$GAMUDA (5398.MY)$ has updated that Upper Padas Power Sdn Bhd has signed acceptance of a Letter of Notification from the Energy Commission of Sabah for the development of the Ulu Padas Hydroelectric Project with an installed capacity of 187.5 MW.
$GAMUDA (5398.MY)$ 據報道,Upper Padas Power Sdn Bhd已經簽署了沙巴能源委員會發出的UlU Padas水力發電項目的通知書接受信,並計劃開發187.5兆瓦的裝機容量。
The Project will be developed by UPPSB, a wholly owned subsidiary of UPP Holdings Sdn Bhd ("JV Company") whereby a Joint Venture Agreement was entered into on 30 October 2023. The JVA became effective as of 14 August 2024 with Gamuda holding a 45% indirect interest in UPPSB via the JV Company.
該項目將由UPPSb開發,UPP Holdings Sdn Bhd(「聯營公司」)的全資子公司,於2023年10月30日簽署了合資協議。合資協議於2024年8月14日生效,Gamuda通過聯營公司間接持有UPPSb的45%的股權。
The Project involves the construction of a dam located in Tenom and Sipitang districts of Sabah and will deliver an average of 1,052GWh of clean energy per annum. Once completed, the Project is expected to generate revenue exceeding
RM400 million per annum.
該項目涉及修建位於沙巴州的Tenom和Sipitang地區的一座大壩,並每年提供1,052GWh的清潔能源。項目完成後,預計營業收入將超過
RM40000萬人民幣。
Construction is estimated to be completed within six years with Scheduled Commercial Operation Date ("SCOD") to be on or before 31 December 2030.
預計施工將在六年內完成,並計劃於2030年12月31日或之前達到商業運營日期(「SCOD」)。
In addition, as a condition of the LoN, UPPSB is to propose and implement a floating solar solution integrated with the Project, which is to achieve SCOD before 31 December 2031.
此外,作爲LoN的條件,UPPSb將提出並實施與項目集成的浮動太陽能解決方案,以在2031年12月31日之前達到SCOD。
Under the Sabah Energy Roadmap and Master Plan 2040, Sabah's dependable capacity of electricity is approximately 1,180 MW as of 2021, of which less than 105 MW is from renewable energy sources.
根據沙巴能源路線圖和2040年總體規劃,截至2021年,沙巴的可靠電力容量約爲1,180兆瓦,其中不到105兆瓦來自可再生能源。
Gamuda said the funding for the Project will be from a mixture of internally generated funds and borrowings with minimum debt to equity ratio of 80:20.