Ascot Provides Construction Update on the Premier Gold Project

Ascot Provides Construction Update on the Premier Gold Project

Ascot提供Premier Gold项目的施工最新情况
GlobeNewswire ·  02/20 08:57

Figure 1

图 1

Visible gold in quartz vein found in ore drive 6 at Big Missouri
在大密苏里州的6号矿石大道中发现了石英矿脉中的可见金

Figure 2

图 2

TSF overview looking south
TSF 概览向南看

Figure 3

图 3

TSF South and Southeast dams complete
TSF 南大坝和东南大坝完工

Figure 4

图 4

WTP commissioning
WTP 调试

Figure 5

图 5

WTP MBBR system
WTP MBBR 系统

Figure 6

图 6

Mill piping over 90% complete
磨机管道已完成 90% 以上

Figure 7

图 7

Premier underground portal overhead
头顶的顶级地下门户

Figure 8

图 8

Premier underground portal front view
高级地下入口正面视图

Figure 9

图 9

Mill area overview
磨机区域概述

VANCOUVER, British Columbia, Feb. 20, 2024 (GLOBE NEWSWIRE) -- Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) ("Ascot" or the "Company") is pleased to provide a construction update on the Company's Premier Gold Project ("PGP" or the "Project"), located on Nisga'a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. Project construction was 86% complete as of December 31, 2023 (approximately 90% as of January 31, 2024) and is currently nearing completion, with first ore delivery to the mill anticipated by the end of March 2024, and first gold pour anticipated in April.

不列颠哥伦比亚省温哥华,2024年2月20日(GLOBE NEWSWIRE)——阿斯科特资源有限公司(多伦多证券交易所股票代码:AOT;OTCQX:AOTVF)(“阿斯科特” 或 “公司”)很高兴提供该公司位于尼斯的顶级黄金项目(“PGP” 或 “项目”)的最新施工情况ga'a Nation Treaty 位于不列颠哥伦比亚省西北部多产的金三角。截至2023年12月31日,项目建设已完成86%(截至2024年1月31日约为90%),目前已接近完成,预计第一批矿石将于2024年3月底交付该工厂,首次淘金预计将于4月交付。

Derek White, President and CEO, commented, "With Project construction nearing completion and early commissioning underway, we eagerly anticipate progressing to the production and operations phase at the Premier Gold Mine. The Project also accomplished an impressive safety milestone having surpassed one million hours without a lost time incident, along with another quarterly reduction in total recordable incident frequency. We are also proud to have recently closed an additional financing package which we believe is sufficient for the Company to progress from construction to first gold pour, ramp-up, commercial production and steady-state operations. With the gold price still trading near US$2,000 per ounce, this is an opportune time for us to become Canada's next gold producer."

总裁兼首席执行官德里克·怀特评论说: “随着项目建设接近完成,早期调试正在进行中,我们热切期待Premier金矿进入生产和运营阶段。该项目还实现了令人印象深刻的安全里程碑,没有发生损失工时事故超过一百万小时,同时可记录的事故总频率又减少了一个季度。我们还自豪地最近完成了一项额外的一揽子融资计划,我们认为这足以让公司从施工到首次淘金、扩建、商业生产和稳态运营。由于黄金价格仍接近每盎司2,000美元,这是我们成为加拿大下一个黄金生产国的好时机。”

PROJECT CONSTRUCTION

项目施工

Funding for Construction and Ramp-Up
On February 20, 2024, the Company announced the closing of its financing for a total of US$50 million from Sprott Resource Streaming and Royalty Corp. and/or its affiliates ("Sprott Streaming") and Nebari Natural Resources Credit Fund II, LP ("Nebari"), as further described in the Company's news release dated January 22, 2024. Concurrently, the Company closed its previously announced bought deal private placement financing with a syndicate of underwriters co-led by BMO Capital Markets and Desjardins Capital Markets (together, the "Joint Bookrunners"), and including CIBC World Markets Inc., Raymond James Ltd. and Velocity Trade Capital Ltd. (collectively, with the Joint Bookrunners, the "Underwriters"). Under the bought deal financing, the Company issued a total of 65,343,000 common shares of the Company (the "Common Shares") at a price of C$0.44 per Common Share, for gross proceeds of approximately C$29 million, which included the full exercise of the Underwriters' option.

为施工和扩建提供资金
2024年2月20日,该公司宣布完成来自Sprott Resource Streaming and Royalty Corp. 和/或其附属公司(“Sprott Streaming”)和Nebari自然资源信贷基金II,LP(“Nebari”)的总额为5000万美元的融资,该公司在2024年1月22日的新闻稿中对此进行了进一步的描述。同时,该公司与由BMO资本市场和Desjardins资本市场(统称为 “联合账簿管理人”)共同牵头的承销商集团完成了先前宣布的收购交易私募融资,其中包括加拿大帝国商业银行世界市场公司、雷蒙德·詹姆斯有限公司和Velocity Trade Capital Ltd.(合称 “承销商”)。根据收购交易融资,公司以每股普通股0.44加元的价格共发行了公司65,343,000股普通股(“普通股”),总收益约为2900万加元,其中包括承销商全部行使期权。

Construction Progress Key Performance Indicators ("KPI")

施工进度关键绩效指标(“KPI”)

At the end of Q4 2023, overall construction excluding mine development was 86% complete (approximately 90% as of January 31, 2024), compared with 66% complete at the end of Q3 2023. Numerous pre-commissioning activities in the mill have commenced. The Company anticipates introducing first ore into the mill by the end of March 2024, and pouring first gold in April.

截至2023年第四季度末,不包括矿山开发在内的总体施工已完成86%(截至2024年1月31日约为90%),而2023年第三季度末的施工完成率为66%。该工厂的许多预调试活动已经开始。该公司预计,到2024年3月底将第一块矿石引入该工厂,并在4月注入第一批黄金。

Capital costs, including mining costs, incurred as of December 31, 2023 were $292 million. As of December 31, 2023, the remaining project construction capital required to complete construction and achieve the first gold pour is approximately $47 million including mine development costs but excluding certain pre-operating costs and working capital. This implies a total project capital cost of $339 million, which is slightly higher than the most recent total project budget of $334 million as reported last quarter. The increase is mainly attributable to the increase in duration of the earthworks and project indirect costs.

截至2023年12月31日,包括采矿成本在内的资本成本为2.92亿美元。截至2023年12月31日,完成施工和实现首次淘金所需的剩余项目建设资金约为4700万美元,其中包括矿山开发成本,但不包括某些运营前成本和营运资金。这意味着项目总资本成本为3.39亿美元,略高于上个季度公布的最新项目总预算3.34亿美元。增加的主要原因是土方工程持续时间延长和项目间接费用。

The Company ended December 2023 with a cash balance of C$27 million. With the aforementioned additional financing of US$50 million from Sprott Streaming and Nebari Credit Fund II, and the equity financing with gross proceeds of C$29 million, the Company believes it is well financed to complete construction of the Project, progress through the ramp-up phase to commercial production and reach nameplate capacity at the Premier Gold Mine.

截至2023年12月,该公司的现金余额为2700万加元。借助上述来自Sprott Streaming和Nebari Credit Fund II的5000万美元额外融资,以及总收益为2900万加元的股权融资,该公司认为,其资金充足,可以完成该项目的建设,进入商业化生产的准备阶段,并达到Premier金矿的标称产能。

Safety
The Premier Gold Project reached an important safety milestone in Q4 of 2023: one million hours without lost time incidents ("LTI"). By the end of Q4 2023, this figure reached 1,143,029 hours LTI free. The total recordable incident frequency has been reduced yet again from 0.69 at the end of Q3 2023 to 0.52 by the end of Q4 2023. The frequency of total incidents including property damage, first aid injuries, and near misses, was relatively similar to Q3 2023. Reporting activity continues to improve, and the Company will continue to work on proactive safety training and measures to reduce overall incidents on site, especially with pending transition from construction to the operations phase.

安全
Premier Gold 项目在 2023 年第四季度达到了一个重要的安全里程碑:一百万小时没有发生损失工时事件(“LTI”)。到 2023 年第四季度末,这一数字达到了 1,143,029 小时免长期保费。可记录的总事件频率已从2023年第三季度末的0.69再次降低到2023年第四季度末的0.52。包括财产损失、急救伤害和险些失误在内的总事件发生频率与 2023 年第三季度相对相似。报告活动持续改善,公司将继续开展积极的安全培训和措施,以减少现场的总体事故,尤其是在尚待从施工阶段过渡到运营阶段的情况下。

Processing Plant
In Q3 2023, mechanical and electrical work in the mill was substantially advanced. In Q4 2023, work in the mill focused on piping, systems & controls as well as remaining electrical terminations.

加工厂
2023 年第三季度,工厂的机械和电气工作大幅推进。2023 年第四季度,工厂的工作重点是管道、系统和控制装置以及剩余的电气终端。

Piping installation included work inside the mill building and also outside connections to the carbon-in-leach ("CIL") tanks, and cyanide destruction and tailings thickener lines. Piping installation at the mill is over 90% complete. Electrical work progressed on completing terminations and installation of the fire detection system. Instrumentation and controls installations are advancing well. Staged commissioning has started on the Ball and SAG mills, CIL circuit, and cyclone feed pumps. As a part of the commissioning process, both Ball and SAG mills have been energized and rotated. The Ball mill has been loaded with water and successfully rotated for an 8-hour period with no issues. The SAG mill has been rotated for several hours and will undergo water load testing this week.

管道安装包括工厂大楼内部的工程,以及与碳浸出(“CIL”)储罐的外部连接,以及氰化物销毁和尾矿增稠剂管线。工厂的管道安装已完成90%以上。完成火灾探测系统的终端和安装后,电气工作取得了进展。仪表和控制装置进展顺利。球磨机和 SAG 磨机、CIL 回路和旋风进料泵的分阶段调试已经开始。作为调试过程的一部分,球磨机和半自磨机均已通电和旋转。球磨机已经装满了水,成功旋转了 8 小时,没有出现任何问题。SAG磨机已经旋转了几个小时,并将在本周进行水负荷测试。

Tailings Storage Facility ("TSF") Earthworks
With the milder-than-average winter season so far, much work was progressed on the TSF earthworks in Q4 2023 and into early 2024. The South Dam, North Dam, and Southeast Dam have been completed. The minor remaining work is focused on the smaller East Dam and spillway which is expected to complete by mid-March.

尾矿储存设施(“TSF”)土方工程
由于迄今为止冬季节低于平均水平,2023年第四季度至2024年初,TSF土方工程取得了许多进展。南坝、北坝和东南大坝已经建成。剩余的小部分工作集中在较小的东坝和溢洪道上,预计将于3月中旬完工。

Currently the earthworks around the TSF are substantially complete, with some minor works remaining anticipated to be completed by late February.

目前,TSF周围的土方工程已基本完成,一些小型工程预计将于2月下旬完成。

Water Treatment Plant ("WTP")
Commissioning of the WTP components started in Q4 2023, with most areas being commissioned in isolation. Upon the delivery and installation of two transformers and a buffer tank in December 2023, and the 138 kV power connection in January 2024, the WTP is currently undergoing final commissioning. Normal operation of the WTP is anticipated this month. As of the writing of this release, Ascot can report that the High-Density Sludge ("HDS") plant has been successfully commissioned and is awaiting final test results on the effluent water before discharge into the environment is authorized. The Moving Bed Bio-Reactor ("MBBR") is mechanically and electrically complete and media is being loaded into the tanks. The plant will be brought into service mid-March in time for mill start-up.

水处理厂(“WTP”)
WTP 组件的调试于 2023 年第四季度开始,大多数区域是隔离调试的。在2023年12月交付和安装两台变压器和一个缓冲罐,以及在2024年1月交付和安装138千伏电力连接之后,水处理厂目前正在进行最后的调试。预计WTP将于本月正常运行。截至撰写本新闻稿时,阿斯科特可以报告说,高密度污泥(“HDS”)工厂已成功投入使用,正在等待污水的最终测试结果,然后才获准排放到环境中。移动床生物反应器(“MBBR”)的机械和电气均已完成,介质正在装入储罐。该工厂将于3月中旬投入使用,正好赶上工厂的启动。

Site Infrastructure
During Q3 2023, most of the new electrical substation was mechanically completed, and crews completed the 138kV power line to connect to the power grid less than 500 metres away. In Q4 2023, all 138kV lines were pulled and linked up with the BC Hydro grid. Site electrification was originally planned for mid-December, but three new switches were required. Once these were delivered in early January 2024, site powerup on the 138 kV line was completed on January 14, 2024.

站点基础架构
在 2023 年第三季度,大部分新变电站已机械完工,工作人员完成了 138kV 的电力线,连接到不到 500 米外的电网。2023 年第四季度,所有 138 千伏线路都已拉开并与不列颠哥伦比亚水电网相连。场地电气化原计划于12月中旬进行,但需要三台新的开关。这些线路于 2024 年 1 月初交付后,这条 138 千伏线路的现场供电于 2024 年 1 月 14 日完成。

Off-Site Infrastructure
On October 3, 2023, the town council of Stewart, B.C. approved a Temporary Use Permit ("TUP") to install a camp facility in the town to provide additional accommodations for workers at the Project. The TUP is for a three-year term with potential to renew for another three years afterwards. The Company quickly mobilized and installed living quarters with an initial capacity of 76 beds in early December. This has alleviated some of the pressure caused by the extended earthworks schedule.

场外基础设施
2023年10月3日,不列颠哥伦比亚省斯图尔特市议会批准了临时使用许可证(“TUP”),在该镇安装露营设施,为该项目的工作人员提供更多住宿。TUP的任期为三年,之后可能会再续约三年。12月初,公司迅速调动并安装了起居区,初始容量为76张床位。这缓解了土方工程延期所造成的一些压力。

On September 19, 2023, the Company acquired a full-service laboratory facility ("Assay Lab") in Stewart, BC from Seacan Labs Corp. The Assay Lab will be used to perform the testing required by Ascot for mineral exploration, mining operation, and environmental monitoring. During Q4 2023, the Assay Lab was re-commissioned for use and is currently ramping up toward full capacity of 250-300 samples per day with a 24-hour turnaround.

2023年9月19日,该公司从Seacan Labs Corp. 手中收购了位于不列颠哥伦比亚省斯图尔特的全方位服务的实验室设施(“化验实验室”)。该化验实验室将用于进行阿斯科特要求的矿产勘探、采矿作业和环境监测的测试。在 2023 年第四季度,化验实验室重新投入使用,目前正逐步提高到每天 250-300 个样本的满负荷容量,周转时间为 24 小时。

Mine Development
In Q3 2023, the Company's underground mining contractor Procon began their initial mobilization to site and deployed senior project management personnel to coordinate storage and laydown areas ahead of operating crew mobilization.

矿山开发
2023 年第三季度,该公司的地下采矿承包商 Procon 开始了对现场的初步调动,并在动员运营人员之前部署了高级项目管理人员来协调储存和布局区域。

In Q4 2023, once the Big Missouri Portal infrastructure and mine services were re-established, underground development was re-commenced. Procon advanced underground waste and ore development including the decline, which will eventually connect to the Silver Coin deposit. In advance of mill start-up in Q1 2024, Ascot is stockpiling mineralized material from Big Missouri in the Diego pit, ready for processing. Underground development rates at Big Missouri have been gradually improving, with linear advances as high as 16 metres per day achieved, and on average crews are achieving approximately 10 to 12 metres per day currently. Including development in 2022, total underground development at Big Missouri totaled 1,300 metres as of Q4 2023, and approximately 1,650 metres by February 15, 2024.

2023 年第四季度,大密苏里门户基础设施和矿山服务重新建立后,地下开发便重新开始。Procon推进了地下废物和矿石的开发,包括衰退,最终将与银币矿床相连。在工厂于2024年第一季度启动之前,Ascot正在迭戈矿坑中储存来自密苏里大公司的矿化材料,准备加工。大密苏里州的地下开发速度一直在逐步提高,每天的线性进度高达16米,目前工作人员平均每天的开发速度约为10至12米。包括2022年的开发项目在内,截至2023年第四季度,大密苏里州的地下开发总量为1300米,到2024年2月15日约为1,650米。

Recently in ore drive 6 at Big Missouri, the geology team noted an occurrence of coarse, visible gold in a quartz vein (see Figure 1 below). This material was within a geological wireframe approximately on dip with an existing stope shape about 20 metres away. In conjunction with exploration drilling intercepting high-grade gold mineralization outside of existing stope shapes in 2023, this occurrence provides further evidence of the potential for expansion beyond the current mine plan.

最近,在大密苏里州的6号矿石大道中,地质小组注意到石英矿脉中存在粗糙可见的黄金(见下图1)。这种材料大约在倾斜时位于地质线框内,现有的采场形状在大约 20 米外。再加上勘探钻探将在2023年截获现有采场形状之外的高品位金矿化,这进一步证明了在当前采矿计划之外扩张的潜力。

In August 2023, surface work commenced on the new Premier Portal close to the mill. In Q4 2023, Procon continued the portal face preparations including holes for cable bolts and other ground support and began clearing a pad area for service infrastructure including gensets and compressors. The underground decline development started in early December with initial rounds and placement of shotcrete arches similar to what was done at Big Missouri in 2022. Poor ground near surface and extreme cold temperatures slowed advance in January 2024, but conditions have improved in February. Mining development will be advanced down into the Premier deposit for initial mining in the Prew Zone, with ore development anticipated to begin in Q2 2024, and stope production following in Q3 2024. The ramp has been strategically laid out to allow for underground drilling on the Sebakwe Zone in 2024 and will eventually connect a footwall ramp over to the 602 area at the southern end of the Premier deposit.

2023 年 8 月,工厂附近的新的 Premier Portal 开始了地面施工。2023 年第四季度,Procon 继续进行门面准备工作,包括为电缆螺栓和其他地面支撑开孔,并开始为包括发电机组和压缩机在内的服务基础设施清理停机坪区域。地下斜坡开发始于12月初,最初的几轮施工和喷射混凝土拱门的布置与2022年密苏里巨头的施工情况类似。2024年1月,地表附近地面条件不佳,极端寒冷的气温减缓了前进速度,但2月份情况有所改善。采矿开发将向下推进到Premier矿床,用于在Prew区进行初始采矿,矿石开发预计将于2024年第二季度开始,采场生产将在2024年第三季度开始。该坡道的布局经过了战略规划,允许在2024年在Sebakwe区进行地下钻探,并将最终将人行坡道与Premier矿床南端的602区域连接起来。

Recruitment
Recruitment efforts and activity materially increased in the past quarter, as Ascot continues to have many qualified candidates applying for open positions. In January 2024, Ascot representatives attended a recruitment fair in Campbell River, BC, after it was announced that the nearby Myra Falls underground mine and mill was being placed on care & maintenance. During the job fair Ascot conducted two hundred in person and virtual interviews, and the Company has since been able to fill many open positions for skilled trades and operators.

招聘
由于Ascot继续有许多合格的候选人申请空缺职位,招聘工作和活动在过去一个季度中大幅增加。2024年1月,阿斯科特代表参加了在不列颠哥伦比亚省坎贝尔里弗举行的招聘会,此前宣布附近的迈拉瀑布地下矿山和磨坊正在接受保养和维护。在招聘会期间,阿斯科特进行了两百次面对面和虚拟面试,此后,该公司得以为熟练工人和操作员填补了许多空缺职位。

Key senior level roles filled during Q4 2023 and recently include Operations Manager, a second Mine Superintendent, a Senior Mining Engineer, Maintenance Superintendent, Maintenance General Foreman, Mill Operations General Foreman and a number of Supervisors.

2023年第四季度担任的主要高级职位包括运营经理、第二矿山主管、高级采矿工程师、维护总监、维护总监、维护总管、工厂运营总领班和多名主管。

PROJECT PHOTOS

项目照片

Figure 1 – Visible gold in quartz vein found in ore drive 6 at Big Missouri

图 1 — 在密苏里州大道 6 号矿石中发现的石英矿脉中可见的金

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 2 – TSF overview looking south

图 2 — 向南看的 TSF 概述

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 3 – TSF South and Southeast dams complete

图 3 — TSF 南大坝和东南大坝完工

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 4 – WTP commissioning

图 4 — WTP 调试

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 5 – WTP MBBR system

图 5 — WTP MBBR 系统

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 6 – Mill piping over 90% complete

图 6 — 磨机管道已完成 90% 以上

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 7 – Premier underground portal overhead

图 7 — 头顶的顶级地下门户

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 8 – Premier underground portal front view

图 8 — 顶级地下入口正面视图

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Figure 9 – Mill area overview

图 9 — 磨机区域概述

A photo accompanying this announcement is available at

本公告附带的照片可在以下网址获得

Qualified Person

合格人员

John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company's Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.

根据National Instrument 43-101的定义,公司首席运营官约翰·基尔南是公司的合格人员(QP),并已审查并批准了本新闻稿的技术内容。

On behalf of the Board of Directors of Ascot Resources Ltd.
"Derek C. White"
President & CEO

代表阿斯科特资源有限公司董事会
“德里克·C·怀特”
总裁兼首席执行官

For further information contact:

欲了解更多信息,请联系:

David Stewart, P.Eng.
VP, Corporate Development & Shareholder Communications
dstewart@ascotgold.com
778-725-1060 ext. 1024

大卫·斯图尔特,P.Eng
企业发展与股东传播副总裁
dstewart@ascotgold.com
778-725-1060 分机 1024

About Ascot Resources Ltd.

关于阿斯科特资源有限公司

Ascot is a Canadian junior exploration and development company focused on re-starting the past producing Premier Gold Mine, located on Nisga'a Nation Treaty Lands, in British Columbia's prolific Golden Triangle. Ascot shares trade on the TSX under the ticker AOT. Concurrent with progressing the development of Premier, the Company continues to explore its properties for additional high-grade underground resources. Ascot is committed to the safe and responsible development of Premier in collaboration with Nisga'a Nation as outlined in the Benefits Agreement.

Ascot是一家加拿大初级勘探和开发公司,专注于重启过去生产位于尼斯的Premier金矿的历史ga'a Nation Treaty Lands 位于不列颠哥伦比亚省多产的金三角。阿斯科特股票在多伦多证券交易所上市,股票代码为AOT。在推进Premier开发的同时,该公司继续勘探其地产,寻找更多的高品位地下资源。如福利协议所述,阿斯科特致力于与尼斯加民族合作,以安全和负责任的方式发展Premier。

For more information about the Company, please refer to the Company's profile on SEDAR+ at or visit the Company's web site at , or for a virtual tour visit under Ascot Resources.

有关公司的更多信息,请参阅公司在SEDAR+上的简介,或访问公司的网站,或访问Ascot Resources下的虚拟参观。

The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

多伦多证券交易所尚未审查本新闻稿的充分性或准确性,也不承担任何责任。

Cautionary Statement Regarding Forward-Looking Information

关于前瞻性信息的警示声明

All statements and other information contained in this press release about anticipated future events may constitute forward-looking information under Canadian securities laws ("forward-looking statements"). Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeted", "outlook", "on track" and "intend" and statements that an event or result "may", "will", "should", "could", "would" or "might" occur or be achieved and other similar expressions. All statements, other than statements of historical fact, included herein are forward-looking statements, including statements in respect of advancement and development of the PGP and the timing related thereto, the completion of the PGP mine, the production of gold and management's outlook for the remainder of 2024 and beyond. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements, including risks associated with entering into definitive agreements for the transactions described herein; fulfilling the conditions to closing of the transactions described herein, including the receipt of TSX approvals; the business of Ascot; risks related to exploration and potential development of Ascot's projects; business and economic conditions in the mining industry generally; fluctuations in commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; the need for cooperation of government agencies and indigenous groups in the exploration and development of Ascot's properties and the issuance of required permits; the need to obtain additional financing to develop properties and uncertainty as to the availability and terms of future financing; the possibility of delay in exploration or development programs and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; and other risk factors as detailed from time to time in Ascot's filings with Canadian securities regulators, available on Ascot's profile on SEDAR+ at including the Annual Information Form of the Company dated March 23, 2023 in the section entitled "Risk Factors". Forward-looking statements are based on assumptions made with regard to: the estimated costs associated with construction of the Project; the timing of the anticipated start of production at the Project; the ability to maintain throughput and production levels at the PGP mill; the tax rate applicable to the Company; future commodity prices; the grade of mineral resources and mineral reserves; the ability of the Company to convert inferred mineral resources to other categories; the ability of the Company to reduce mining dilution; the ability to reduce capital costs; and exploration plans. Forward-looking statements are based on estimates and opinions of management at the date the statements are made. Although Ascot believes that the expectations reflected in such forward-looking statements and/or information are reasonable, undue reliance should not be placed on forward-looking statements since Ascot can give no assurance that such expectations will prove to be correct. Ascot does not undertake any obligation to update forward-looking statements, other than as required by applicable laws. The forward-looking information contained in this news release is expressly qualified by this cautionary statement.

根据加拿大证券法,本新闻稿中包含的有关未来预期事件的所有陈述和其他信息可能构成前瞻性信息(“前瞻性陈述”)。前瞻性陈述通常使用 “寻求”、“预测”、“相信”、“计划”、“估计”、“期望”、“目标”、“展望”、“走上正轨” 和 “打算” 等词语来识别,以及关于某一事件或结果 “可能”、“将”、“可能”、“将” 或 “可能” 发生或实现的陈述以及其他类似的表述。除历史事实陈述外,此处包含的所有陈述均为前瞻性陈述,包括有关PGP进展和发展及其相关时机、PGP矿竣工、黄金产量以及管理层对2024年剩余时间及以后的展望的陈述。这些陈述涉及已知和未知的风险、不确定性和其他因素,可能导致实际结果或事件与此类前瞻性陈述中的预期存在重大差异,包括与就本文所述交易签订最终协议相关的风险;满足本文所述交易的完成条件,包括获得多伦多证券交易所的批准;阿斯科特的业务;与阿斯科特项目的勘探和潜在开发相关的风险;采矿业的业务和经济状况整个工业;大宗商品价格和货币汇率的波动;与钻探结果解释以及矿床地质、连续性和品位有关的不确定性;政府机构和土著群体在勘探和开发阿斯科特的房产和发放所需许可证方面进行合作的必要性;开发房产需要获得额外融资以及未来融资的可得性和条款的不确定性;勘探或开发计划延迟的可能性以及实现预期计划里程碑的不确定性;及时获得许可证和其他政府批准的不确定性;以及阿斯科特向加拿大证券监管机构提交的文件中不时详述的其他风险因素,可在SEDAR+的Ascot简介中查阅,包括2023年3月23日的公司年度信息表中的标题为 “风险因素” 的部分。前瞻性陈述基于以下方面的假设:与项目建设相关的估计成本;项目预计开始生产的时间安排;维持PGP工厂吞吐量和产量水平的能力;适用于公司的税率;未来大宗商品价格;矿产资源和矿产储量等级;公司将推断的矿产资源转换为其他类别的能力;公司减少采矿稀释的能力;减少资本的能力成本;和勘探计划。前瞻性陈述基于陈述发表之日管理层的估计和意见。尽管阿斯科特认为此类前瞻性陈述和/或信息中反映的预期是合理的,但不应过分依赖前瞻性陈述,因为阿斯科特无法保证此类预期会被证明是正确的。除非适用法律要求,否则Ascot不承担任何更新前瞻性陈述的义务。本警示声明明确限制了本新闻稿中包含的前瞻性信息。


声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发