources and liquidity, assumptions related to gold and silver prices, and the expectation that anticipated development and operating results will not differ materially from expectations. On September 30, 2023 the Company had a working capital deficiency of US$66.1 million. There is no guarantee that sufficient funds will be available to meet the Company's financial obligations and the Company may be required to raise funds through the issuance of equity or by other means. There can be no assurances that such funding will be available, and if so, under acceptable terms and conditions. Although management considers these assumptions to be reasonable based on information available to it, they may prove to be incorrect. By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and the risk exists that estimates, forecasts, projections, and other forward-looking statements will not be achieved or that assumptions on which they are based do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important factors could cause the actual outcomes to differ materially from the expectations expressed in them. These risk factors may be generally stated as the risk that the assumptions expressed above do not occur, but may include additional risks as described in the Company's latest Annual Information Form, and other disclosure documents filed by the Company on SEDAR+. The foregoing list of factors that may affect future results is not exhaustive. Investors and others should carefully consider the foregoing factors and other uncertainties and potential events. The Company does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by the Company or on behalf of the Company, except as required by law.
本新闻稿包含有关以下方面的前瞻性陈述:为改善开发进度和加工等级、减少稀释、降低运营成本、发现更多矿化物和吸引梅赛德斯矿山人员而采取的行动;公司对梅赛德斯2024年运营的目标和预期;各种采矿方法的技术和地质适当性;现金资源在勘探钻探中的预期用途以及这些勘探计划的预期目标;公司的财务状况和未来潜在的现金流;重组协议产生的预期影响;多伦多证券交易所对重组协议的批准;重组协议的条款和条件以及公司根据该协议承担的义务的能力;以及重组协议对公司财务状况的预期影响。这些前瞻性陈述是截至本新闻稿发布之日提供的,反映了对未来事件的预测、预期或信念,这些前瞻性陈述基于公司发表声明时的预期,以及他们做出的各种假设和目前可获得的信息。在发表本新闻稿中包含的前瞻性陈述时,公司运用了几项重大假设,包括但不限于与公司计划发展和经营活动、业务目标、目标和能力、财务资源和流动性、与黄金和白银价格相关的假设,以及对预期发展和经营业绩与预期没有重大差异的预期。2023年9月30日,该公司的营运资金赤字为6,610万美元。无法保证有足够的资金来履行公司的财务义务,公司可能需要通过发行股票或其他方式筹集资金。无法保证此类资金会到位,如果有,也无法保证在可接受的条款和条件下提供。尽管根据现有信息,管理层认为这些假设是合理的,但这些假设可能被证明是不正确的。就其本质而言,前瞻性陈述涉及固有的风险和不确定性,包括一般和具体的风险和不确定性,并且存在估计、预测、预测和其他前瞻性陈述无法实现或其所依据的假设无法反映未来经验的风险。我们提醒读者不要过分依赖这些前瞻性陈述,因为许多重要因素可能导致实际结果与其中表达的预期存在重大差异。这些风险因素通常可以说是上述假设不发生的风险,但可能包括公司最新的年度信息表以及公司在SEDAR+上提交的其他披露文件中所述的其他风险。上述可能影响未来业绩的因素清单并不详尽。投资者和其他人应仔细考虑上述因素以及其他不确定性和潜在事件。除非法律要求,否则公司不承诺更新公司或代表公司不时发表的任何前瞻性陈述,无论是书面还是口头的。
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
多伦多证券交易所风险交易所及其监管服务提供商(该术语在多伦多证券交易所风险交易所的政策中定义)均不对本新闻稿的充分性或准确性承担责任。