NexGen Energy Provides Rook I Update, Costs $645 Million More Than Expected

ネクスジェンエナジーはルークIの最新情報を提供し、予想以上に6億4500万ドルかかりました。

Benzinga ·  08/02 09:59

NexGen Energy (NYSE:NXE) has announced that construction costs for its Rook I uranium project in Saskatchewan have soared nearly 70% above the previous estimate from 2021.

The updated capital cost now stands at $1.6 billion, up from around $950 million, showcasing the challenge of domestic uranium production.

"The updated capital cost presents an all-encompassing spend to bring the Rook I project into production based on robust, proven mining and construction methodologies, with a payback period of 12 months," said CEO Leigh Curyer.

Operating costs are projected to nearly double to $10 per pound of uranium oxide (U3O8), compared to $5.4 per pound in the earlier study. Consequently, the project's after-tax net present value has fallen from $5.55 billion to $4.54 billion, and the internal rate of return has dropped from 79% to 45%.

Now Read: EXCLUSIVE – Seabed Mining Company Execs See Industry Developing Regardless Of UN Authority Vote

Regardless of the cost hike, Alexander Pearce, a mining analyst at BMO Capital Markets, remains optimistic.

"Despite an increase in cash cost to about $10 per lb., the asset would remain one of the largest and lowest cost uranium mines globally," he said, per a Bloomberg report.

The Rook I project is in Saskatchewan's Athabasca Basin, known for its rich uranium deposits. It aims to produce 21.7 million pounds of U3O8 annually and has a potential production capacity of up to 30 million pounds. The site holds 3.7 million measured and indicated tons with an average grade of 3.1% U3O8.

The new cost estimates reflect $220 million attributed to price inflation and $425 million from enhanced engineering and procurement activities since March 2021. NexGen is advancing its project engineering, now 45% complete, up from 18% during the feasibility study.

The company's strategy includes incorporating underground tailings management to reduce environmental impact and lower closure costs to an estimated $50 million, significantly less than other uranium mines in Canada. Rook I's unique design integrates progressive reclamation, reducing future liabilities and ensuring a safer, more efficient operation.

The project has already received provincial environmental approval and is awaiting the completion of the federal review process. NexGen is looking to begin construction soon after receiving the green light from federal authorities.

Now Read:

  • Uranium Prices Surge To 16-Year Highs Due To Supply Uncertainties, Rising Demand For AI Data Centers

Benzinga Mining is the bridge between mining companies and retail investors. Reach out to licensing@benzinga.com to get started!

Image: Shutterstock

これらの内容は、情報提供及び投資家教育のためのものであり、いかなる個別株や投資方法を推奨するものではありません。 更に詳しい情報
    コメントする